Mabus v. General Dynamics C4 Systems, Inc.

633 F.3d 1356, 2011 WL 343960
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 4, 2011
Docket2009-1550, 2009-1560
StatusPublished
Cited by22 cases

This text of 633 F.3d 1356 (Mabus v. General Dynamics C4 Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mabus v. General Dynamics C4 Systems, Inc., 633 F.3d 1356, 2011 WL 343960 (Fed. Cir. 2011).

Opinions

Opinion for the court filed by Circuit Judge MOORE.

Dissenting opinion filed by Circuit Judge NEWMAN.

MOORE, Circuit Judge.

Appellant Raymond E. Mabus, Secretary of the Navy (Navy) appeals the final judgment of the Armed Services Board of Contract Appeals (Board) holding that General Dynamics C4 Systems, Inc. (General Dynamics) is entitled to damages. Because the Board abused its discretion by [1358]*1358denying the Navy’s equitable estoppel defense, we reverse.

Background

On September 4,1998, the Navy entered into a contract with Motorola, Inc. (Motorola) for the development and delivery of Digital Modular Radios. A Digital Modular Radio (radio) is also called a “software radio” and allows a single computer to interface with a number of different radio signals that would typically each require its own receiving device. This was an indefinite delivery/indefinite quantity (ID/IQ) contract meaning that the Navy, after purchasing a contractual minimum, could order additional radios at the contract price. The contract included an “Ordering Clause” that stated:

If mailed, a delivery order or task order is considered “issued” when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the schedule.

J.A. 105. The schedule did not authorize electronic transmission of orders.

The initial phase of the contract involved two contractors, Motorola and a competitor. The government issued its initial delivery order (DO) by mail on September 8, 1998. This DO satisfied the government’s ordering obligation under the contract. The contract included five option years. Prior to exercising Option I, the Navy performed a “down-select,” choosing Motorola. As part of this down-select, the parties entered into a bilateral modification that specified the criteria for the down-select as well as anticipated quantities that the government would require under each option. This modification also extended the times for exercising Options I-IV. The modification did not extend the time for exercising Option V, so the last date for issuing any orders would be September 30, 2003. Prior to down-select, the Navy issued D02 and D03. It is unknown whether the Navy sent these by mail or email. On November 30, 1999, the Navy issued D04 via email.

As part of the down-select process, Motorola issued a revised proposal for lower prices throughout the option years. Motorola prevailed in the down-select and the Navy exercised Option I on February 1, 2000. The Navy then issued D05 through D07 via email.

Prior to exercising Option II, the parties entered negotiations to modify the terms of the contract. The Navy agreed to extend the higher prices of Option I through Option II. This was advantageous to Motorola who had been losing money on the contract and stood to lose more under the Option II prices. Following this agreement, the Navy exercised Option II on March 28, 2000. The Navy then issued D08 via email.

On September 28, 2001, General Dynamics assumed the contract from Motorola with knowledge that it was not profitable. Appeal of Gen. Dynamics C4 Sys., Inc., ASBCA No. 54988, 09-2 BCA ¶ 34150, 2009 WL 1464387 at 11 (Board Opinion). Although the Navy exercised Option III, it did not order any radios under that option. In 2002 and early 2003, the parties entered negotiations and General Dynamics asked the Navy to extend Option I pricing. The parties entered a bilateral modification on September 27, 2002, which did not extend Option I pricing, but did require the Navy to pay higher prices for repair parts. This modification also exercised Option IV. The Navy then issued D015 for a number of radios via email.

For reasons that are not entirely clear, the parties continued to negotiate whether to extend Option I pricing after the exercise of Option IV. In addition to extending Option I pricing, General Dynamics also sought to delete from the contract the [1359]*1359“HF waveform,” an apparently costly waveform that the Navy had not yet ordered under the contract. No contract modification resulted from these negotiations and the Navy ordered HF waveforms via email as D016. Board Opinion at 6. General Dynamics was “a little shocked” that the government ordered these HF waveforms because it believed that there was an agreement to delete this contract term. Id. However, the parties never executed a modification to this effect and the Navy demanded delivery of the HF waveforms stating that “the contract, as written, remains in full force and effect.” Id.

On September 10, 2003, the Navy exercised Option V. Id. at 7. The Navy then issued DOs 18-20 and 22-29 via email under the Option V pricing. On September 30, 2003, the deadline for ordering under the contract, General Dynamics contacted the Navy to inquire about D021. The Navy confirmed that it “skipped” that DO and that it would not issue it.

General Dynamics did not want to accept DOs 18-20 and 22-29 at Option V prices. Id. Sometime in September or early October 2003, General Dynamics personnel began discussing ways to avoid filling these orders. Id. At this time, General Dynamics reviewed the contract and determined that the Ordering Clause prohibited emailing DOs unless authorized by the schedule and that the accompanying schedule did not allow for email delivery of DOs. Id. at 7-8. General Dynamics sent a letter to the Navy on October 6, 2003, stating that General Dynamics rejected DOs 17-20 and 22-29. The Navy responded that it considered the DOs valid and demanded that General Dynamics deliver. Id. at 9. General Dynamics argued that the DOs were not valid and construed the Navy’s demand as direction to proceed under the Changes Clause of the contract. The Changes Clause requires a contractor to go forward with work even if it disputes the propriety of the Navy’s request. Id. at 3^.

Following the Navy’s demand for performance, General Dynamics filed a claim with the contracting officer. The contracting officer denied this claim. General Dynamics appealed to the Board. The Board ruled that the Navy failed to send the disputed DOs in strict compliance with the contract, and they were thus invalid. The Board further rejected the Navy’s arguments regarding waiver and estoppel. The Navy appeals; we have jurisdiction under 28 U.S.C. § 1295(a)(10).

Discussion

We review the Board’s legal determinations de novo. England v. Sherman R. Smoot Corp., 388 F.3d 844, 848 (Fed.Cir.2004). We will not set aside a factual determination of the Board “unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.” 41 U.S.C. § 609(b). We review the Board’s determination on equitable estoppel for abuse of discretion. A.C. Aukerman Co. v. R.L. Chaides Constr. Co., 960 F.2d 1020, 1028 (Fed.Cir.1992) (en banc).

Equitable estoppel requires:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JORDAN v. United States
Federal Claims, 2025
In Re AGADIA SYSTEMS INC.
Federal Circuit, 2025
Dynamic Systems Technology, Inc.
Armed Services Board of Contract Appeals, 2023
ECC International, LLC
Armed Services Board of Contract Appeals, 2020
Baha v. United States
Federal Claims, 2019
TranLogistics LLC
Armed Services Board of Contract Appeals, 2018
Dis Vintage, LLC v. United States
2018 CIT 104 (Court of International Trade, 2018)
Parwan Group Company
Armed Services Board of Contract Appeals, 2018
Navajo Nation v. Department of the Interior
174 F. Supp. 3d 161 (District of Columbia, 2016)
Coast Professional, Inc. v. United States
120 Fed. Cl. 727 (Federal Claims, 2015)
Allen Engineering Contractor, Inc. v. United States
115 Fed. Cl. 457 (Federal Claims, 2014)
Northrop Grumman Corporation
Armed Services Board of Contract Appeals, 2014
Chapman Law Firm, LPA v. United States
113 Fed. Cl. 555 (Federal Claims, 2013)
P & K Contracting, Inc. v. United States
108 Fed. Cl. 380 (Federal Claims, 2012)
SUFI Network Services, Inc. v. United States
108 Fed. Cl. 287 (Federal Claims, 2012)
System Planning Corp. v. United States
107 Fed. Cl. 710 (Federal Claims, 2012)
City of North Oaks v. Sarpal
797 N.W.2d 18 (Supreme Court of Minnesota, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
633 F.3d 1356, 2011 WL 343960, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mabus-v-general-dynamics-c4-systems-inc-cafc-2011.