Jana, Inc. v. The United States

936 F.2d 1265, 1991 WL 101430
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 30, 1991
Docket91-5012
StatusPublished
Cited by58 cases

This text of 936 F.2d 1265 (Jana, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jana, Inc. v. The United States, 936 F.2d 1265, 1991 WL 101430 (Fed. Cir. 1991).

Opinion

MICHEL, Circuit Judge.

The United States appeals the judgment of the United States Claims Court holding that JANA, Inc. did not overcharge the government on two contracts, and dismissing the government’s counterclaim for repayment. JANA, Inc. v. United States, No. 650-87 C (Cl.Ct. Aug. 23, 1990). Because the Claims Court’s construction of the contracts’ records retention requirements was incorrect, and because it is uncontested that JANA could not produce records supporting the disputed billings as required by the contracts, we reverse and remand, directing entry of judgment for the government on its counterclaim.

BACKGROUND

In October 1975, JANA was awarded two technical publication contracts with the United States Navy. These contracts were so-called “time and materials” contracts— that is, the contract price was to be determined largely by multiplying the number of employee hours billed by JANA against fixed hourly rates stated in the contracts. The final contract price was to be determined after the work was completed and, if the government so elected, an audit was performed.

JANA’s work on the contracts was completed in late 1980, and the Navy made its last payment in early 1981. Over two years later, in July 1983, the Defense Contract Audit Agency (DCAA) began a routine audit of the contracts, at the request of the Navy. The audit showed large discrepancies between the number of hours for which JANA had billed, and been paid by, the government, and the number of hours actually worked, according to JANA’s own time records. The DCAA issued audit reports for both contracts characterizing charges of $343,622 and $220,-164, for the unsubstantiated hours on each contract, as overpayments.

Based on the audit reports, the contracting officer issued a final decision in December 1986, finding that JANA had overcharged the government on the two contracts, and demanding repayment. Pursuant to the Contract Disputes Act, JANA contested the contracting officer’s decision in the Claims Court. 41 U.S.C. § 609(a) (1988). The government counterclaimed for the alleged overpayments.

After denying cross-motions by the parties for summary judgment, the Claims Court tried the case and issued an oral bench ruling on August 10, 1990. The court found that the government had proven “beyond a reasonable doubt” that JANA could not produce records substantiating all the invoices it submitted to the government, but nevertheless found, in light of its construction of the contract provisions regarding JANA’s duty to retain records, that the government had not proved that JANA had been overpaid. Bench Ruling, Joint Appendix (Jt.App.) at 5, 16. The court therefore entered judgment in favor of JANA. JANA, Inc. v. United States, No. 650-87 C (Cl.Ct. Aug. 23, 1990). The government appeals.

We have jurisdiction over the government’s appeal pursuant to 28 U.S.C. § 1295(a)(3) (1988).

*1267 DISCUSSION

I

The discrepancy at issue in this case concerns the various types of documents used in JANA’s method of recording and billing the time its employees worked on these two government contracts. Each JANA employee filled out “time cards,” listing time worked on various jobs. The time each employee recorded for a given job — such as one of the contracts at issue here — was then transferred to a “labor recap sheet.” The labor recap sheets for each of these contracts thus showed the time each employee spent working on just that contract during a given month. The time recorded on the labor recap sheets was then converted to a dollar value and recorded on the “job control register.” Finally, the contents of the job control register were transferred to the “invoices” sent to the government for payment under each contract.

The DCAA audit of the two contracts at issue here detected that the labor recap sheets listed fewer hours than those reflected in labor costs on the job control register and billed to the government on invoices. In other words, the billings were not fully backed up by information from the labor recap sheets showing that the hours invoiced were actually worked.

It is undisputed, and indeed the trial court found “beyond a reasonable doubt,” that neither at the time of trial, nor at the time of the audit, could JANA produce records substantiating all the charges it invoiced under the two contracts. The initial question we must consider is whether this entitles the government to repayment. To determine this, we must look to the interpretation of the contracts at issue.

Both of these time and materials contracts contain a “Submission of Invoices” clause, which provides that the contractor would only be paid for hours that can be substantiated:

Invoice submissions for payment shall be made based on the actual hours worked_ The contractor may be required to justify invoice billings as the Government reserves the right to audit task efforts, employee time cards, etc. Such reviews will normally be conducted by the task ordering officer or, if requested by Naval Air Technical Services Facility, the Defense Contract Audit Agency.

Jt.App. at 98 (emphasis added in part). The contract itself thus put JANA on notice that no payments were final until the contracts had been audited, or the time for auditing had expired, and that at least until then, JANA could be required to produce records substantiating its invoices.

Both of the contracts also contained the “Audit by Department of Defense” clause required by the Armed Services Procurement Regulations (ASPR) 1 in effect at the time the contracts were awarded, providing:

(a) General. The Contracting Officer or his representatives shall have the audit and inspection rights described in the applicable paragraphs ... below.
(b) Examination of Costs. If this is a cost reimbursement type, incentive, time and materials, labor hour, or price rede-terminable contract, or any combination thereof, the Contractor shall maintain, and the Contracting Officer or his representatives shall have the right to examine books, records, documents, and other evidence and accounting procedures and practices, sufficient to reflect properly all direct and indirect costs of whatever nature claimed to have been incurred and anticipated to be incurred for the performance of this contract.
if: íN H5 Jjs
*1268 (e) Availability. The materials described in (b) ... above shall be made available at the office of the Contractor, at all reasonable times, for inspection, audit, or reproduction, until the expiration of three years from the date of final payment under this contract or such lesser time specified in Appendix M....

ASPR H 7-104.41, codified at 32 C.F.R. Vol. II (1975) (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doubleshot, Inc.
Armed Services Board of Contract Appeals, 2022
Pds Consultants, Inc. v. United States
132 Fed. Cl. 117 (Federal Claims, 2017)
InSpace 21 LLC v. United States
128 Fed. Cl. 69 (Federal Claims, 2016)
National Telecommuting Institute, Inc. v. United States
123 Fed. Cl. 595 (Federal Claims, 2015)
Northrop Grumman Corporation
Armed Services Board of Contract Appeals, 2014
Reilly v. United States
104 Fed. Cl. 69 (Federal Claims, 2012)
Carter v. United States
98 Fed. Cl. 632 (Federal Claims, 2011)
Mabus v. General Dynamics C4 Systems, Inc.
633 F.3d 1356 (Federal Circuit, 2011)
Council of Athabascan Tribal Governments v. United States
693 F. Supp. 2d 116 (District of Columbia, 2010)
Global Computer Enterprises, Inc. v. United States
88 Fed. Cl. 350 (Federal Claims, 2009)
Land Grantors in Henderson, Union v. United States
86 Fed. Cl. 35 (Federal Claims, 2009)
Data Computer Corp. of America v. United States
80 Fed. Cl. 606 (Federal Claims, 2008)
Heritage of America, LLC v. United States
77 Fed. Cl. 66 (Federal Claims, 2007)
Six v. United States
71 Fed. Cl. 671 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
936 F.2d 1265, 1991 WL 101430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jana-inc-v-the-united-states-cafc-1991.