Doubleshot, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 19, 2022
DocketASBCA No. 61691
StatusPublished

This text of Doubleshot, Inc. (Doubleshot, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doubleshot, Inc., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Doubleshot, Inc. ) ASBCA No. 61691 ) Under Contract No. N6835-06-C-0416 et al. )

APPEARANCE FOR THE APPELLANT: Mr. Alan Shulman CEO

APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq. DCMA Chief Trial Attorney Srikanti Schaffner, Esq. Trial Attorney Defense Contract Management Agency Carson, CA

OPINION BY ADMINISTRATIVE JUDGE O’CONNELL ON APPELLANT’S MOTION FOR PARTIAL SUMMARY JUDGMENT

Appellant, Doubleshot, Inc. (Doubleshot), has filed a motion for partial summary judgment contending that it is entitled to judgment as a matter of law on the government’s claim to the extent that it is based on (1) missing or unsigned time cards and (2) disallowed independent research and development and bid and proposal costs. The Board grants Doubleshot’s motion with respect to time cards but denies it with respect to independent research and development and bid and proposal costs.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The following facts are undisputed or uncontroverted, except as noted below with respect to the date Doubleshot produced its general ledger. The government has not disputed any of Doubleshot’s proposed material facts not in dispute (AMF). This is Doubleshot’s second motion for summary judgment. Doubleshot, Inc., ASBCA No. 61691, 20-1 BCA ¶ 37,677 (Doubleshot I) recon. denied, 20-1 BCA ¶ 37,741. We restate the facts only to the extent necessary in this opinion. 1. As related in Doubleshot I, the parties entered into the following four contracts:

Naval Air Warfare Center Contract No. N68335-06-C-0416 (the 416 contract) dated September 14, 2006 (R4, tab 1);

U.S. Army Tank-automotive and Armaments Command (TACOM) Contract No. W56HZV-07-C-0295 (the 295 contract) dated March 22, 2007 (R4, tab 2);

Office of Naval Research Contract No. N00014-07-C-0386 (the 386 contract) dated June 13, 2007 (R4, tab 5); and

Office of Naval Research Contract No. N00014-08-C-0497 (the 497 contract) dated September 11, 2008 (R4, tab 11).

Doubleshot I, 20-1 BCA ¶ 37,677 at 182,902.

2. The contracts were all at least in part cost-plus-fixed-fee and incorporated Federal Acquisition Regulation (FAR) clause 52.216-7, ALLOWABLE COST AND PAYMENT (DEC 2002) and FAR 52.215-2, AUDIT AND RECORDS – NEGOTIATION (JUN 1999) (AMF ¶ 2; R4, tab 1 at 18; tab 2 at 16; tab 5 at 12; tab 11 at 12-13 1). The 416 contract incorporated DFARS 252.215-7002 COST ESTIMATING SYSTEM REQUIREMENTS (OCT 1998) 2 (R4, tab 1 at 19). (The 295 contract incorporated DFARS 252.242-7004, MATERIAL MANAGEMENT AND ACCOUNTING SYSTEM (NOV 2005) (R4, tab 2 at 17).

Time Cards – Missing and Unsigned

3. The larger of the two issues in the government’s claim relates to Doubleshot’s time cards. The following events are relevant to the contentions raised in Doubleshot’s motion.

4. On January 28, 2010, the Defense Contract Audit Agency (DCAA) visited Doubleshot’s office and conducted an examination of Doubleshot’s accounting system. As described in Doubleshot I, DCAA found the accounting system to be “non-existent.” Doubleshot I, 20-1 BCA ¶ 37,677 at 182,903. DCAA detailed the issues it had identified in what it called a “Flash Report” that it issued more than 15 months later, on April 29, 2011. Id. (citing R4, tab 25 at 3).

1 R4 citations are to the .pdf page of the electronic file. 2 Both the 386 and 497 contracts incorporate this clause, but then state that the clause is only applicable if the contract was awarded based on certified cost or pricing data, which is not the case for either contract (R4, tab 5 at 16, tab 11 at 17) 2 5. By the time these events had occurred, the relevant Doubleshot fiscal years (FYs) had ended. Doubleshot FY 2009 ended on February 28, 2009. Doubleshot FY 2010 ended on February 28, 2010. Doubleshot failed to submit final indirect cost rate proposals (ICRPs) within six months of each of those dates as required by the Allowable Cost and Payment clause, FAR 52.216-7(d)(2)(i). Id. at 182,904; (AMF ¶ 5) Ultimately, Doubleshot submitted revised ICRPs for both FY 2009 and FY 2010 on September 25, 2013 (R4, tab 28 at 25, tab 29 at 31).

6. More than two years later, on November 30, 2015, DCAA notified Doubleshot that it would conduct an audit of its FY 2009 and 2010 proposals (AMF ¶ 6). According to the government, Doubleshot first produced its general ledgers on December 29, 2015 during that audit (gov’t statement of genuine issues of material fact (GSMF) ¶ 8). Doubleshot disputes this, contending that it produced the general ledgers on September 25, 2013, when it submitted the ICRPs (app. reply at 11).

7. DCAA issued an audit report on June 12, 2017 that questioned various costs (R4, tab 30). The contracting officer (CO) adopted DCAA’s calculation and issued a final decision on June 8, 2018, for a government claim of $804,979, which included $633,397 arising from employee time cards (R4, tab 35; AMF ¶ 7).

8. As explained in greater detail in the DCAA audit report, the $633,397 included a total of $479,852 3 in direct and indirect costs in FY 2009 and 2010 “due to lack of time cards,” that is, time cards that Doubleshot could not produce, although it was able to demonstrate that it had paid the relevant employees. For both issues related to time cards, the audit and final decision relied upon FAR 31.201-2(d), which provides:

A contractor is responsible for accounting for costs appropriately and for maintaining records, including supporting documentation, adequate to demonstrate that costs claimed have been incurred, are allocable to the contract, and comply with applicable cost principles in this subpart and agency supplements. The contracting officer may disallow all or part of a claimed cost that is inadequately supported.

(AMF ¶ 7; R4, tab 30 at 15-16; R4, tab 35 at 3-4).

3 R4, tab 30 at 15-16 ($162,432 + $79,213 + $158,411 + $79,796 = $479,852) 3 9. The claim also included $153,545 4 in direct and indirect costs in FY 2009 and 2010 relating to what the audit described as “unsupported labor transactions due to unsigned time cards by employees/managers and time cards/labor distribution schedules which did not reconcile to posted general ledger hours.” (R4, tab 30 at 16) But the audit once again acknowledged that Doubleshot had provided documents demonstrating that it had paid the employees. (R4, tab 30 at 15-16, tab 35 at 3-4)

Independent Research & Development/Bid & Proposal (IR&D/B&P)

10. The final decision states that the CO had disallowed “inadequately supported IR&D/B&P costs, including allocable fringe and overhead costs in that Doubleshot, Inc. did not segregate/accumulate IR&D costs by project/job no.. There was no authorization of the IR&D activity, and no delineation of the IR&D/B&P proposed statement of work by project/job number.” (R4, tab 35 at 4). The parties agree that the amount in dispute is $202,321 (AMF ¶ 8).

11. The Board concludes that this issue has not been developed adequately in Doubleshot’s motion, which contains a single sentence in its proposed undisputed facts about this issue, and just over one page of argument. It appears to the Board that there are material facts in dispute.

12. For example, Doubleshot contends in the argument section of its brief that “there is no cost impact of B&P or IR&D classifications” and that the costs of individual IR&D or B&P efforts were not material and, as a result, its accounting method was appropriate (app. mot. at 5). The government disputes the assertion that the costs were not material. In addition to calculating a cost impact of $202,321, the government contends that Doubleshot failed to produce sufficient documentation during the audit to reach such a conclusion (gov’t resp. at 18).

13. Doubleshot filed a timely appeal on July 12, 2018.

DECISION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Jana, Inc. v. The United States
936 F.2d 1265 (Federal Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Doubleshot, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/doubleshot-inc-asbca-2022.