KMS Fusion, Inc. v. United States

42 Cont. Cas. Fed. 77,211, 39 Fed. Cl. 593, 1997 U.S. Claims LEXIS 261, 1997 WL 719911
CourtUnited States Court of Federal Claims
DecidedNovember 19, 1997
DocketNo. 95-46C
StatusPublished
Cited by26 cases

This text of 42 Cont. Cas. Fed. 77,211 (KMS Fusion, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KMS Fusion, Inc. v. United States, 42 Cont. Cas. Fed. 77,211, 39 Fed. Cl. 593, 1997 U.S. Claims LEXIS 261, 1997 WL 719911 (uscfc 1997).

Opinion

OPINION

MILLER, Judge.

This case is before the court on an application for attorneys’ fees and expenses pursuant to the Equal Access to Justice Act (the “EAJA”), 28 U.S.C. § 2412 (1994).

[596]*596FACTS

The dispute preceding this EAJA application was resolved via a bench ruling after trial issued by the court pursuant to RCFC 52(a). In its ruling the court noted that the background and facts in the underlying litigation were strikingly similar to those addressed by the court in its published opinion in KMS Fusion, Inc. v. United States, 36 Fed. Cl. 68 (1996), aff'd, 108 F.3d 1393 (1997) (Table).1 Accordingly, for the purpose of placing this EAJA application in the proper context, a summary of only those facts and background issues relevant to an award of attorneys’ fees is provided.

The United States Department of Energy (“DOE”) awarded Contract No. DE-AC08-87DP10560 to KMS Fusion, Inc. (“plaintiff’), on May 1, 1987.2 This was a level-of-effort contract with a three-year duration and two separate one-year options. Plaintiff was to be compensated on a cost-plus-fix-fee basis.

The contract was for the purpose of research and development in support of DOE’s Inertial Confinement Fusion Program. Much of the research and development centered around projects involving the radioactive isotope of hydrogen known as tritium. Because of its high level of radioactivity, tritium is regulated by the Nuclear Regulatory Commission.

By January 1990 DOE had determined that its needs with respect to the Inertial Confinement Fusion Program had changed. DOE planned to recompete plaintiffs contract that was set to expire on April 30,1990. However, DOE determined that if it were to send out a request for proposals, the process of finding a new contractor would extend well beyond the April 30,1990 termination date of plaintiff’s contract. Thereafter, DOE and plaintiff entered into negotiations to modify the extant contract to ensure an efficient transition and to avoid a period during which no work was performed on the Inertial Confinement Fusion Program.

The parties negotiated successfully Modification A022 (“Mod 22”) on April 30, 1990. Under the terms of Mod 22, DOE obtained two options whereby it could increase unilaterally the level of effort and limitation of funds clauses. Option A permitted DOE to extend performance through December 31, 1990. Option B extended performance until March 31, 1991. Upon reaching agreement on Mod 22, DOE invoked Option A and extended the contract with plaintiff through December 31,1990.

DOE also embarked upon its plan to re-compete the contract when it issued a request for proposals on August 2, 1990. By December 27, 1990, plaintiff had received notification that the new contract was being awarded to General Atomics, Inc. On December 28,1990, DOE informed plaintiff that it was invoking Option B to Mod 22 and extending the original contract until March 31,1991.

DOE subsequently directed plaintiff to develop a close-out plan through which plaintiff would articulate the manner in which it would return all DOE property and transfer any tritium in its possession to the new contractor. On January 10, 1991, plaintiff, pursuant to Clause 37(b) of the contract, informed DOE of a limitation of costs (“LOC”) and funds (“LOF”) problem in that it had exceeded 75% of the funds allocated to the contract. Moreover, plaintiff ceased all performance of the contract. The parties then entered into negotiations that culminated in Modification A035 (“Mod 35”), signed on August 8, 1991. In accordance with Mod 35, contract performance was extended through December 31,1991.

Pursuant to the regulations governing cost-plus-fix-fee contracts, plaintiff was required to submit annual proposals detailing costs incurred. Each proposal would be audited by the Defense Contract Audit Agency (the “DCAA”). Plaintiff submitted reports claiming that it was owed $3,169,294.00. [597]*597However, after auditing plaintiffs reports for 1987 through 1991, the DCAA determined on March 7, 1996, that plaintiff was required to reimburse DOE $5,808,326.00. Accordingly, DOE’s contracting officer denied plaintiffs claim on January 3, 1995, and asserted that plaintiff was required to reimburse DOE $5,808,326.00.

Plaintiff subsequently filed suit in the United States Court of Federal Claims appealing the denial of both the $3,169,294.00 claim and the $5,808,326.00 claim. At the outset of trial, defendant conceded an issue involving environmental remediation at the Chemform, Inc. (Chemform), site utilized by plaintiff. In its bench ruling, the court found that plaintiff was entitled to recover $1,621,-413.00 plus interest.3 The bench ruling delineated five discrete issues: 1) waiver of the LOC/LOF clauses; 2) general and accounting (“G & A”); 3) indirect labor costs; 4) severance pay; and 5) advertising. The court’s judgment in favor of plaintiff was offset by the $2 million partial settlement that plaintiff had obtained from DOE in state court litigation, as previously agreed. After prevailing on some of its claims in the underlying lawsuit, plaintiff filed this application seeking $163,164.90 in attorneys’ fees and $52,676.13 in expenses.4

DISCUSSION

“The purpose of the EAJA is ‘to eliminate legal expenses as a barrier to challenges of unreasonable government action.’ ” Community Heating & Plumbing Co. v. Garrett, 2 F.3d 1143, 1145 (Fed.Cir.1993) (quoting Ellis v. United States, 711 F.2d 1571, 1576 (Fed.Cir.1983)). The EAJA serves as “a specific waiver of sovereign immunity to enable persons who prevail in certain suits brought against the government to an award of attorney fees incurred in challenging the government’s action in court.” Chiu v. United States, 948 F.2d 711, 714 (Fed.Cir.1991). As with any waiver of sovereign immunity, the EAJA is to be construed strictly. See Ruckelshaus v. Sierra Club, 463 U.S. 680, 685, 103 S.Ct. 3274, 3277-78, 77 L.Ed.2d 938 (1983).

The EAJA requires “1) that the claimant be a ‘prevailing party’; 2) that the Government position was not ‘substantially justified’; 3) that no ‘special circumstances make an award unjust’; and 4) ... that any fee application be submitted ... within 30 days of final judgment ... and be supported by an itemized statement.” Commissioner, INS v. Jean, 496 U.S. 154, 158, 110 S.Ct. 2316, 2319, 110 L.Ed.2d 134 (1990). Once a litigant files a fee application, the burden is on the Government to demonstrate that its position was substantially justified. See Doty v. United States, 71 F.3d 384, 385 (Fed. Cir.1995) (citing Gavette v. OPM, 808 F.2d 1456, 1465-66 (Fed.Cir.1986) (en banc)); Bailey v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wollman v. United States
Federal Claims, 2015
Ulysses, Inc. v. United States
117 Fed. Cl. 772 (Federal Claims, 2014)
Mann v. United States
Federal Claims, 2014
Prochazka v. United States
116 Fed. Cl. 444 (Federal Claims, 2014)
Metropolitan Van & Storage, Inc. v. United States
101 Fed. Cl. 173 (Federal Claims, 2011)
Greenhill v. United States
96 Fed. Cl. 771 (Federal Claims, 2011)
United Partition Systems, Inc. v. United States
95 Fed. Cl. 42 (Federal Claims, 2010)
Precision Pine & Timber, Inc. v. United States
83 Fed. Cl. 544 (Federal Claims, 2008)
JGB Enterprises, Inc. v. United States
83 Fed. Cl. 20 (Federal Claims, 2008)
Geo-Seis Helicopters, Inc. v. United States
79 Fed. Cl. 74 (Federal Claims, 2007)
Hillensbeck v. United States
74 Fed. Cl. 477 (Federal Claims, 2006)
Carmichael v. United States
70 Fed. Cl. 81 (Federal Claims, 2006)
CEMS, Inc. v. United States
65 Fed. Cl. 473 (Federal Claims, 2005)
Filtration Development Co., LLC v. United States
63 Fed. Cl. 612 (Federal Claims, 2005)
Hopi Tribe v. United States
55 Fed. Cl. 81 (Federal Claims, 2002)
Applegate v. United States
52 Fed. Cl. 751 (Federal Claims, 2002)
Baldi Bros. Constructors v. United States
52 Fed. Cl. 78 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
42 Cont. Cas. Fed. 77,211, 39 Fed. Cl. 593, 1997 U.S. Claims LEXIS 261, 1997 WL 719911, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kms-fusion-inc-v-united-states-uscfc-1997.