CEMS, Inc. v. United States

65 Fed. Cl. 473, 2005 U.S. Claims LEXIS 106, 2005 WL 950495
CourtUnited States Court of Federal Claims
DecidedApril 22, 2005
DocketNos. 99-951C, 00-437C to 00-439C
StatusPublished
Cited by26 cases

This text of 65 Fed. Cl. 473 (CEMS, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CEMS, Inc. v. United States, 65 Fed. Cl. 473, 2005 U.S. Claims LEXIS 106, 2005 WL 950495 (uscfc 2005).

Opinion

OPINION

HORN, Judge.

This matter comes before the court on the application of CEMS, Inc. for attorney fees under the Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412 (2000). Plaintiff alleges that it is entitled to an award of attorney fees and expenses under EAJA. More specifically, plaintiff argues that (1) the contracting officer assigned to this case at the Department of Transportation Federal Highway Administration (FHA), Western Federal Lands Highway Division “surrendered his or her authority to make decisions” during the administration of the contract; (2) that the contracting officer also “surrendered to others adjudication of claims submitted by CEMS;” and (3) that the government was not substantially justified in proceeding to trial on those claims on which CEMS ultimately prevailed. Plaintiff also alleges that the government should have recognized the “core failings of [the agency contracting officer] to administer the project or determine the claims... [and] should have earlier and more actively sought a global solution, but instead it compelled CEMS to adjudicate its claims at a cost that was overwhelming.” Plaintiff seeks $221,701.56 in EAJA attorney fees. After careful consideration of the record before the court and the applicable law, the court finds that the defendant is liable to the plaintiff for $57,058.64 in EAJA fees.

FINDINGS OF FACT

The facts of this case were fully detailed in this court’s lengthy November 3, 2003 opinion, CEMS, Inc. v. United States, 59 Fed.Cl. 168 (2003), and those facts are incorporated into this opinion. Only a brief recitation of the most pertinent facts to the present motion will be repeated here. On April 6, 1998, the FHA awarded a $1,676,154.00 contract to CEMS for the construction of a bicycle path on a 3.888 kilometer portion of the Historic Columbia River Highway, between the Columbia Fish Hatchery and the “Bridge of the Gods.”

As a result of disputes which arose during performance of the contract, plaintiff filed multiple claims with the contracting officer. The plaintiff then filed several separate appeals before the Department of Transportation Board of Contract Appeals (DOTBCA). During the pendency of the plaintiff’s appeals before the DOTBCA, the plaintiff submitted another, comprehensive claim to the agency contracting officer, including numerous separate claims, some of which included separate pay items for changes, delays, and other allegations of acts or omissions by FHA, for which plaintiff requested an equitable adjustment under the terms of the contract. Following the denial of a number of plaintiff’s claims and separate bid items by the contracting officer, CEMS filed its complaint in this court. The plaintiff subsequently filed a motion to consolidate the DOTBCA appeals with this case, which the court granted.

On June 27, 2000, pursuant to a government motion to dismiss, this court dismissed a number of the claims filed with this court. On the first day of trial, the parties settled a number of additional claims and separate bid items. A large number of claims and individ[475]*475ual bid items remained for trial. During the trial, CEMS added 3 supplemental claims, bringing the total damages sought to $1,241,203.70. Following the trial, this court found government liability on 6 of the remaining 19 claims and 3 of the remaining 11 bid items, resulting in a judgment for the plaintiff in the amount of $316,567.52. Defendant then filed a motion for partial reconsideration of this court’s opinion, seeking review of 3 of the claims included in the court’s opinion. The court granted reconsideration regarding 2 of the bid items and claims in favor of the government and revised plaintiffs recovery from $316,562.52 to $294,777.89.

Plaintiffs EAJA application was filed in this court seeking attorney fees and expenses for work performed. Plaintiffs itemized statement indicates that it seeks fees and other expenses incurred from June 8,1999 to July 20, 2004.

DISCUSSION

I. EAJA Requirements

The EAJA provides that a judgment for costs “may be awarded to the prevailing party in any civil action brought by or against the United States____” 28 U.S.C. § 2412(a)(1). Section 2412(d)(1)(B) of the EAJA provides:

A party seeking an award of fees and other expenses shall, within thirty days of final judgment in the action, submit to the court an application for fees and other expenses which shows that the party is a prevailing party and is eligible to receive an award under this subsection, and the amount sought, including an itemized statement from any attorney or expert witness representing or appearing on behalf of the party stating the actual time expended and the rate at which fees and other expenses were computed. The party shall also allege that the position of the United States was not substantially justified.

28 U.S.C. § 2412(d)(1)(B). “The purpose of the EAJA is to ‘eliminate legal expenses as a barrier to challenges of unreasonable government action.’ ” Cmty. Heating & Plumbing Co. v. Garrett, 2 F.3d 1143, 1145 (Fed.Cir. 1993) (citations omitted). Because EAJA constitutes a “partial waiver of sovereign immunity,” the statute is to be “strictly construed in favor of the United States,” Ardes-tani v. I.N.S., 502 U.S. 129, 137, 112 S.Ct. 515, 116 L.Ed.2d 496 (1991) and, therefore, cannot be “enlarged beyond what the language requires.” United States v. Nordic Vill., 503 U.S. 30, 34, 112 S.Ct. 1011, 117 L.Ed.2d 181 (1992).

Thus, eligibility for an award of attorney fees and expenses in a civil action requires (1) that the claimant be a prevailing party; (2) that the government’s position viewed over the entire course of the dispute was not substantially justified; (3) that no special circumstances make an award unjust; and (4) that pursuant to section 2412(d)(1)(B), any fee application be submitted to the court within thirty days of final judgment in the action and be supported by an itemized statement. See 28 U.S.C. § 2412(d)(1)(A),(B); Comm’r, I.N.S. v. Jean, 496 U.S. 154, 158, 110 S.Ct. 2316, 110 L.Ed.2d 134 (1990).

II. Entitlement

Defendant concedes that plaintiff was the prevailing party in this action and is otherwise EAJA-eligible. However, because EAJA “was not intended to be an automatic fee-shifting device” in any given lawsuit where the applicant prevails against the government, the government may successfully assert a substantial justification defense to prevent recovery under EAJA. See Luciano Pisoni Fabbrica Accessori Instrumenti Musicali v. United States, 837 F.2d 465, 467 (Fed.Cir.), cert. denied 488 U.S. 819, 109 S.Ct. 60, 102 L.Ed.2d 38 (1988) (quoting Gavette v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Q Integrated Companies, LLC v. United States
133 Fed. Cl. 479 (Federal Claims, 2017)
Rda Construction Corp. v. United States
132 Fed. Cl. 732 (Federal Claims, 2017)
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Mann v. United States
Federal Claims, 2014
Prochazka v. United States
116 Fed. Cl. 444 (Federal Claims, 2014)
Atkins North America, Inc. v. United States
106 Fed. Cl. 491 (Federal Claims, 2012)
Standard Communications, Inc. v. United States
106 Fed. Cl. 165 (Federal Claims, 2012)
Greenhill v. United States
96 Fed. Cl. 771 (Federal Claims, 2011)
United Partition Systems, Inc. v. United States
95 Fed. Cl. 42 (Federal Claims, 2010)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Information Sciences Corp. v. United States
86 Fed. Cl. 269 (Federal Claims, 2009)
Blakley v. United States
85 Fed. Cl. 360 (Federal Claims, 2008)
Precision Pine & Timber, Inc. v. United States
83 Fed. Cl. 544 (Federal Claims, 2008)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
Sweetwater v. United States
75 Fed. Cl. 214 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
65 Fed. Cl. 473, 2005 U.S. Claims LEXIS 106, 2005 WL 950495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cems-inc-v-united-states-uscfc-2005.