Meva Corp. v. United States

511 F.2d 548, 20 Cont. Cas. Fed. 83,728, 206 Ct. Cl. 203, 1975 U.S. Ct. Cl. LEXIS 9
CourtUnited States Court of Claims
DecidedFebruary 19, 1975
DocketNo. 492-69
StatusPublished
Cited by8 cases

This text of 511 F.2d 548 (Meva Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meva Corp. v. United States, 511 F.2d 548, 20 Cont. Cas. Fed. 83,728, 206 Ct. Cl. 203, 1975 U.S. Ct. Cl. LEXIS 9 (cc 1975).

Opinion

Per Curiam : This case comes before the court on exceptions by the plaintiff and the defendant to the recommended decision, filed January 11, 19T4, by Trial Judge Harry E. Wood pursuant to Buie 134 (h). The court has considered the case on the briefs and oral argument of counsel for the parties [207]*207and the Amicus Curiae. Since the court agrees with the recommended decision of the trial judge, as supplemented by the court, and as hereinafter set forth, it hereby affirms and adopts the recommended decision, as supplemented, as the basis for its judgment in this case. Therefore, plaintiff is entitled to recover and judgment is entered for plaintiff in the sum of $600,000.

OPINION OP TRIAL JUDGE

Wood, Trial Judge:

In this contract action, plaintiff, a California corporation, contends that in the facts and circumstances of this cause defendant’s refusal after contract award to permit plaintiff either (1) to substitute another subcontractor for one listed by plaintiff in its bid as the subcontractor who would (should plaintiff be awarded the contract) perform clearing and footings work, or (2) to perform the clearing and footings work itself, constituted a breach of contract, and that defendant is accordingly liable to it for its resulting damages, alleged to amount to some $1,600,000.

Defendant’s position is that the Contracting Officer never rendered “a decision that was final as to the contractor’s right to substitute”; that, assuming arguendo the Contracting Officer did make “an arbitrary and final decision”, plaintiff’s claim for resulting damages is nonetheless barred by estoppel or waiver; that in any event plaintiff’s “total cost” approach to the problem of damages is deficient; and that, there being “no other competent proof of damages, plaintiff cannot recover.”1

For the reasons which follow, it is concluded that plaintiff is entitled to recover, in the amount of $600,000.

I

Early in 1964, defendant, acting through the Bureau of Reclamation, Department of the Interior, issued an invitation for bids (IFB) for the construction and completion of a proposed “Flagstaff-Pinnacle Peak” 345-kilovolt transmission line running from near Winona, Arizona, to the Bureau of Reclamation’s Pinnacle Peak 'Substation some 14 [208]*208miles north, of Scottsdale, Arizona. Bids were to be opened in Phoenix May 12,1964.

The IFB indicated that the work to be performed (which included, inter alia, clearing and footings work) was to be divided into two schedules, each approximately 57 miles in length; that work should begin within 30 calendar days after the contractor’s receipt of notice to proceed; and that all of the contract work should be completed within 630 days from the date of receipt of such notice. The IFB also included Special Condition 24, Specifications No. DC-6090, “Listings of Subcontractors”, the genesis of this litigation.

Briefly, paragraph b of Special Condition 24 required that a bidder submit with his bid the firm name and address of each subcontractor to whom a subcontract would be awarded for each category of work listed in a “Supplement to Bid Form, S.F. 21 — List of Subcontractors”. Paragraph b further stated that, “Except as otherwise provided herein, the bidder agrees, if awarded the contract, not to contract to have any of the listed categories of work performed by any subcontractor other than the subcontractor named for the performance of such work.” Special Condition 24 also provided in part as follows:

e. No substitution for any named subcontractor will be permitted prior to award, and only in unusual situations after award and then only upon the contractor’s submission, in writing, to the Contracting Officer of a complete justification therefor and after obtaining the Contracting Officer’s written approval thereof. * * *

Mr. S. M. Rivers, who had become an employee of plaintiff on April 27, 1964, was responsible for the preparation of plaintiff’s bid on the proposed transmission line. Despite his intent to subcontract the clearing and footings work, Mr. Rivers proceeded on his own to prepare a prime contract bid for plaintiff. He endeavored to obtain bids on the clearing and footings work, and as part of this effort solicited a bid from a Mr. Hal Perry, a Phoenix contractor doing business as Sun States Contracting Company. Mr. Rivers received a bid from Sun States on the evening of May 11,1964, the day before bid opening.

[209]*209Perhaps because of the timing of the Sun States bid, plaintiff’s prime contract bid to defendant did not reflect Sun States’ bid figures on the clearing and footings work (a total of about $1,523,000), but instead contained Mr. Rivers’ own higher bid figures for that work (a total of about $1,864,-000).2 In bidding on the proposed transmission line, Mr. Rivers, for plaintiff, did list Sun States (as “Sun States Construction Co.”) as a subcontractor for both clearing and footings work pursuant to Special Condition 24, supra. At some time prior to coming to work for plaintiff, Mr. Rivers had checked Mr. Perry’s “credit” and had found it to be “slow but good”. No further pre-bid investigation of either Mr. Perry’s or Sun States’ financial situation was then made.

At bid opening May 12, 1964, plaintiff’s bid of $6,148,581 on the proposed transmission line was within about $115,000 of defendant’s engineer’s estimate (of some $6,265,000), but was about $850,000 less than that of the next lowest bidder, a construction company which had just completed a parallel transmission line along the same right-of-way. Plaintiff was awarded a contract for construction of the Flagstaff-Pinnacle Peak 345-kilovolt transmission line, at an estimated price of some $6,133,000, June 5,1964.

In the meantime, and following May 12,1964, plaintiff had begun to investigate Sun States’ financial situation. After an unsuccessful effort to obtain information from Mr. Perry, receipt, on May 20, 1964, of a financial report showing Mr. Perry’s net worth to be rather small, and advice on June 9, 1964, from Sun States that it had secured a line of credit at a Phoenix bank (and from the bank that there was no such line of credit), two of plaintiff’s representatives visited the Bureau of Reclamation’s office in Phoenix on June 9, 1964, to inquire about the possibility of substituting another contractor for Sun States (whose financial condition was then mentioned) or of doing the clearing and footings work itself.

During this same period of time, however, representatives of Sun States, in conversations with representatives of defendant in Phoenix, had made a number of allegations re[210]*210specting plaintiff. Among other things, defendant was told that plaintiff was trying to “dump” Sun States, and that plaintiff was “bid shopping”. The latter term describes a situation where, after bid opening and award, a successful government prime contract bidder who has utilized a particular potential subcontractor’s bid figure in submitting its prime contract bid “shops” the subcontract work to other potential subcontractors in an effort either to obtain from another subcontractor a lower price for the work to be subcontracted or to drive down that of the subcontractor whose figures were used in computing the prime bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holloway Construction Co. v. United States
32 Cont. Cas. Fed. 72,389 (Court of Claims, 1984)
Salem Engineering & Construction Corp. v. United States
31 Cont. Cas. Fed. 71,312 (Court of Claims, 1983)
Degenaars Co. v. United States
31 Cont. Cas. Fed. 71,186 (Court of Claims, 1983)
Hoel-Steffen Construction Co. v. United States
684 F.2d 843 (Court of Claims, 1982)
Sun Oil Co. v. United States
572 F.2d 786 (Court of Claims, 1978)
Consolidated Diesel Electric Co. v. United States
533 F.2d 556 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
511 F.2d 548, 20 Cont. Cas. Fed. 83,728, 206 Ct. Cl. 203, 1975 U.S. Ct. Cl. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meva-corp-v-united-states-cc-1975.