Harvey Radio Laboratories, Inc. v. United States

115 F. Supp. 444, 126 Ct. Cl. 383, 1953 U.S. Ct. Cl. LEXIS 44
CourtUnited States Court of Claims
DecidedOctober 6, 1953
DocketNo. 49870
StatusPublished
Cited by20 cases

This text of 115 F. Supp. 444 (Harvey Radio Laboratories, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harvey Radio Laboratories, Inc. v. United States, 115 F. Supp. 444, 126 Ct. Cl. 383, 1953 U.S. Ct. Cl. LEXIS 44 (cc 1953).

Opinion

LittletoN, Judge,

delivered the opinion of the court:

This is an action on a contract to recover the balance of the price stated in the contract, alleged to be due and unpaid. In April 1946, plaintiff and defendant entered into a letter contract whereby plaintiff agreed to develop and fabricate for defendant certain radar equipment for use in long range navigation. In February 1947, a definitive fixed-price contract superseding the letter contract was executed, providing for a total contract price of $1,146,780.54. The contract specified that the prices contained therein were subject to revision in accordance with the provisions of Article 40 (finding 13). Article 40 required the contractor to submit to the contracting officer, within sixty days after the completion or termination of the contract, a detailed statement of the costs of performing the contract. It further provided that “Upon written demand of the Contracting Officer, made at any time within thirty days after the submission of such statement, the Contractor will negotiate to reduce the contract price to an amount representing fair and reasonable compensation for the performance of the contract.”

By a joint motion of the parties, allowed by the court on December 5, 1951, the issue before the court at this time is limited to determining whether or not the provision for revision of the contract price has become or can still be made [385]*385operative. Defendant concedes that if the contract price revision clause did not become or cannot now be made operative, plaintiff is entitled to recover the unpaid balance of the price stated in the contract, which has been stipulated to be $188,325.83.

Plaintiff contends that the making of a written demand by the contracting officer within the period specified by Article 40, after plaintiff submitted its statement of costs, was a condition precedent to any obligation upon it to negotiate a revision of the contract price; that no written demand was made by the contracting officer; and that as there was no waiver of the performance of the condition, plaintiff is not and cannot become obligated to negotiate to revise the contract pi’ice under the provisions of Article 40.

It is defendant’s position that the parties by their conduct waived any requirement for written notice of price revision proceedings; that plaintiff engaged in negotiations for price revision; that plaintiff cannot insist upon compliance with the technical demand provision of Article 40 because it did not complete the contract prior to the submission of its statement of costs, as required by Article 40; and, finally, that to permit plaintiff to recover the entire price stated in the contract, without revision based on costs of performance, would be to work a forfeiture against defendant and to place an excessive penalty on the failure to comply with a technicality.

The facts are that plaintiff and defendant, acting through its agent Watson Laboratories of the Air Technical Services Command, Army Air Forces (hereinafter Watson), entered into a letter contract on April 3, 1946, by the terms of which plaintiff agreed to develop and fabricate for defendant low frequency radar equipment for use in long range navigation.

Under the terms of the letter contract, which originally authorized expenditures of $95,000, plaintiff agreed to enter into negotiations with the War Department looking toward the execution of a definitive contract which would contain a detailed delivery schedule, and prices, terms, and conditions as agreed to by the parties. Work proceeded under the letter contract throughout the remainder of 1946 and into 19.47. Plaintiff gathered and transmitted to Watson the cost data [386]*386‘necéssary for the preparation of a definitive contract, and under- daté of February 12, 1947, a definitive contract was executed, superseding the letter contract.

This contract, which will be referred to herein as contract ac-76, required that plaintiff furnish and supply to the Government seven items (finding 10), for a total contract price of $1,146,780.54. Article 15 (a), containing the items and prices, provided that “The prices specified herein are subject to revision in accordance with the provisions of Article 40.”1

In April 1948, plaintiff wrote Watson that it expected to complete all of the items required by contract ac-76 within a few weeks, and suggested that early action be taken under the clause requiring redetermination of price prior to final payment. On May 7,1948, Watson replied that there would be ample time before June 30,2 to redetermine the price under the contract. On May 13,1948, Watson advised plaintiff that in accordance with Article 40 it was necessary that certain cost information be furnished Watson. On May 18, plaintiff replied that at such time as all of the work was completed (then estimated as June 1), cost information would be prepared in accordance with Watson’s May 13 letter and forwarded to Watson for appropriate study and review.

This exchange of correspondence was directed toward the submission by plaintiff of “a detailed statement of the costs of performing this contract” within sixty days after the completion of the contract, as required by Article 40. Both plaintiff and Watson were aware that the contract contained a price redetermination provision. Neither plaintiff nor Watson' reviewed the terms of Article 40, however, and neither of them was specifically aware of the demand provisions of the Article. Plaintiff assumed that Watson would do whatever was necessary to invoke the provision for price revision, and Watson assumed that plaintiff would negotiate to reduce the contract price without written demand to do so. Watson followed the policy and custom, with regard to all of its contracts, of conducting price redetermi-nations in accordance with the spirit of the contract articles, [387]*387without serving formal written demands to negotiate on the contractors.

This was the situation as it existed in May Of 1948. The information, intentions, and understandings of the-parties with respect to the price revision provisions of contract ac-76 remained unchanged from that time until September of 1949. What Occurred in September of 1949 will be the subject of discussion hereinafter. -

On November 24, 1948, plaintiff submitted what it termed .“complete detailed cost information applicable to-this contract [ac-76] from the date of its inception to final completion,” stating that it was particularly interested in completing any final price negotiations under Article 40 of the contract prior to the end of the current fiscal" year. This submission by plaintiff of what it considered to be the cost data, called for by the contract, constituted substantial performance by it in the first instance of- the requirement of Article 40 that a detailed statement of the costs Of performing the ¡contract be submitted to the contracting officer within sixty days after completion of the contract, and was intended as such performance by plaintiff. We do not interpret Article 40 as precluding the defendant to call -for further data or information as to costs, or to investigate and verify such cost statement of plaintiff before making the démand to negotiate a revision of the price stated in the contract under Article 40.

Article 40 of the contract reads in-pertinent part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Computer Supplies, Inc. v. United States
43 Fed. Cl. 351 (Federal Claims, 1999)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Zoubi v. United States
37 Cont. Cas. Fed. 76,287 (Court of Claims, 1992)
Dynamics Corp. of America v. United States
33 Cont. Cas. Fed. 74,498 (Court of Claims, 1986)
International Verbatim Reporters, Inc. v. United States
33 Cont. Cas. Fed. 74,323 (Court of Claims, 1986)
Meva Corp. v. United States
511 F.2d 548 (Court of Claims, 1975)
Petrofsky v. United States
488 F.2d 1394 (Court of Claims, 1973)
L. B. Samford, Inc. v. The United States
410 F.2d 782 (Court of Claims, 1969)
Industrial Uranium Company v. The United States
376 F.2d 868 (Court of Claims, 1967)
Industrial Uranium Co. v. United States
376 F.2d 868 (Court of Claims, 1967)
Penn-Ohio Steel Corporation v. The United States
354 F.2d 254 (Court of Claims, 1965)
Hoffman Motors Corporation v. Alfa Romeo SpA
244 F. Supp. 70 (S.D. New York, 1965)
Acme Process Equipment Co. v. United States
347 F.2d 509 (Court of Claims, 1965)
Acme Process Equipment Co. v. United States
347 F.2d 538 (First Circuit, 1965)
Copco Steel & Engineering Co. v. The United States
341 F.2d 590 (Court of Claims, 1965)
Appalachian Floor Co. v. United States
144 Ct. Cl. 11 (Court of Claims, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
115 F. Supp. 444, 126 Ct. Cl. 383, 1953 U.S. Ct. Cl. LEXIS 44, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harvey-radio-laboratories-inc-v-united-states-cc-1953.