Dynamics Corp. of America v. United States

33 Cont. Cas. Fed. 74,498, 10 Cl. Ct. 275, 1986 U.S. Claims LEXIS 847
CourtUnited States Court of Claims
DecidedJuly 1, 1986
DocketNo. 549-84C
StatusPublished
Cited by7 cases

This text of 33 Cont. Cas. Fed. 74,498 (Dynamics Corp. of America v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dynamics Corp. of America v. United States, 33 Cont. Cas. Fed. 74,498, 10 Cl. Ct. 275, 1986 U.S. Claims LEXIS 847 (cc 1986).

Opinion

OPINION

MARGOLIS, Judge.

The plaintiff, Dynamics Corporation of America [Dynamics], seeks review of two final decisions of a Government Contracting Officer, recovery of $3,822,072.26 withheld pursuant to these decisions and relief from an outstanding indebtedness resulting from the Contracting Officer’s decisions. The defendant United States seeks to uphold the Contracting Officer’s decisions and counterclaims to recover the outstanding balance due.

Jurisdiction is founded on the Contract Disputes Act of 1978, 41 U.S.C. § 609(a)(1) (1982). Both parties have moved for summary judgment.

For reasons discussed, the Court grants the defendant’s motion as to Count I (six-month adjustment provision), but denies the remainder of the defendant’s motion. The plaintiff’s motion as to Count II (Economic Price Adjustment Clause) is granted.

[277]*277FACTS

In March 1981 the Government issued an Invitation for Bids [IFB No. DAAJ09-81-B-0158] for the production of electric generator sets to be delivered to the U.S. Army. The IFB included a draft contract with required delivery dates for each of the first two program years of performance. An option to increase each program year order by 150% and a performance schedule for these first and second program year options were also included.

Bidders were asked to include anticipated inflation in their price. A Government forecast of inflation for the required delivery schedule was provided, and contractors were to use the forecast in preparing their bids.

As noted in the IFB, the Government forecasts were obtained from Bureau of Labor Statistics [BLS] indices of inflation. Composite estimates of inflation for each program year were embodied in Table I of the IFB as escalation factors.

The relevant portion of Table I is reproduced below:

Table I
ANTICIPATED COMPOSITE ESCALATION FACTORS
Program Year Factor
First Program Year Jun 81—Mar 83 1.1399
Second Program Year Mar 82—Sep 83 1.2044
First Program Year Option Apr 82—Apr 84 1.2389
Second Program Year Option Nov 82—Jan 85 1.3077

Table I was part of an IFB provision entitled “ADJUSTMENT FOR UNANTICIPATED ECONOMIC FLUCTUATION: INDEX METHOD,” which allowed for adjustments in contract price if actual inflation differed significantly from forecasted inflation. If inflation varied from the fore-casted values by more than 2%, the contract price would be adjusted by 70% of the difference. These adjustments were to be “made by contract modification within six months after the end of the applicable program year or option period.” [Adjustment Clause, Section H-6n].

Because Dynamics wanted to propose earlier delivery dates and was unsure about how the adjustment clause would be applied to early delivery, it requested clarification from the Contracting Officer. In particular, Dynamics wanted to know if the inflation factors in Table I of the IFB would be changed to reflect an earlier delivery schedule. If this was true, Dynamics would incorporate less inflation into the bid prices. Otherwise, Dynamics’ bid prices would need to account for inflation over the full contract term originally proposed in the IFB.

The Contracting Officer responded to this and other inquiries with a mailgram sent to all bidders. The pertinent part of his response is reproduced below:

3. PARA H-6 (ADJUSTMENT FOR UNANTICIPATED ECONOMIC FLUCTUATION-INDEX METHOD) IS TO BE REVIEWED AND EVALUATED IN ITS ENTIRETY. INDIVIDUAL SENTENCES OR PARAGRAPHS ARE NOT DESIGNED TO STAND ON THEIR OWN OR BE STATEMENTS OF FACT, BUT CONTRIBUTE TO THE OVERALL UNDERSTANDING OF THE INTENDED PURPOSE OF THE CLAUSE.
4. FOR FINAL EPA [ECONOMIC PRICE ADJUSTMENT CLAUSE] ADJUSTMENT PURPOSES, THE ADJUSTING FACTOR WILL BE BASED ON THE MONTH OF ACTUAL DELIVERY OR SCHEDULED DELIVERY WHICH EVER IS EARLIER, SEE PARA H-6(2) [sic].
5. IN THE EVENT THE OPTION IS NOT EXERCISED AT ONE TIME, THAT IS, IF IT IS EXERCISED IN SEPARATE INCREMENTS, THERE WILL BE SEPARATE EPA ADJUSTMENTS TO REFLECT THE DIFFERENT TIME PERIODS. THE TIME PERIODS WILL BE FROM THE TIME OF EXERCISE THROUGH FINAL DELIVERY (SCHEDULED OR ACTUAL, WHICH EVER IS EARLIER) OF EACH SEPARATE INCREMETN [sic] (SEE PARA H-6(4)).
6. CONTRACTORS ARE NOT REQUIRED TO AGREE WITH ESCALATION FACTORS GIVEN IN PARA [278]*278H-6E IN PREPARING THEIR BIDS, HOWEVER THE GOVERNMENT WILL ASSUME THAT THE FACTORS IN PARA H-6E WERE USED WHEN FINAL ADJUSTMENT IS CALCULATED.

Mailgram of May 8, 1981.

Dynamics interpreted this response to mean that the inflation factors in Table I would vary with the delivery schedule and that the BLS base line of forecasted inflation would be used to predict inflation factors for an early schedule. In other words, Dynamics asserts that the bid it submitted included less inflation than would a bid based on the originally proposed inflation factors and delivery schedule.

The Government awarded the contract to Dynamics in June 1981, adopting Dynamics’ early delivery schedule. Shortly thereafter, on July 7, Dynamics wrote to the Contracting Officer requesting that the original inflation factors in Table I be revised in accordance with the early delivery schedule. After numerous discussions, it became apparent that the Contracting Officer would not modify the original inflation factors. Dynamics asked for a final decision, but the Contracting Officer refused because BLS indices would not be available until approximately five months after the end of the program year.

Discussions about the appropriate adjustment factors continued throughout the first, second and third program year option periods. By the time a final decision covering the first three periods was rendered on January 17,1984, it was clear that inflation had not been as high as predicted. Dynamics admitted that a downward adjustment in contract price was appropriate but insisted that the adjustment should be based on the difference between projected inflation during its early delivery schedule and actual inflation over that same period.

In essence, Dynamics argued that the contract price adjustment made by the Contracting Officer was unduly large and that the Contracting Officer failed to consider the draft contract as modified by the early delivery schedule. In the Contracting Officer's view, Dynamics’ bid was assumed to include inflation for the entire period originally proposed in the IFB. Hence, Dynamics’ bid price supposedly included a large amount of inflation that never occurred, and a large price adjustment was necessary. Using the inflation factors from Table I of the IFB, the Contracting Officer issued modifications with his January 17, 1984 final decision reducing the contract price by $1,643,930.26.

The final decision and modifications came approximately one year and four months after the expiration of the first program year, approximately eleven months after the expiration of the second program year, and approximately eight months after the expiration of the first year option period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Martin v. United States
20 Cl. Ct. 738 (Court of Claims, 1990)
Erwin v. United States
36 Cont. Cas. Fed. 75,766 (Court of Claims, 1989)
Dynamics Corp. of America v. United States
35 Cont. Cas. Fed. 75,663 (Court of Claims, 1989)
Brutoco Engineering & Construction, Inc. v. United States
34 Cont. Cas. Fed. 75,249 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,498, 10 Cl. Ct. 275, 1986 U.S. Claims LEXIS 847, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dynamics-corp-of-america-v-united-states-cc-1986.