Ceccanti, Inc. v. United States

32 Cont. Cas. Fed. 73,041, 6 Cl. Ct. 526, 1984 U.S. Claims LEXIS 1267
CourtUnited States Court of Claims
DecidedOctober 31, 1984
DocketNo. 559-82C
StatusPublished
Cited by14 cases

This text of 32 Cont. Cas. Fed. 73,041 (Ceccanti, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ceccanti, Inc. v. United States, 32 Cont. Cas. Fed. 73,041, 6 Cl. Ct. 526, 1984 U.S. Claims LEXIS 1267 (cc 1984).

Opinion

OPINION

MARGOLIS, Judge.

The plaintiff Ceccanti, Inc., brings this action under the Contract Disputes Act seeking compensation for additional expenses incurred during the performance of a contract with the defendant United States. The plaintiff has moved for summary judgment on the issue of liability for high water levels which allegedly delayed work and resulted in the plaintiff incurring additional costs totaling $47,845.82. The defendant filed a cross motion for summary judgment contending that under the terms of the contract, the plaintiff bore the risk of high water levels.

After considering the entire record and hearing oral argument, the Court finds that the contract clearly allocated the risk of high water levels to the plaintiff. Therefore, the plaintiff’s motion for summary judgment is denied. Because the plaintiff’s complaint includes a claim based on an allegedly defective project design, and because both parties agree that this claim involves material disputed issues of fact, the defendant’s motion for summary judgment is granted in part and denied in part.

PACTS

On September 25, 1981, the plaintiff contracted with the United States Department of Agriculture Forest Service to undertake river bank stabilization and bridge pier protection with respect to an already existing Forest Service bridge located over a stream which feeds into Lake Cushman. Lake Cushman is situated on the Olympic Peninsula in Washington State and is a man-made lake with a dam at its southern end. The dam, and therefore the water level, is controlled by the City of Tacoma.

The total contract price was fixed at $111,803.30. Though there is some dispute as to the length of the contract, it appears that both parties expected the work to be completed within sixty days. But because of an ambiguity in the contract, the Forest Service extended the length of the contract for an additional sixty days.

The defendant issued a Notice to Proceed on October 21, 1981. Upon arrival at the site on November 3, 1981, the plaintiff found that the water level was higher than what it considered to be workable. The Contracting Officer disagreed, noting several items which could be performed despite the high water. The plaintiff performed these items, and on December 10, 1981 the Forest Service stopped charging time. On December 28, 1981 an Order to Resume Work was issued. High water in mid-February 1982 again required a partial and then a total Suspension of Work order; the latter was issued on February 23, 1982. The plaintiff was instructed to demobilize [528]*528under the assumption that no more work would be done until the following fall. But shortly thereafter the water level fell, and on March 17, 1982, a Notice to Resume was issued. The plaintiff remobilized and, despite rising water levels, substantially completed the project by April 21, 1982, at which time the work was inspected and accepted by the Forest Service.

The plaintiff submitted a number of claims to the Contracting Officer pursuant to the Contract Disputes Act, 41 U.S.C. § 605(a) (1982), totaling $52,327.78.- Of this total, $47,845.82 was allegedly the result of interference caused by the high water levels, specifically the costs of remo-bilization and equipment standby time. The Contracting Officer denied all claims in his final decision dated July 20, 1982.

DISCUSSION

The plaintiffs main contention is that the high water levels caused unreasonable delays, and that therefore an equitable adjustment of the contract price is justified. Principally, the plaintiff argues that the contract is ambiguous with regard to liability for ground conditions, and that the plaintiffs interpretation, if reasonable, should prevail over even an equally reasonable interpretation by the defendant. It is well settled that the interpretation of a contract is a question of law, Dynamics Corporation of America v. United States, 182 Ct.Cl. 62, 71-72, 389 F.2d 424, 429 (1968), and if the plaintiffs interpretation is reasonable, it will prevail. A & K Plumbing & Mechanical, Inc. v. United States, 1 Cl.Ct. 716, 721 (1983). However, this rule only applies where the contract drafted by the Government is in fact ambiguous, and where the plaintiffs interpretation is reasonable. A mere dispute over the terms does not constitute ambiguity, and an interpretation which is merely possible is not necessarily reasonable. Tri-Cor, Inc. v. United States, 198 Ct.Cl. 187, 211, 458 F.2d 112, 126 (1972).

To justify its interpretation of the contract, the plaintiff argues that the contract must be considered as a whole. Specifically, the plaintiff relies upon the Control of Work clause, which permits the Contracting Officer “to issue orders to suspend the work wholly or in part for such period of time as he determines necessary due to: (1) weather or ground conditions unsuitable for prosecution of the work or detrimental to project access____” Supplemental General Provisions to Form 6300-42, § 30.1. The plaintiff also relies upon the Government’s Responsibility for Utilities clause, which provides that “[t]he Government will notify all utility companies or other parties affected and make arrangements for all necessary adjustments of the public or private utility fixtures, pipelines, and other appurtenances affected by the construction.” Forest Service, General Provisions, Public Works Contract, § 50.5 (December 1979). The plaintiff claims that the Control of Work clause only refers to natural ground conditions such as rain or snow, and that the Responsibility for Utilities clause indicates that the Government will be responsible for contacting local utilities and making the necessary arrangements with them. The two clauses combined allegedly result in the Government being liable for conditions caused by a local utility, City of Tacoma, when that utility failed to make arrangements to accommodate the plaintiff’s work by lowering the water level.

However, the plaintiff fails to justify limiting the provision regarding ground conditions (§ 30.1) to only natural conditions. Furthermore, the section on Responsibility for Utilities (§ 50.5) refers only to the defendant’s legal responsibility to the public, not to the plaintiff, to insure that the necessary adjustments are made so that utility fixtures, pipelines, and other appurtenances are not adversely affected by the construction. Finally, in interpreting a contract, an interpretation which gives a reasonable meaning to the whole is favored over one which leaves a portion of it “useless, inexplicable, inoperative, void, insignificant, meaningless, or superfluous____” Hol-Gar Manufacturing Corp. v. United States, 169 Ct.Cl. 384, 395, 351 [529]*529F.2d 972, 979 (1965). The defendant is correct in pointing out that the interpretation which plaintiff urges this Court to adopt would render the Prosecution of Work clause meaningless. That section states: “Reservoir elevations for Lake Cushman are controlled by the City of Tacoma. Information relating to high and low water elevations, time periods of low water and flow data is available from the Tacoma City and Light Business Office (phone: (206) 383-2471).” Supplemental General Provisions to Form 6300-42, § 40.-2(c).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
Blackstone Consulting, Inc. v. United States
65 Fed. Cl. 463 (Federal Claims, 2005)
Allstates Air Cargo, Inc. v. United States
42 Cont. Cas. Fed. 77,391 (Federal Claims, 1998)
Rutgers v. United States
42 Cont. Cas. Fed. 77,377 (Federal Claims, 1998)
A Olympic Forwarder, Inc. v. United States
40 Cont. Cas. Fed. 76,788 (Federal Claims, 1995)
North Star Alaska Housing Corp. v. United States
39 Cont. Cas. Fed. 76,607 (Federal Claims, 1993)
American Satellite Co. v. United States
36 Cont. Cas. Fed. 75,884 (Court of Claims, 1990)
Edwards v. United States
36 Cont. Cas. Fed. 75,822 (Court of Claims, 1990)
Kelley v. United States
36 Cont. Cas. Fed. 75,771 (Court of Claims, 1989)
Diggins Equipment Corp. v. United States
35 Cont. Cas. Fed. 75,687 (Court of Claims, 1989)
International Business Investments, Inc. v. United States
35 Cont. Cas. Fed. 75,668 (Court of Claims, 1989)
Jeppesen Sanderson, Inc. v. United States
14 Cl. Ct. 624 (Court of Claims, 1988)
Dynamics Corp. of America v. United States
33 Cont. Cas. Fed. 74,498 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,041, 6 Cl. Ct. 526, 1984 U.S. Claims LEXIS 1267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ceccanti-inc-v-united-states-cc-1984.