Maki v. United States

34 Cont. Cas. Fed. 75,417, 13 Cl. Ct. 779, 1987 U.S. Claims LEXIS 225, 1987 WL 22371
CourtUnited States Court of Claims
DecidedDecember 9, 1987
DocketNo. 288-85C
StatusPublished
Cited by7 cases

This text of 34 Cont. Cas. Fed. 75,417 (Maki v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maki v. United States, 34 Cont. Cas. Fed. 75,417, 13 Cl. Ct. 779, 1987 U.S. Claims LEXIS 225, 1987 WL 22371 (cc 1987).

Opinion

OPINION

ANDEWELT, Judge.

In this action, plaintiff charges the Department of the Navy with breach of a contract under which plaintiff was to construct a facility for keeping dogs used in drug detection work. The action is presently before this Court on cross-motions for summary judgment. Plaintiff seeks judgment in the amount of $472,857; defendant does not contest $3,744.33 of plaintiff’s claim, but disputes the remainder. For the reasons explained herein, plaintiff is granted summary judgment only to the extent of its uncontested claim for $3,744.33, and defendant’s cross-motion is granted as to the remainder of plaintiff’s claim.

Facts

The contract in issue, Contract No. N62472-83-C-5840, was awarded to Maki by the Department of the Navy on September 30, 1983. The contract called for Maki to build a dog facility according to a specified design and to complete construction by January 13, 1984. The contract price was $27,330.

Maki received notice to proceed with performance of the contract on November 4, [780]*7801983. On November 9, 1983, the Navy issued a requirement that all military working dog kennel facilities be approved by the Chief of Naval Operations. In a letter dated November 16, 1983, the Navy informed Maki that “[a] change in criteria for the construction of [the contract] facilities has been made ... we will notify you as soon as possible after a determination of the required changes, if any, that must be incorporated into your contract.” Maki was told in the letter “to refrain from accomplishing any work or procuring any materials for [the] referenced contract until you receive further authority____”

Approximately five months later, in a letter dated April 23, 1984, the Navy provided Maki with a set of revised design specifications for the dog facility, and requested that Maki submit a bid proposal for “the inclusion under the subject contract” of the revised specifications. In its response dated April 28, 1984, Maki did not submit a new bid, but instead submitted a certified claim for delay damages under paragraph 17(b) of the contract. That paragraph provides:

If the performance of ... the work is, for any unreasonable period of time, suspended, delayed or interrupted by an act of the Contracting Officer in the administration of this contract, or by his failure to act within the time specified in this contract (or if no time is specified within a reasonable time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable suspension, delay or interruption and the contract modified in writing accordingly.

In its certified claim, Maki sought $2,932 to cover certain expenditures arising prior to November 8, 1983, a “contractor fee” of $800 per day from November 8, 1983, until the date the claim was settled, and “liquidated damages” of $1,575 per day from September 30,1984, until the date the claim was settled. Maki claimed that the Navy had unreasonably delayed its submission of the revised specifications, and that Maki could not offer “a responsible bid” for construction of the dog facility under the revised specifications until its certified claim for delay damages was resolved.

Maki subsequently met with Navy personnel to discuss the contract and, by letter dated May 10, 1984, submitted a $58,343 bid for construction of the dog facility according to the revised specifications. The Navy responded in a May 22, 1984, letter that Maki’s bid was “excessive” in that it called for 56% inflation in eight months for what amounted to only 75% of the original work. The letter went on to state: “Considering your price, this office is considering terminating the contract for convenience. Please submit your proposal for your expenditures on the enclosed forms, in order that we may negotiate a fair and equitable settlement.”

By letter dated May 30, 1984, Maki submitted the requested expenditure proposal. In its breakdown estimate of direct costs, Maki sought a total of $551,232. This figure included a “contractor fee” of $164,000 ($800 per day for the 205-day period from November 8, 1983, to May 30, 1984) and “damages” of $384,300 ($1,575 per day for the 244-day period from September 30, 1983, to May 30, 1984).

The Navy forwarded Maki’s proposal for expenditures to the Defense Contract Audit Agency (“DCAA”) for verification. After conducting an audit, the DCAA auditor, in a November 2, 1984, report, stated:

Maki has no books or records to support any of the cost claimed by Mr. Young-berg [Maki’s individual owner] ... The records only support several minor expenditures made by Maki ... The contractor furnished us with invoices from Chesley & Cline insurance brokers, but refused to provide us with proof of payment (cancelled checks) ... Finally, the value of the basic contract was under $60,000. Therefore, the inclusion of a contractor’s fee of $164,000 and liquidated damage request of $284,800 is almost fraudulent.

The auditor concluded that Maki substantiated only $790 of the $551,232 Maki claimed.

[781]*781By letter dated November 14, 1984, the Government terminated the contract for its convenience. In the November 14, 1984, termination letter, Maki was advised that its certified claim would be considered its termination claim unless Maki advised the Government differently. On January 12, 1985, Maki informed the Government that it took exception to its claim being considered a termination claim. Maki did not, however, submit a different termination claim. On March 18, 1985, the contracting officer rendered a final decision with respect to Maki’s certified claim, finding that, for work performed, Maki was entitled to $3,744.33, including its direct costs, home office overhead, and interest.

On May 15,1985, Maki filed its complaint with this Court, seeking review of the contracting officer’s decision, and damages in the amount of $472,857, due as of April 28, 1984.

Discussion

A grant of summary judgment is appropriate only where there is no genuine issue of material fact (i.e., a fact that might affect the outcome of the suit) and the movant is entitled to judgment as a matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). See Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed.Cir.1987). The moving party bears the burden of establishing the absence of any genuine issue of material fact. That burden may be discharged by pointing out to the Court that there is an absence of evidence to support the non-moving party’s case, i.e., an absence of evidence as to a material fact on which the non-movant bears the burden of proof. Celotex Corp. v. Catrett, 477 U.S. 317, 106 S.Ct. 2548, 2554, 91 L.Ed.2d 265 (1986). When the moving party successfully discharges its burden in this way, to defeat the summary judgment motion, the non-movant must present sufficient evidence as to the existence of that fact so that the trier of fact could reasonably find in favor of the nonmovant. See Liberty Lobby, 106 S.Ct. at 2512. The Federal Circuit has delineated the non-moving party’s burden in this respect as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metric Construction Co. v. United States
83 Fed. Cl. 446 (Federal Claims, 2008)
Law v. United States
26 Cl. Ct. 382 (Court of Claims, 1992)
Construction Equipment Lease Co. v. United States
38 Cont. Cas. Fed. 76,328 (Court of Claims, 1992)
Wilner v. United States
37 Cont. Cas. Fed. 76,101 (Court of Claims, 1991)
Avedon Corp. v. United States
35 Cont. Cas. Fed. 75,577 (Court of Claims, 1988)
Maki v. The United States
852 F.2d 1293 (Federal Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,417, 13 Cl. Ct. 779, 1987 U.S. Claims LEXIS 225, 1987 WL 22371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maki-v-united-states-cc-1987.