Construction Equipment Lease Co. v. United States

38 Cont. Cas. Fed. 76,328, 26 Cl. Ct. 341, 1992 U.S. Claims LEXIS 222, 1992 WL 103607
CourtUnited States Court of Claims
DecidedMay 15, 1992
DocketNo. 92-88C
StatusPublished
Cited by3 cases

This text of 38 Cont. Cas. Fed. 76,328 (Construction Equipment Lease Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Construction Equipment Lease Co. v. United States, 38 Cont. Cas. Fed. 76,328, 26 Cl. Ct. 341, 1992 U.S. Claims LEXIS 222, 1992 WL 103607 (cc 1992).

Opinion

ORDER

ANDEWELT, Judge.

In this government contract action, plaintiffs, Construction Equipment Lease Company (CELCO) and Judd Construction Company (Judd), seek payments pursuant to a contract between Judd and the United States Department of the Interior, Office of Surface Mining (OSM). This action is presently before the court on defendant’s motion for partial summary judgment. For the reasons set forth below, defendant’s motion is granted as to Count III of plaintiffs’ second amended complaint, and Count IV is dismissed for lack of jurisdiction.1

I2

In June 1983, OSM solicited bids for a contract covering the extinguishment of an abandoned, burning refuse pile in Kodak, Kentucky. In July 1983, OSM awarded the contract to Judd, based on a bid signed by its “owner,” Billy H. Judd. The contract required Judd to (1) clear and “grub” the refuse pile and waste area; (2) cool, excavate, and dispose of burning refuse material; (3) place a covering over the refuse; and (4) regrade, restore, and revegetate all disturbed areas. Judd subcontracted with CELCO to perform the contract work and, in turn, CELCO hired Billy H. Judd as the project supervisor.

On November 9, 1983, Judd stopped work on the project. In a letter to the contracting officer dated November 29, 1983, Judd explained: “The subject job was shut down November 9,1983, primarily due to lack of operating funds.” In that same letter, Judd further stated:

Even though the job has been plagued with many problems, drought, vandalism, arson, theft, inadequate repair resulting in unnecessary loss of equipment and man-hours, etc., ... by far the most costly is with interpretations and changes of the specifications. Limitations and/or restrictions placed on disposal of the refuse is the most costly.

Approximately seven months later, on June 12, 1984, OSM issued a modification to the contract. Plaintiffs thereafter resumed work.

On June 12, 1986, Judd submitted to the contracting officer a certified claim requesting an equitable adjustment in the amount of $369,201.16. The claim stated, in pertinent part:

II.
That sometime during October of 1983, a material dispute arose between the contractor and the United States based upon a question as to the volume of refuse that had been removed by that time by the contractor ... and;
III.
That because of said dispute ... the payments for ongoing work ... were suspended, forcing the contractor to cease operations, for lack of operating capital at that time ... and;
******
V.
That upon completion of [a government] survey, and after 34 weeks of cessation of operations, it was revealed that [344]*344the contractor had indeed removed some 3,000 more cubic yards of refuse than had been thought by the Government, and therefore the reason for the prior cessation of payments and subsequent cessation of work, was revealed to be entirely outside of the control of the contractor and without any fault whatsoever upon his part and;
VI.
That because of said cessation of payments under the contract and the subsequent cessation of work because thereof, the contractor suffered losses which [it] has fully enumerated in [an] attached schedule____

In subsequent discussions between plaintiffs and OSM, both parties apparently considered the June 12, 1986, claim for $369,-201.16 as involving three distinct claims. First, plaintiffs sought $291,341.16 for costs incurred during the seven months plaintiffs had stopped work. These costs included, for example, costs relating to keeping machinery on the contract site and available for work during the stop-work period. Second, plaintiffs sought $7,680 for additional work allegedly performed by the contractor. And third, plaintiffs sought $70,000 on the ground that OSM had improperly refused to permit plaintiffs to dispose of the refuse at certain sites chosen by plaintiffs.

In a February 11, 1987, decision, the contracting officer denied plaintiffs’ three claims except for $4,320 of the second claim. As to the first claim, the contracting officer concluded that plaintiffs were not entitled to costs incurred during the stop-work period. The contracting officer explained: “This agency maintains the position that the contractor was fully paid for all work completed at the time he chose to arbitrarily cease work because of alleged lack of working capital.” The contracting officer further concluded that “all costs associated with the contractor’s total down time cannot be paid for by the Government, as the contractor’s shut down was of his own making and not due to fault of the Government.” As to the third claim, to the effect that OSM had improperly refused to allow plaintiffs to employ alternative disposal sites, the contracting officer concluded that the contract specifically identified a designated waste disposal site and that OSM had been justified in refusing to allow the alternative sites plaintiffs had proposed.

On February 11, 1988, CELCO filed the instant action, on Judd’s behalf, challenging the contracting officer’s February 11, 1987, decision. In a July 17, 1989, order, this court joined Judd as a real party in interest. See Constr. Equipment Lease Co. v. United States, 17 Cl.Ct. 628 (1989). The second amended complaint contains four counts in which Judd and CELCO seek equitable adjustments totalling $418,-142.39. In Count IV, plaintiffs contend that OSM violated the terms of the contract when, on October 21, 1985, it made a progress payment of $49,121.39 to Judd’s account at the Citizens National Bank, Bowling Green, Kentucky. Judd did not present this allegation to the contracting officer in its June 12, 1986, claim and the contracting officer did not address this issue in his February 11, 1987, final decision on that claim. However, on November 27, 1989, plaintiffs submitted a separate claim to the contracting officer covering this allegation of a misdirected progress payment. The contracting officer denied the claim in a July 12, 1990, final decision.

II.

Summary judgment is not a “disfavored procedural shortcut” but rather “an integral part of the Federal Rules as a whole.” Celotex Corp. v. Catrett, 477 U.S. 317, 327, 106 S.Ct. 2548, 2554-55, 91 L.Ed.2d 265 (1986). The necessary procedures for such a disposition are well-established in case law and commentary. See, e.g., Anderson v. Liberty Lobby, Inc., ATI U.S. 242, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Celotex Corp. v. Catrett, 477 U.S. 317, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Matsushita Electric Industrial Co. v. Zenith Radio Corp., 475 U.S. 574, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986); 6 J. Moore, W. Taggart, & J. Wicker, Moore’s Federal Prac[345]*345tice ¶ 56.01 et seq. (2d ed. 1992); RUSCC 56. In Maki v. United States, 13 Cl.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Made in the USA Foundation v. United States
51 Fed. Cl. 252 (Federal Claims, 2001)
Aero-Abre, Inc. v. United States
39 Fed. Cl. 654 (Federal Claims, 1997)
Robin Industries, Inc. v. United States
29 Fed. Cl. 122 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,328, 26 Cl. Ct. 341, 1992 U.S. Claims LEXIS 222, 1992 WL 103607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-equipment-lease-co-v-united-states-cc-1992.