DeLong v. United States

175 F. Supp. 169, 146 Ct. Cl. 289, 1959 U.S. Ct. Cl. LEXIS 159
CourtUnited States Court of Claims
DecidedJuly 13, 1959
DocketNo. 146-57
StatusPublished
Cited by4 cases

This text of 175 F. Supp. 169 (DeLong v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DeLong v. United States, 175 F. Supp. 169, 146 Ct. Cl. 289, 1959 U.S. Ct. Cl. LEXIS 159 (cc 1959).

Opinion

LaRAmoee, Judge,

delivered the opinion of the court:

This is a suit by plaintiff1 for expenses incurred under a 90-day cancellation clause in a shipyard lease obtained under the original specification of a Government contract, but not used because of changes in addenda to the contract.

The case arises on plaintiff’s motion and defendant’s cross-motion for summary judgment, and presents only the question as to whether costs incurred on a shipyard facility not used in the performance of a cost-plus-fixed-fee contract are allowable.

The facts which are not in dispute are these: In January 1952, discussions and negotiations began between plaintiff and the Transportation, Research and Development Station of the Department of the Army for a cost-plus-fixed-fee contract for the construction of self-elevating barges.

On February 21, 1952, one Burt B. Rand, acting as attorney for plaintiff in the negotiations, advised defendant by letter that plaintiff intended to perform the contract at the Wainwright Shipyard at Panama City, Florida, and that DeLong intended to acquire ownership of the yard (either in his own name or jointly with corporations owned or controlled by him) within the next 60 days. At that time the shipyard was owned by the United States.

As a result of the negotiations, on March 14,1952, DeLong entered into a cost-plus-fixed-fee contract with the Transportation Corps of the Army, which contract was dated February 1, 1952, and was assigned No. DA44-177-TC-96.

The contract provided for the construction of four barges, 500 feet in length, the largest steel barges ever constructed in the. United States. At the time of drafting the contract, it was the consensus of both parties, and a fact, that Wainwright Shipyard at Panama City was the only shipyard available for such construction. Accordingly, the Chief of Staff of the Department of the Army in a memorandum to the Chief of the Transportation Corps, required that approval of the contract would be contingent upon the contractor having available the Wainwright Shipyard facilities.

[291]*291To comply with this requirement DeLong negotiated with the Seaboard Machinery Corporation, the then lessee of a portion of the Wainwright Shipyard, for Seaboard to obtain a lease for the remainder from the General Services Administration. Seaboard then leased from the United States and DeLong subleased from Seaboard the facilities of said shipyard. Both the lease and the sublease were dated March 14, 1952, and contained identical 90-day cancellation clauses.

Article II of the lease from Seaboard recited that the purpose for which the facilities were leased was for construction, outfitting, assembly and other related purposes of the equipment, materials, items and services described in the contract now being considered, which contract was executed subsequently but on the same day as the aforementioned leases. The contract bears the date of February 1, 1952.

First Modification, Supplemental Agreement No. 1 to the contract, dated March 14, 1952, resulted and provided in pertinent part as follows:

1. The Contractor represents, as an inducement to the Government to award the Principal Contract, that the facilities of the Wainwright Shipyard, Panama City, Florida, are available to the Contractor for the performance of the Principal Contract and will be available during all of the time required for its performance. It is understood that this representation of availability of facilities is subject to any and all provisions of Federal Law, Executive Order and applicable Federal regulations relating to National Industrial Reserve Properties.
2. That the Contractor will not be reimbursed under the provisions of the Principal Contract for any cost incurred in the performance of the contract for any major repair or rehabilitation of the Wainwright Shipyard.

. Supplemental Agreement No. 2 to the contract, dated April 25, 1952, reduced the length of the barges from 500 feet to 427 feet each. Supplemental Agreement No. 2 reads as follows:

THIS SUPPLEMENTAL AGREEMENT NO. 2 entered into this 25th day of April 1952 by and between the UNITED STATES OF AMERICA (hereinafter referred to as the “Government”), represented by the Research Contracting Officer executing (this Supplemental Agreement (hereinafter referred to as the [292]*292“Contracting Officer”) and LEON B. DELONG;, an individual trading as DeLong Engineering and Construction Company (hereinafter referred to as the “Contractor”):

WITNESSETH THAT:

WHEREAS, under date of 1 February 1952, the parties hereto entered into Contract No. DA 44-177-TC-96 (hereinafter referred to as the “Contract”) for the construction of certain self-elevating barges at .a total estimated cost of Fourteen Million Nine Hundred Five Thousand Dollars ($14,905,000.00); and
WHEREAS, in order to comply with the conditional approval of the contract by the Assistant Chief of Staff, G-4, Department of the Army, the parties executed a first modification to the contract providing, inter alia, that the Contractor represented that the facilities of the Wainwright Shipyard, Panama City, Florida, were available to the Contractor for the performance of the contract, and that the Contractor would not be reimbursed for any costs incurred in any major repair or repair or rehabilitation of such yard; and
WHEREAS, subsequent to the execution of the contract, the parties have agreed to reduce the length of certain of the barges required to be produced, under the contract from 500 feet to approximately 427 feet, such reduction in length resulting from engineering studies made subsequent to the execution of the contract; and
WHEREAS, the Contractor has represented that the reduction in the length of the barges has made it more feasible to produce such barges in shipyards other than the Wainwright Shipyard at Panama City, Florida, because of in cost and of production; and
WHEREAS, by reason of the reduction in the length of the barges and the consequent decrease in the amount of work to be performed by the Contractor under the contract, the parties have negotiated an equitable adjustment of the fixed fee provided to be paid the Contractor under the contract, but that because of increase in cost of certain materials, the total estimated cost exclusive of fee, shall remain and
WHEREAS, the parties desire to amend the contract to reflect all of such and
WHEREAS, this Supplemental Agreement No. 2 is deemed to be in the best interest of the Government and is authorized by the Armed Services Procurement Act of 1947 (Public Law 413, 80th Congress);

[293]*293NOW, THEREFORE, the parties hereto do mutually agree as follows:

1. Clause 1, Statement of Work, Item 1 b. and Item 2 are hereby amended to provide that barges provided in the contract to be of 500-foot length shall be approximately 427 feet in length, and that such barges shall be equipped with such numbers of caissons, air jacks, mechanical grippers, air compresors, welders, cranes and other equipment and machinery as may be approved or directed by the Research Contracting Officer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SWR, Inc.
Armed Services Board of Contract Appeals, 2014
Coley Properties Corp. v. United States
593 F.2d 380 (Court of Claims, 1979)
Lockheed Aircraft Corporation v. The United States
375 F.2d 786 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
175 F. Supp. 169, 146 Ct. Cl. 289, 1959 U.S. Ct. Cl. LEXIS 159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delong-v-united-states-cc-1959.