Racine Screw Co. v. United States

156 Ct. Cl. 256, 1962 U.S. Ct. Cl. LEXIS 54, 1962 WL 9283
CourtUnited States Court of Claims
DecidedFebruary 7, 1962
DocketNo. 227-56
StatusPublished
Cited by7 cases

This text of 156 Ct. Cl. 256 (Racine Screw Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Racine Screw Co. v. United States, 156 Ct. Cl. 256, 1962 U.S. Ct. Cl. LEXIS 54, 1962 WL 9283 (cc 1962).

Opinion

Per Curiam:

The Ordnance Department of the Army on June SO, 19'50, awarded plaintiff company a contract for 130,000 shells to be produced for and delivered to the United States. With immaterial exceptions the company failed to produce and deliver the shells. Before the departmental agencies and thereafter in this court the company attributed the failure primarily to a national steel shortage, and to other secondary causes. However, after the end of the delay due to the steel shortage the company still failed to produce and deliver the shells within a time extended to make up for that delay. The Government terminated the contract for default, and claimed liquidated damages under its terms, plus a small amount, the claim for which was later withdrawn, as the excess cost due to the actual difference of price upon reprocurement.1 The company denied default and [258]*258asserted that the United States owed it $47,874.29, as the amount it had expended and which was not repaid to it. In its present suit the plaintiff’s claim is stated to amount to $43,029.17. The United States denied any liability to plaintiff and has counterclaimed in the present suit for $29,264.98, the final amount which had been recomputed administratively as liquidated damages. The departmental administrative decisions had been adverse to the company as to all matters except with respect to the delay due to the steel shortage, for which due allowance was made.

We agree with the findings of the Commissioner that “the evidence does not establish and the plaintiff has not alleged that the administrative decisions in the'case on matters of fact were fraudulent, capricious, arbitrary, or so grossly erroneous as necessarily to imply bad faith; or that such decisions are not supported by substantial evidence.”

We find no merit in plaintiff’s challenge to the validity of the report of the Commissioner on the ground that the Commissioner did not conduct the hearing.

On the basis of the foregoing, plaintiff is not entitled to recover and its petition will be dismissed. The United States is entitled to judgment on its counterclaim in the sum of $29,264.98. Judgment will be entered accordingly.

It is so ordered.

FINDINGS OF FACT

The court, having considered the evidence, the report of Trial Commissioner Richard Arens, and the briefs and argument of counsel, makes findings of fact as follows:

1. The plaintiff, Racine Screw Company, is a Wisconsin corporation with its principal place of business in Racine, Wisconsin.

2. Under date of May 25,1950, there was issued by Frank-ford Arsenal, Department of the Army, Ordnance Department, located in Philadelphia, an invitation for bids for furnishing 130,000 semi-finished 57 mm shell at a unit price of $.958, with a total price of $124,540. The invitation for bids provided that the bids would be received until June 14, 1950, at which time they would be publicly opened.

[259]*2593. The Continuation Schedule attached to the invitation to bids, and to which the bids were subject, provided in part as follows:

DELIVERY: F.O.B. Frankford Arsenal.
10,000 Shell on or before the first week of August 1950, a minimum of 12,000 Shell each week thereafter until completion.
Five (5) weeks after receipt of order 10,000 Shell and 12,000 per week thereafter until completion.
Time will be a material factor for the purpose of comparing bids. There will be added to each bid, other than the one offering to complete in the shortest time, provided the shortest time is m excess of the time set forth in the Invitation for delivery, an amount equal to the daily liquidated damages named in the Invitation for Bids multiplied by the number of calendar days that such bidders have named for performance of the work in excess of the days named by the bidder proposing to do the work in the shortest time.
Inspection and preliminary acceptance at Contractor’s Plant by the Ordnance District in which Contractor’s Plant is located. Title to vest in the Government upon delivery and final acceptance at destination.
All Bidders must supply Bid Bonds in the amount of 10%. Successful Contractor will be required to supply Performance Bond in the amount of 20%.
The successful Contractor will be required to deliver the minimum quantity of 130,000 each. The maximum quantity that will be accepted is 131,000 each, when caused by conditions of loading, shipping, packing, or allowances in manufacturing processes, and payments shall be adjusted accordingly.
Prior to the execution of this contract, the contractor will furnish a certified or photostatic copy of its Certificate of Registration with the Department of State, ■which copy shall be attached to the copy of this contract on file in the Office of the chief of the procuring service concerned.

The evidence does not reveal the date of the registration by the plaintiff with the Department of State (as a manu[260]*260facturer of arms) but the Certificate of Registration issued to the plaintiff provided that the Certificate “is valid for five years from August 22,1950.”

4. The Continuation Schedule also provided in part as follows:

The contractor shall be required to submit to F.A. prior to start of production, 100 Shell that are representative of the contractors production and have been inspected and accepted by the Area Ordnance District.

The Area Ordnance District in which the plaintiff was located was the Chicago Ordnance District, Department of the Army, with headquarters in Chicago.

5. Under date of June 12,1950, the plaintiff submitted its bid to Frankford Arsenal in accordance with the terms of the invitation for bids which it had received.

6. The body of a letter, dated June 30, 1950, addressed to the plaintiff from Frankford Arsenal reads as follows:

This is to inform you that Contract DA-36-231ORD-962 dated 30 June 1950 is being assigned to you in connection with your bid against F.A. Invitation 50-304 for 130,000 Shells, 57 M/M M307 at .958 each or a total of $124,540.00.
The definitive instrument is being withheld subject to the receipt of your Performance Bond in the sum of 20%.
Please expedite the bond so that the contract may be executed and mailed to you.

7. A letter, dated July 22, 1950, addressed to the plaintiff from Frankford Arsenal reads in part as follows:

There is inclosed herewith your executed triplicate copy of Invitation for Bid No. ORD-36-038-50-304.
Item No. One (1) has been awarded to you and Contract No. DA-36-038-ORD-962 assigned thereto.

The award as returned to the plaintiff from Frankford Arsenal was dated June 30,1950.

8. Except for the shell which the plaintiff submitted to Frankford Arsenal for inspection prior to authorization to proceed with production, the plaintiff failed to deliver any of the 130,000 shell which it was required by the contract to produce and deliver to Frankford Arsenal. The plaintiff contended before the Armed Services Board of Contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
J.F. Whalen & Company v. The United States
895 F.2d 1422 (Federal Circuit, 1990)
Martin J. Simko Construction, Inc. v. United States
33 Cont. Cas. Fed. 74,888 (Court of Claims, 1986)
Peterson-Sharpe Engineering Corp. v. United States
32 Cont. Cas. Fed. 72,873 (Court of Claims, 1984)
S. N. T. Fratelli Gondrand v. United States
166 Ct. Cl. 473 (Court of Claims, 1964)
Anthony P. Miller, Inc. v. United States
161 Ct. Cl. 455 (Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
156 Ct. Cl. 256, 1962 U.S. Ct. Cl. LEXIS 54, 1962 WL 9283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/racine-screw-co-v-united-states-cc-1962.