Automatic Screw Products Company v. United States
This text of 169 F. Supp. 951 (Automatic Screw Products Company v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
This is a suit by petitioner, Automatic Screw Products Company, who had a contract entered into June 18, 1951, to supply the United States certain army shells at a fixed price. Petitioner alleged the United States prevented performance of ■the contract by various failures to inspect plaintiff’s product and practices and by demanding in October an acknowledgment of plaintiff’s insolvency before allowing plaintiff to sell certain machinery not utilized in performance of the contract. In order to be allowed to continue said sale, it is alleged one of petitioner’s officers signed a statement “acknowledging insolvency.” Plaintiff further alleges the United States, desiring to take possession of certain steel acquired by petitioner to perform the contract, terminated the contract “for the convenience of the Government” and replevied the steel. Plaintiff states the letter of termination of November 20,. 1951, contained the following language:
“By reason of the above and pursuant to condition 11 — Default—of the subject contract, the government hereby terminates your right to deliver the undelivered balance of 129,-250 units. The said quantity of 129,250 units which you have failed! to deliver will be procured in the open market against your account, and you will be held liable for any excess costs.”
The phrase “By reason of the above,” refers to the preceding paragraph of the letter of termination, reading as set out in note 2, paragraph 2.
Plaintiff alleges that its failure to complete the contract was “due to causes beyond [its] control and without the fault or negligence of the petitioner” and prays judgment for $62,702.13, lost in attempted performance and costs.
The allegations of the preceding paragraph would, if true, bring the termination within the terms of the default clause of the contract, Article 11:
'“(a) The Government may, subject to'the provisions of paragraph (b) below, by written Notice of Default to the Contractor terminate the whole or any part of this contract in any one of the following circumstances :
“(i) if the Contractor fails to make delivery of the supplies or to perform the services within the time *953 specified herein or any extension thereof;
******
“(b) The Contractor shall not be liable for any excess costs if any failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. * * *
******
“(e) If, after notice of termination of this contract under the provisions of paragraph (a) of this clause, it is determined that the failure to perform this contract is due to causes beyond the control and without the fault or negligence of the Contractor pursuant to the provisions of paragraph (b) of this clause, such Notice of Default shall be deemed to have been issued pursuant to the clause of this contract entitled “Termination for Convenience of the Government;” and the rights and obligations of the parties hereto shall in such event be governed by such clause.” 1
It is not necessary, however, to pass upon these allegations which are denied by the Government’s answer for we conclude that the Government’s motion for summary judgment on the ground that plaintiff did not exhaust its administrative remedies under the contract should be sustained. Under Article 12 of the contract — Disputes—this provision appears:
“Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. Within 30 days from the date of receipt of such copy, the Contractor may appeal by mailing or otherwise furnishing to the Contracting Officer a written appeal addressed to the Secretary, and the decision of the Secretary or his duly authorized representative for the hearing of such appeals shall be final and conclusive: Provided, That if no such appeal is taken, the decision of the Contracting Officer shall be final and conclusive. * * * ”
On November 20, 1951, the Government terminated the contract by letter to the plaintiff, as set out below. 2 After a dispute over the Government’s right to take possession of steel acquired by a Government advance, ending in a consent stipulation by plaintiff in a replevin action by the Government to secure the steel, the Government again computed finally the accounts under the contract between the plaintiff and itself, and notified the plaintiff on October 12, 1954, that it was indebted to the United States in the *954 amount of $3,170.94. Demand was made for payment. This is the amount of the Government’s counterclaim. The account was determined as a result of a claim letter from the plaintiff of September 28, 1954. This ruling of October 12, 1954, determined by the “Contracting Officer” as required by Article 12, stated it also was a finding of fact under the Disputes article of the contract. We think it was.
The interchange of letters attempting to settle accounts between plaintiff and defendant contained full statements of charges and credits and contradictory claims of balances due. No issue was then raised as to plaintiff’s freedom from fault or negligence. Had such an issue been raised at the casting of accounts in the terms of plaintiff’s allegations, its resolution would have concerned “a question of fact” under Article 12, Disputes, supra at note 1. 3
Thereafter a notice of appeal to the Secretary of the Army was filed, notarized July 1, 1955. This was dismissed by order of November 26, 1956. The order contained this explanation:
“This Board has uniformly and consistently held that it is without authority to extend the period of time fixed by the contract terms, within which the appellant may appeal from decisions of contracting officers. The evidence discloses that appellant failed to appeal from the contracting officer's decision which was received by it on 15 October 1954 until more than 8 months .thereafter, on 1 July 1955, whereas the contract terms unequivocally provided that an appeal be taken within 30 days.”
There is nothing in the record to justify plaintiff’s claim that negotiations between the parties extended its time to appeal.
We hold that the contract provision for the settlement of disputes concerning facts is a valid provision for deciding these factual questions. It affords a prompt means for adjustment of factual disputes advantageous to both parties and is exclusive. United States v. Joseph A. Holpuch Co., 328 U.S. 234, 239, 66 S.Ct. 1000, 90 L.Ed. 1192. See also Stiers Bros. Construction Co. v. United States, 109 Ct.Cl. 353, 388; John J. Harte Co. v. United States, 97 F.Supp. 753, 117 Ct.Cl. 309.
Free access — add to your briefcase to read the full text and ask questions with AI