Lebolo-Watts Constructors v. Secretary of the Army

CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 18, 2022
Docket21-1749
StatusUnpublished

This text of Lebolo-Watts Constructors v. Secretary of the Army (Lebolo-Watts Constructors v. Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lebolo-Watts Constructors v. Secretary of the Army, (Fed. Cir. 2022).

Opinion

Case: 21-1749 Document: 42 Page: 1 Filed: 02/18/2022

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit ______________________

LEBOLO-WATTS CONSTRUCTORS 01 JV, LLC, Appellant

v.

SECRETARY OF THE ARMY, Appellee ______________________

2021-1749 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in Nos. 59740, 60378, 60459, 60507, 60508, Adminis- trative Judge J. Reid Prouty, Administrative Judge Reba Page, Administrative Judge Richard Shackleford. ______________________

Decided: February 18, 2022 ______________________

HERMAN MARTIN BRAUDE, Braude Law Group, P.C., Rockville, MD, argued for appellant.

DANIEL B. VOLK, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washing- ton, DC, argued for appellee. Also represented by BRIAN M. BOYNTON, MARTIN F. HOCKEY, JR., PATRICIA M. MCCARTHY. ______________________ Case: 21-1749 Document: 42 Page: 2 Filed: 02/18/2022

Before LOURIE, BRYSON, and CUNNINGHAM, Circuit Judges.

BRYSON, Circuit Judge. In this appeal, Lebolo-Watts Constructors 01 JV, LLC, (“Lebolo”) seeks compensation for costs associated with the performance of a contract to construct a satellite communi- cations operations center at Fort Meade, Maryland. The appeal includes a claim by Lebolo on its own behalf and pass-through claims that Lebolo submitted on behalf of two of its subcontractors, Worch Electric Inc. (“Worch”) and Warner Mechanical Corporation (“Warner”). The Armed Services Board of Contract Appeals denied compensation as to all three claims, and this appeal followed. We affirm. I A On November 24, 2010, the U.S. Army Corps of Engi- neers published a contract solicitation for construction of the Wideband Satellite Communication Operations Center (“WSOC”) at Fort Meade, Maryland. J.A. 379. In addition to the construction of the WSOC building, the contract called for the construction of a new electrical substation. J.A. 2. The new substation would receive power from ex- isting electrical switchgear in another building known as “Building 8905” and would provide power to the WSOC building. Id. The solicitation for the WSOC contract included Draw- ing No. EP 601, which depicted the existing switchgear in Building 8905. J.A. 10478. That drawing was subse- quently revised, and on December 20, 2010, it was issued as part of an amendment to the solicitation. J.A. 478. The drawing indicated that the contractor was to use spare cu- bicles five and ten in Building 8905 to connect to the Case: 21-1749 Document: 42 Page: 3 Filed: 02/18/2022

LEBOLO-WATTS CONSTRUCTORS v. SECRETARY OF THE ARMY 3

existing switchgear and to provide power to the new sub- station. J.A. 10435. Drawing No. EP 601 depicted two circuit breakers, one in cubicle five and one in cubicle ten, in bold font. Id. Other circuit breakers depicted in the drawing were shown in light gray font. Id. As found by the Board, the typical con- vention is that bolded items on a drawing represent new work to indicate to the contractor what is within the con- tract’s scope of work. J.A. 79–80, 11687. In addition to the bolded items, the drawing included four notes. The first note relevant here, note two, required the contractor to “furnish and install 1 set of 3 #2/0-AWG- C and 1 #6-AWG-G.” J.A. 10435. The second note relevant here, note four, stated that the “circuit breaker installed in the existing switchgear shall be compatible with the exist- ing switchgear,” and that such work should be included “in the coordination study.” Id. Neither the drawing nor the contract specifications explicitly stated whether the gov- ernment or the contractor was to furnish the circuit break- ers to be used in cubicles 5 and 10. Lebolo submitted a bid and was ultimately awarded the WSOC contract. In January 2013, after work had be- gun on the contract, representatives of Lebolo and the gov- ernment visited Building 8905. During the visit, it became clear that the government’s position was that Lebolo was responsible for furnishing the two circuit breakers referred to in Drawing No. EP 601. J.A. 11679. On March 15, 2013, Lebolo directed one of its contractors, Enterprise Electric Company (“Enterprise”), to “furnish and install th[o]se breakers.” J.A. 2370. Enterprise did not obtain the circuit breakers and deliver them to Building 8905 until June 11, 2013, causing a delay in the project. J.A. 7966. Additional delays continued to impact the project after the delivery of the circuit breakers. For instance, Lebolo repeatedly notified Worch of deficiencies in its work from May through December 2013. J.A. 36–39. Lebolo also Case: 21-1749 Document: 42 Page: 4 Filed: 02/18/2022

charged Enterprise with having caused delay on the project starting in May 2013 and running through April 2014. J.A. 48–49; Lebolo-Watts Constructors 01 JV, LLC, ASBCA Nos. 59740, 60378, 60459, 60507, 60508, Transcript of Oct. 11, 2017, Hearing at 172–74. In addition, it was discovered that the relays in the existing switchgear were not compat- ible with the new circuit breakers. The government then obtained and furnished new relays that were compatible with the circuit breakers, resulting in a delay in contract completion. J.A. 40–41, 11709. Another period of delay of 18 days resulted from issues with the existing differential relays in Building 8905 and out-of-phase conductors at the existing substation. Lebolo-Watts Constructors 01 JV, LLC, ASBCA Nos. 59740, 60378, 60459, 60507, 60508, R4, tab 338 (“Ockman Rep.”) at 40–42. Permanent power was finally made available at the new substation on December 19, 2013. J.A. 48. Throughout the contract, Lebolo negotiated several contract modifications with the government to extend the completion date on the contract and to compensate Lebolo for various delays. In one of those modifications, Modifica- tion No. A00016, the government compensated Lebolo for, among other things, installing the new relays that the gov- ernment furnished for use in the existing switchgear. J.A. 5453. That modification included a release for all claims “on behalf of the Contractor and its Subcontractors and Suppliers . . . for all delays related thereto.” Id. at 5454. Another modification, Modification No. P00030, pro- vided Lebolo monetary compensation and a time extension for various delays associated with “power delays and sub- station changes.” J.A. 1112. The release language in that modification was very similar to the release language in Modification No. A00016, except that Modification No. P00030 did not specifically reference the claims of Lebolo’s Case: 21-1749 Document: 42 Page: 5 Filed: 02/18/2022

LEBOLO-WATTS CONSTRUCTORS v. SECRETARY OF THE ARMY 5

subcontractors. 1 Id. A contemporaneous email exchange between Lebolo and the government indicated that Lebolo intended to reserve the rights of its subcontractors to bring a delay claim for the issues addressed by Modification No. P00030. See J.A. 5979–83. B After the completion of the project, Lebolo raised sev- eral claims to the contracting officer. When those claims were denied or not acted upon, Lebolo appealed to the Armed Services Board of Contract Appeals. Three claims are relevant to this appeal. Lebolo sub- mitted one claim seeking compensation for the circuit breakers that it furnished for use in Building 8905. In the other two claims, which Lebolo submitted on behalf of Worch and Warner, Lebolo sought compensation for losses suffered by those subcontractors due to the delay in estab- lishing permanent power at the new substation. With respect to Lebolo’s claim regarding the circuit breakers, the Board held that the contract required Lebolo to provide the circuit breakers, J.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mountain Home Contractors v. United States
425 F.2d 1260 (Court of Claims, 1970)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Sharp Electronics Corporation v. Army
707 F.3d 1367 (Federal Circuit, 2013)
Premier Office Complex of Parma, LLC v. United States
916 F.3d 1006 (Federal Circuit, 2019)
Per Aarsleff A/S v. United States
829 F.3d 1303 (Federal Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Lebolo-Watts Constructors v. Secretary of the Army, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lebolo-watts-constructors-v-secretary-of-the-army-cafc-2022.