Adserballe & Knudsen A/S v. Facilities Development Corporation

Court of Appeals for the Fourth Circuit·Decided April 10, 2026·No. 25-1604·Unpublished

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 25-1604

ADSERBALLE & KNUDSEN A/S, Plaintiff – Appellee,

v.

FACILITIES DEVELOPMENT CORPORATION, Defendant – Appellant.

Appeal from the United States District Court for the Eastern District of Virginia, at Alexandria. Claude M. Hilton, Senior District Judge. (1:24-cv-02062-CMH-WBP)

Submitted: November 17, 2025 Decided: April 10, 2026

Before KING, HARRIS, and RICHARDSON, Circuit Judges.

Affirmed by unpublished opinion. Judge Harris wrote the opinion, in which Judge King and Judge Richardson joined.

ON BRIEF: Christopher J. Norris, Miami, Florida, Emil Hirsch, Lauren K. Ierardi, CARLTON FIELDS, P.A., Washington, D.C., for Appellant. James E. Berger, Charlene C. Sun, New York, New York, Cooper C. Millhouse, DLA PIPER LLP (US), Washington, D.C., for Appellee.

Unpublished opinions are not binding precedent in this circuit.

PAMELA HARRIS, Circuit Judge:

Facilities Development Corporation, a United States company, subcontracted with Danish construction company Adserballe & Knudsen A/S for work on a United States government construction project in Denmark. A dispute between the parties went to arbitration, and Adserballe & Knudsen A/S, the Danish subcontractor, now seeks to enforce the foreign arbitral award against Facilities Development Corporation.

In support of enforcement, Adserballe & Knudsen A/S invokes the New York Convention, a treaty that provides, with limited exceptions, for the recognition and enforcement of foreign arbitral awards. Facilities Development Corporation responds by invoking two of those exceptions: the public policy exception and the exception for improperly composed arbitral tribunals. The district court found that neither exception applied and granted the petition to enforce. We agree with the district court’s ruling and affirm its judgment.

I.

Facilities Development Corporation (“Facilities”), a Virginia company, contracted with the Department of State to renovate the United States Embassy in Copenhagen, Denmark. It then subcontracted with Adserballe & Knudsen A/S (“A&K”) to do construction work on the embassy project. The agreement between Facilities and A&K (the “Agreement”) incorporated a set of contract terms widely used in the Danish construction industry, known as AB 92. It also provided that all disputes under the

Agreement would be settled by the construction arbitration court in Copenhagen, pursuant to AB 92’s provisions for binding arbitration.

During the parties’ engagement, a series of disputes arose as to whether the Agreement incorporated not only the Danish contracting regulations but also United States regulations – specifically, the Federal Acquisition Regulations and Department of State Acquisition Regulations, referred to collectively as “FAR/DOSAR.” Facilities believed A&K was failing to comply with FAR/DOSAR and, accordingly, withheld payment to A&K; A&K insisted it was not bound by those requirements and demanded payment. Consistent with the Agreement, the parties brought their dispute to the Danish construction arbitration court.

To hear the dispute, the arbitration court appointed a tribunal of three members pursuant to the agreed-upon AB 92 arbitration rules. The tribunal ruled in favor of A&K, finding that the Danish contracting regulations – not FAR/DOSAR –governed the parties’ legal relationship. Accordingly, it held Facilities in breach of the Agreement and ordered payment of damages and costs to A&K.

When Facilities refused to pay, A&K filed a petition to confirm and enforce its arbitral award in federal court in Virginia, pursuant to what is known as the New York Convention. See Convention on the Recognition of Foreign Arbitral Awards, June 10, 1958, 21 U.S.T. § 2517 (adopted at 9 U.S.C. § 201 et seq.). The New York Convention allows a party to a foreign arbitration to petition a United States court for an order confirming an arbitral award against the other party. 9 U.S.C. § 207. And it requires federal courts to confirm such an award unless a court “finds one of the grounds for refusal

or deferral of recognition or enforcement of the award specified in” the Convention itself. Id.

Facing A&K’s petition, Facilities invoked two such grounds for refusal. The first – the so-called “public policy” exception – applies where “recognition or enforcement of the award would be contrary to the public policy of” the United States. New York Convention, art. V(2)(b). According to Facilities, the federal FAR/DOSAR regulations reflect a “well- defined and dominant” public policy of the United States, and it would violate that policy to enforce an arbitral award that failed to apply FAR/DOSAR to work on a federal government contract. The second exception permits refusal where the “composition of the arbitral authority . . . was not in accordance with the agreement of the parties.” Id. art. V(1)(d). Here, Facilities argued that the tribunal was improperly composed because the two “expert” members required by AB 92’s arbitration rules lacked proficiency in United States government contracting law under FAR/DOSAR.

The district court disagreed on both counts. See Order, A&K v. Facilities, No. 1:24-

cv-2062 (E.D. Va. May 8, 2025), ECF No. 38 (reprinted at J.A. 1034–41). On public policy, the court rejected Facilities’ claim that confirming an award that failed to apply United States contracting rules to the subcontract in question would violate this country’s public policy, distinguishing the out-of-circuit authority advanced by Facilities. Facilities’ real objection, as the district court saw it, was to the merits of the arbitral tribunal’s decision, unreviewable in this posture.

As for the composition of the arbitral tribunal, the district court found it consistent with the parties’ arbitration agreement, which provided for two “experts” to be appointed

by the arbitration court “on a case-by-case basis, depending upon the nature of the dispute.” J.A. 1040 (quoting AB 92 § 47(4)). The arbitration court appropriately exercised its discretion in appointing “experts” in Danish law – rather than the FAR/DOSAR experts sought by Facilities – given its interpretation of the Agreement as calling for application of Danish and not United States contracting law.

Accordingly, the district court granted A&K’s petition to enforce the award and entered judgment for A&K. Facilities timely appealed.

II.

This court reviews the confirmation of a foreign arbitral award de novo and the district court’s factual findings for clear error. AO Techsnabexport v. Globe Nuclear Servs. & Supply GNSS, Ltd., 404 F. App’x 793, 797 (4th Cir. 2010) (citing Raymond James Fin. Servs., Inc. v. Bishop, 596 F.3d 183, 190 (4th Cir. 2010)). A federal court’s review of a foreign arbitration award is limited: When an award “is taken to another country for confirmation and enforcement, the issues in dispute and the relief granted are treated as fully resolved.” Est. of Ke v. Yu, 105 F.4th 648, 654 (4th Cir. 2024) (explaining New York Convention procedures and policy). And we remain mindful that the New York Convention is intended to “encourage the recognition and enforcement of commercial arbitration agreements.” Id. at 655 (citation omitted).

On appeal, Facilities raises the same two exceptions to enforcement under the New York Convention that it advanced before the district court. 1 And for substantially the reasons given by the district court, we find those arguments unavailing.

Free access — add to your briefcase to read the full text and ask questions with AI

Adserballe & Knudsen A/S v. Facilities Development Corporation, (4th Cir. 2026).

Adserballe & Knudsen A/S v. Facilities Development Corporation (Adserballe & Knudsen A/S v. Facilities Development Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Raymond James Financial Services, Inc. v. Bishop
596 F.3d 183 (Fourth Circuit, 2010)
K-Con, Inc. v. Secretary of the Army
908 F.3d 719 (Federal Circuit, 2018)