Applied Devices Corp. v. United States

591 F.2d 635, 25 Cont. Cas. Fed. 83,047, 219 Ct. Cl. 109, 1979 U.S. Ct. Cl. LEXIS 16
CourtUnited States Court of Claims
DecidedJanuary 24, 1979
DocketNo. 469-77
StatusPublished
Cited by18 cases

This text of 591 F.2d 635 (Applied Devices Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Applied Devices Corp. v. United States, 591 F.2d 635, 25 Cont. Cas. Fed. 83,047, 219 Ct. Cl. 109, 1979 U.S. Ct. Cl. LEXIS 16 (cc 1979).

Opinion

NICHOLS, Judge,

delivered the opinion of the court:

This case is before the court on cross-motions for summary judgment. Plaintiff seeks a Wunderlich Act (41 U.S.C. §§ 321, 322) review of an adverse decision of the Armed Services Board of Contract Appeals (ASBCA), styled Appeal of Applied Devices Corp., ASBCA No. 18384, 77-1 BCA ¶ 12,347 (January 7, 1977). A second count seeks equitable reformation of the contract. Our trial judge deemed the issues to be limited to issues of law, and so informed the court (Rule 166 (b)). Therefore, we have not the benefit of a recommended decision by him as is more usual in such cases. Our conclusion, after briefing and oral argument, including an amicus brief on behalf of RCA Corporation and a government response thereto on the Wunderlich Act review, is that we agree with the ASBCA and find its decision free from legal error, not arbitrary or capricious, and supported by substantial evidence. So far as the claim is one for equitable relief, the claim is submitted on the administrative record, enabling us to dispose of it in this opinion, as we do. There is no triable issue of relevant fact. We hold that plaintiff is entitled to equitable reformation of the contract.

I

Plaintiff, a New York corporation in the electronics industry, bid on a formally advertised invitation proposing a three-step multi-year procurement, the legal incidents of which frame the issues here. Plaintiff offered to supply aircraft carrier radar systems, the specifications for which [113]*113required considerable one-time design and starting expense. Delivery was to be in three annual installments, 5, 9, and 15 systems for fiscal years 1968, 1969, and 1970, respectively.

The contract terms required by ASPR § 1.322, and relied on by the board, are set forth as Appendix A to this opinion. They attempt to provide a means whereby a contract to be performed over a period of years may be awarded, obtaining the economies of volume purchasing, without obligating the entire contract price. To make a contract obligating funds not yet appropriated is normally illegal, even criminal. 41 U.S.C. § 11, 31 U.S.C. § 665. Exemptions by statute are sometimes obtained, where a long-term job is a necessity and Congress perceives the absurdity of having to appropriate the entire cost before the contract is even awarded. This was the case, e.g., in two recent decisions involving construction contracts, S. A. Healy Co. v. United States, 216 Ct. Cl. 172, 576 F.2d 299 (1978); C. H. Leavell & Co. v. United States, 208 Ct. Cl. 776, 530 F.2d 878 (1976). The provision in a supply contract, as here, for installment delivery of multiple units over several years, is not so obvious a case for exemption, and yet we may assume that the aggregate cost would have been greater if separate contracts for each years’ deliveries had been awarded. ASPR in § 1.322 attempts to provide needed legal machinery without help from any special legislation. The award of the contract obligates funds only for the first "program year.” Funds are obligated for later years, and the contractor’s obligation to perform comes alive, only upon a formal notice within a specified time that funds have become available. The economy in unit prices is achieved, however, only if the contractor expects to amortize his design and start up costs over the entire job. A stoppage due to lack of available funds, as for any other reason, would leave the contractor with costs unabsorbed by the prices for units already delivered, and, therefore, a "cancellation charge” is provided for, but it is subject to a "cancellation ceiling” to be agreed upon. In the event of any stoppage covered by the "cancellation charge” any additional compensation under the standard Termination Article is unavailable. Presumably the cancellation ceiling is deemed to obligate the funds needed to cover it, additional to the other obligations. Section l-322.2(e).

[114]*114Here the "cancellation ceiling” in the event that occurred, unavailability, according to defendant, of funds for the 1970 installment, was but three percent of the total contract price. The figure was not negotiated but was prescribed by defendant, take it or leave it. The plaintiff bid, knowing that in the event of a 1970 cancellation the unabsorbed costs would much exceed three percent, indeed be more than double, but it went ahead and executed the contract, for reasons dealt with in the findings. It seems to have supposed it would be most unlikely it would have to rely on a cancellation charge to cover its costs as it deemed a failure by Congress to make funds available to be highly improbable, and did not take into account that funds made available by Congress might become unavailable "to the contracting officer” by decisions made elsewhere. The board found that defendant, for its part, in prescribing the three percent figure failed to estimate the nonrecurring initial costs in a realistic manner as ASPR l-322.2(d) and (e) required. (The references in 1968 were l-322.2(c) and (d)). It used a rule of thumb formula having no relation to the facts of the case. We can assume for purposes of our decision that defendant’s officers simply violated plaintiffs entitlement to a realistic figure. Thus the errors and misconceptions of both sides set up the controversy we are to adjudicate.

Defendant found the necessary funds for 1969, and Congress appropriated funds that could have been used for 1970. However, the number of aircraft carriers in commission was being sharply reduced, and because of this it was decided to modernize existing radar of several carriers with "conversion kits” in lieu of the new systems plaintiff would have furnished in the 1970 installment. Accordingly, the Naval Electronics Systems Command (NAVELEX), to which cognizance of the contract had been transferred, concluded there was no "requirement” for the 1970 installment, and the board found as a fact, with this support of substantial evidence, that there was none. The board concluded that funds were not available to the contracting officer for the somewhat curious reason that he made no request for them. He advised plaintiff that the "1970 buy” would not be exercised. We think it is a fair inference from the evidence that the contracting officer did [115]*115not request the funds because he knew that if he did request them, they would be refused. Funds would not be allotted for a nonexistent requirement. The exact statutory appropriation item is not given; we assume it was a general item available for other purposes than plaintiffs radar, so NAVELEX was in no way compelled by the appropriation language to spend the money for the "1970 buy,” or let it lapse. We also assume, there being no finding to the contrary, that the funds in fact lapsed by nonuse and were not diverted to other procurement.

Plaintiff of course does not argue the Navy should have funded a nonexistent requirement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fuel Tank Maintenance Company, LLC
Armed Services Board of Contract Appeals, 2025
Lee's Ford Dock, Inc.
Armed Services Board of Contract Appeals, 2016
Todd Construction, L.P. v. United States
94 Fed. Cl. 100 (Federal Claims, 2010)
Gould, Inc. v. United States
66 Fed. Cl. 253 (Federal Claims, 2005)
Hermes Consolidated, Inc. v. United States
58 Fed. Cl. 3 (Federal Claims, 2003)
Gold Line Refining, Ltd. v. United States
54 Fed. Cl. 285 (Federal Claims, 2002)
Northrop Grumman Corp. v. United States
47 Fed. Cl. 20 (Federal Claims, 2000)
Barrow Utilities & Electric Cooperative, Inc. v. United States
36 Cont. Cas. Fed. 75,840 (Court of Claims, 1990)
Gould, Inc. v. United States
36 Cont. Cas. Fed. 75,781 (Court of Claims, 1990)
Beta Systems, Div. of Velcon Filters, Inc. v. United States
35 Cont. Cas. Fed. 75,613 (Court of Claims, 1989)
Paragon Energy Corp. v. United States
645 F.2d 966 (Court of Claims, 1981)
Standard-Southern Corp.
650 F.2d 286 (Court of Claims, 1980)
1776 K Street Associates v. United States
602 F.2d 354 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
591 F.2d 635, 25 Cont. Cas. Fed. 83,047, 219 Ct. Cl. 109, 1979 U.S. Ct. Cl. LEXIS 16, Counsel Stack Legal Research, https://law.counselstack.com/opinion/applied-devices-corp-v-united-states-cc-1979.