Fuel Tank Maintenance Company, LLC

CourtArmed Services Board of Contract Appeals
DecidedFebruary 24, 2025
Docket61922, 62509
StatusPublished

This text of Fuel Tank Maintenance Company, LLC (Fuel Tank Maintenance Company, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fuel Tank Maintenance Company, LLC, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Fuel Tank Maintenance Company, LLC ) ASBCA Nos. 61922, 62509 ) Under Contract No. W912DQ-15-C-1000 )

APPEARANCES FOR THE APPELLANT: William A. Lascara, Esq. Pender & Coward, P.C. Virginia Beach, VA

Jesse B. Gordon, Esq. Reaves GovCon Group Chesapeake, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Joseph A. Rosa, Esq. Virginia Murray, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Kansas City

MAJORITY OPINION BY ADMINISTRATIVE JUDGE THRASHER 1

Fuel Tank Maintenance Co., LLC, (FTM or appellant) appeals the U.S. Army Corps of Engineers, Kansas City District’s (USACE’s, COE’s or the government’s) denial of its certified claim for $695,312 and a time extension of an additional 343 days, representing the total sum of eight different issues related to the installation of relief wells, a collector pipe system, and various structural, electrical, and mechanical modifications to a Kansas City Board of Public Utilities pump station and remission of liquidated damages assessed (ASBCA No. 61922). Appellant also appeals the government’s claim for the return of $55,000 due to allegedly deficient work on as-built drawings FTM submitted under the contract (ASBCA No. 62509). We address entitlement only. For the reasons stated below, we sustain in part and deny in part both appeals.

1 Judge McNulty concurs with the entirety of this decision except for § 7, regarding the method to be used for the calculation of field office overhead, with which he dissents. Because of that disagreement, in accordance with the Board’s internal operating procedures, Judges Page and Smith were added to the panel considering these appeals. Judges Page and Smith join the majority decision in all respects and it is considered precedential. FINDINGS OF FACT

Basic Requirements of the Contract

1. The COE awarded Contract No. W912DQ-15-C-1000 to FTM on October 21, 2014 (R4, tab 9 at 2) 2. The contract was for installation of “relief wells, the relief well collector pipe system . . . and minor structural, mechanical, and electrical modifications to an existing pump station and discharge system adjacent to the Kansas City, Kansas, Board of Public Utilities power generation and water treatment facility” (R4, tab 8 at 2). Though this was a COE contract, it was for the benefit of the Kansas City Board of Public Utilities within the Fairfax Drainage District, which had a cost sharing agreement with the COE for this project (id.; tr. 3/177-78). The contract incorporated Federal Acquisition Regulation (FAR) 52.233-1 DISPUTES (MAY 2014), FAR 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996), and DFARS 252.201-7000 CONTRACTING OFFICER’S REPRESENTATIVE (DEC 1991) (R4, tab 8 at 9, 28-29, 33-34).

2. The contract required the contractor to obtain several government approvals prior to performance of the work. These approvals were obtained by submittals to the government for permission to proceed with aspects of the work. The government employed a code system for granting approval of the submittals. In the government’s coding for approval of submittals, an ‘A’ code signified government approval of the document as submitted. A ‘B’ code meant the submittal was approved with accompanying comments, resubmittal not required. A ‘C’ code meant approval on the condition of addressing the government’s comments upon resubmittal. An ‘E’ code meant rejection. An ‘F’ code acknowledged receipt. (R4, tab 125 at 41) For purposes of this decision, we will address the government’s responses as follows: ‘A’ code – approved; ‘B’ code – approved; ‘C’ code – approved; ‘; ‘E’ code – rejected, and ‘F’ code – acknowledged receipt.

3. A central aspect of this contract was the manufacture and installation of two large pumps and associated pump motors in the relief wells, with mechanical drawings specifying each should be 125 horsepower (hp) (R4, tab 4 at 42, 50). Under the contract specifications, if the “motor size provided differs from size indicated or specified, [the contractor must] make adjustments to wiring, disconnect devices, and branch circuit protectors to accommodate equipment actually provided” (R4, tab 3 at 426 ¶ 2.15.3). The specification also stipulated that:

[p]erformance of the pump to be furnished will be accepted on the basis of the factory test. [The contractor must c]onduct this test using either a scale model of pump or

2 Rule 4 citations are to the .pdf page number of the electronic documents.

2 first pump produced for this contract. Cavitation testing shall be performed . . . if no published NPSHR [Net Positive Suction Head Required] curves are available.

(R4, tab 3 at 382 ¶ 2.6.3.1) Moving Waters Incorporated (MWI), appellant’s motor manufacturing subcontractor (tr. 1/47), would “publish” a curve by putting it on its website, or in the case of “a slightly different design” of motor, “it’s something that we would prepare based off of model testing and [send] to the customer” (tr. 3/120). Under the contract, the required wet test for each single pump and motor unit had to be conducted:

under load, at or near normal operating conditions, for at least 2 hours or as directed by the Contracting Officer . . . . . Provide all supplies and equipment required to conduct the test. . . . . The Contracting Officer may waive or postpone the test if sufficient water is not available.

(R4, tab 3 at 389 ¶ 3.2.2) However, the contract stated that “[t]he Government will make all reasonably required utilities available to the Contractor from existing outlets and supplies” (R4, tab 3 at 179 ¶ 3.2.1). The contract also empowered the Contracting Officer (CO) to “waive or postpone the test if sufficient water is not available. Appropriate changes will then be made to the contract” (R4, tab 3 at 389 ¶ 3.2.2). The work further included installing a discharge pipe which was to be subjected to a visual leak inspection (R4, tab 3 at 649 ¶ 3.7.1). “[O]n each definable feature of work,” a preparatory phase had to be “performed prior to beginning work . . . after all required plans/documents/materials are approved/accepted, and after copies are at the work site” (R4, tab 3 at 158 ¶ 3.6.1). According to the contract, “[c]ontractor activities will be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-workdays” (R4, tab 3 at 97 ¶ 1.6.1.1.d). Additionally, the contract specifically states hours for the project are not limited, except on weekends and federal holidays (R4, tab 3 at 86 ¶ 1.9).

4. The contract also required FTM to furnish a schedule and provide “as-built corrections to Contract Drawings, Reference Drawings, as well as the approved shop drawings” after completion of the project (R4, tab 3 at 80). The government would “withhold the amount of $35,000 . . . until the final as-built drawing submittal ha[d] been approved by the Government” (R4, tab 3 at 90 ¶ 1.19.1).

ASBCA No. 61922: CLAIMS I – VII

5. On June 5, 2018, appellant submitted a certified claim for $695,312 and 343 days for delays related to eight issues: the motor upsize, electrical impact study, cavitation testing, monorail adjustment, the November 2016 stop work order,

3 excavation and backfilling of the discharge pipe at the pump house, various other “end of job” delays, and recovery of field office overhead (FOOH) on a per diem rate basis and remission of liquidated damages assessed (R4, tab 59). The government issued a contracting officer’s final decision (COFD) on September 29, 2018, denying the claim in its entirety (R4, tab 2 at 2, 19). FTM appealed this decision on December 23, 2018, and the Board docketed this appeal as ASBCA No. 61922.

I. MOTOR UPSIZE CLAIM

6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hedges v. Dixon County
150 U.S. 182 (Supreme Court, 1893)
Manufacturers' Finance Co. v. McKey
294 U.S. 442 (Supreme Court, 1935)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Beta Systems, Inc. v. The United States
838 F.2d 1179 (Federal Circuit, 1988)
Toombs & Co. v. United States
31 Cont. Cas. Fed. 72,149 (Court of Claims, 1984)
Applied Devices Corp. v. United States
591 F.2d 635 (Court of Claims, 1979)
CRF v. United States
624 F.2d 1054 (Court of Claims, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
Fuel Tank Maintenance Company, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fuel-tank-maintenance-company-llc-asbca-2025.