United Pacific Insurance Company, Reliance Insurance Company, and Reliance National v. United States

464 F.3d 1325, 2006 U.S. App. LEXIS 23927
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 20, 2006
Docket20-1802
StatusPublished
Cited by197 cases

This text of 464 F.3d 1325 (United Pacific Insurance Company, Reliance Insurance Company, and Reliance National v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Pacific Insurance Company, Reliance Insurance Company, and Reliance National v. United States, 464 F.3d 1325, 2006 U.S. App. LEXIS 23927 (Fed. Cir. 2006).

Opinion

SCHALL, Circuit Judge.

United Pacific Insurance Company, Reliance Insurance Company, and Reliance National (collectively, “United Pacific”) brought suit against the government in the *1326 United States Court of Federal Claims under the Tucker Act, 28 U.S.C. § 1491(a)(1). In its suit, United Pacific, which had acted as a Miller Act surety in connection with a government construction project, sought to recover in quantum me-ruit the amount over and above the original contract price that it was required to pay in order to complete the project after the contractor defaulted. United Pacific alleged that it was entitled to quantum meruit recovery because the contract at issue was illegal and therefore void ab initio. According to United Pacific, the contract was illegal because it was entered into in violation of two statutes, 10 U.S.C. § 2805 (1994) (amended 2000) and 10 U.S.C. § 2811 (1994) (amended 2000), which set forth expenditure limitations and require oversight in connection with certain military construction projects. 1 United Pacific now appeals the decision of the Court of Federal Claims dismissing its suit pursuant to Court of Federal Claims Rule 12(b)(6) for failure to state a claim upon which relief could be granted. United Pac. Ins. Co. v. United States, 68 Fed.Cl. 152, 162 (2005) (“Trial Court Opinion"). We affirm.

BACKGROUND

I.

On October 5, 1995, the United States, through the Contracting Squadron at McGuire Air Force Base in New Jersey, entered into a contract with Castle Abatement Corporation (“Castle”). Under the contract, the government agreed to pay Castle $3,152,174 to provide labor, material, and equipment to renovate three buildings at McGuire Air Force Base.

In accordance with the Miller Act, 40 U.S.C. §§ 270a-d (1994) (current version at 40 U.S.C. §§ 3131-3134 (2000 & Supp.2002)), United Pacific issued a performance bond in the penal sum of $3,152,174 and a labor and material bond in the penal sum of $1,576,087 to the government as obligee. 2 On July 21,1997, the government terminated its contract with Castle for default. In response to the government’s demand to United Pacific under the performance bond, United Pacific entered into a written takeover agreement with the government in which it agreed to complete the contract work. United Pacific then hired a contractor, Lattimer & Associates, to complete the work. Lattimer eventually completed the contract work at a total cost to United Pacific of $3,525,757.25. At the same time, United Pacific only received a total of $661,512.31 in payments from the government under the contract. That sum apparently represented the balance of the original contract price.

II.

On April 12, 2000, United Pacific filed a request for an equitable adjustment with *1327 the contracting officer, claiming that the contract between Castle and the government was void ab initio because it was illegal. United Pacific asked the contracting officer to terminate the contract for the convenience of the government and to pay it the sum of $3,194,490.59. This sum represented the costs United Pacific allegedly incurred in completing the contract work, less the $661,572.31 in payments that it had received from the government. After the contracting officer denied the claim, United Pacific filed an appeal with the Armed Services Board of Contract Appeals (“Board”).

On July 20, 2001, the Board issued a decision holding that United Pacific was without standing to assert Castle’s pre-takeover claim that the contract was illegal. In re United Pac. Ins. Co., ASBCA No. 53051, 01-2 B.C.A. ¶ 31,527, at 155,640, 2001 WL 865380 (July 20, 2001). Shortly thereafter, however, we decided Fireman’s Fund Insurance Co. v. England, 313 F.3d 1344 (Fed.Cir.2002). In Fireman’s Fund, we held that the Contract Disputes Act, 41 U.S.C. §§ 601-613, did not give the Board jurisdiction over equitable subrogation claims based on events that took place before a takeover agreement. 313 F.3d at 1352. Based upon Fireman’s Fund, the Board issued a reconsideration decision in which it rejected United Pacific’s claim on jurisdictional grounds, ruling that United Pacific was not a “contractor” within the meaning of the Contracts Disputes Act with respect to pre-takeover agreement events. In re United Pac. Ins. Co., ASBCA No. 53051, 03-2 B.C.A. ¶ 32267, at 159,622, 2003 WL 21350374 (June 4, 2003). In United Pacific Insurance Co. v. Roche, 380 F.3d 1352, 1358 (Fed.Cir.2004), we affirmed the Board’s decision. We held that because “[a]ll of these alleged overpay-ments to Castle ... were made prior to the takeover agreement, at a time when United [Pacific] was not yet a ‘contractor’ with the United States,” the Board “correctly concluded that it lacked jurisdiction over the claims.” Id. at 1356.

On January 12, 2005, United Pacific filed suit in the Court of Federal Claims under the Tucker Act, alleging that the contract between Castle and the government was illegal, and therefore void ab initio, because it was in violation of 10 U.S.C. §§ 2805 and 2811. Consequently, United Pacific urged, as the completing surety, it was entitled to recover its excess costs of completion on a quantum meruit basis. On September 28, 2005, the Court of Federal Claims dismissed United Pacific’s suit under Court of Federal Claims Rule 12(b)(6) for failure to state a claim upon which relief could be granted. Trial Court Opinion, 68 Fed.Cl. at 162. The court did so, inter alia, on the ground that United Pacific’s suit was foreclosed by our decision in American Telephone & Telegraph Co. v. United States, 177 F.3d 1368 (Fed.Cir.1999) (en banc) (“AT & T III ”). Trial Court Opinion, 68 Fed.Cl. at 156-59. At the same time, the court rejected United Pacific’s reliance on United States v. Amdahl, 786 F.2d 387 (Fed.Cir.1986), and Godley v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Target Corp. v. United States
2023 CIT 106 (Court of International Trade, 2023)
Solano v. United States
Federal Claims, 2023
Mohn v. United States
Federal Claims, 2021
Orr v. United States
Federal Claims, 2019
Reid v. United States
Federal Claims, 2019
Shapiro v. United States
Federal Claims, 2018
Scruggs v. United States
Federal Claims, 2018
Greene v. United States
Federal Claims, 2018
Phillips v. United States
Federal Claims, 2017
Soliman v. United States
Federal Claims, 2017
Parsons Government Services, Inc.
Armed Services Board of Contract Appeals, 2017
Stromness Mpo, LLC v. United States
126 Fed. Cl. 195 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
464 F.3d 1325, 2006 U.S. App. LEXIS 23927, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-pacific-insurance-company-reliance-insurance-company-and-reliance-cafc-2006.