Orbas & Associates v. United States

38 Cont. Cas. Fed. 76,373, 26 Cl. Ct. 647, 1992 U.S. Claims LEXIS 329, 1992 WL 199821
CourtUnited States Court of Claims
DecidedJuly 16, 1992
DocketNo. 90-254C
StatusPublished
Cited by6 cases

This text of 38 Cont. Cas. Fed. 76,373 (Orbas & Associates v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orbas & Associates v. United States, 38 Cont. Cas. Fed. 76,373, 26 Cl. Ct. 647, 1992 U.S. Claims LEXIS 329, 1992 WL 199821 (cc 1992).

Opinion

OPINION

BRUGGINK, Judge.

This action, brought pursuant to the Contract Disputes Act of 1978,1 is before the court on the government’s motion to dismiss for lack of subject matter jurisdiction. [648]*648For the reasons that follow, the motion is denied.

FACTUAL BACKGROUND2

Plaintiff, Orbas & Associates, entered into a contract with the Navy to perform certain construction work at the Navy Exchange at the Pacific Missile Test Center, Point Mugu, California. The contract was competitively let. Orbas submitted the low bid of $55,980.00. Performance commenced November 18,1988. The complaint alleges that plaintiff encountered difficulty immediately, due to misleading contract documents, impossible terms, and poor assistance and direction from Navy personnel. The complaint also alleges that Orbas notified the Navy that it was incurring additional costs, delays, and inefficiencies. On May 11, 1989, plaintiff was terminated for alleged default.

On January 15, 1990, Orbas submitted a claim entitled, “Termination for Default Proposal.” This submission includes twenty pages of narrative and a number of attachments. The second paragraph is an overture:

This proposal will demonstrate that during the period of the contract up to and including the receipt of the Termination for Default, Orbas [was] performing in accordance with the terms of the contract and was therefore not technically in default. Further, any delay in completing the work was due to unforeseen causes beyond the control and without the fault or negligence of the Orbas, and entirely a result of actions or inactions of the government in either its sovereign or contractual capacity. Lastly, this proposal provides an estimate of the termination costs, requests withdrawal of the Navy’s Termination for Default decision and proposes the Navy make an equitable adjustment to the contract in the amount of $198,242.00.

Orbas’ claim included a request that the termination for default be converted into a termination for convenience.

On February 28, 1990, the Deputy Resident Officer In Charge of Construction informed Orbas that its claim was incomplete and therefore the government could not finish its evaluation until Orbas submitted the necessary information. By letter dated March 1, 1990, the Contracting Officer (“CO”) also informed Orbas that its claim could not be completed until the supplemental information was forwarded to the government. This letter stated that “[i]n the event you have already or soon will provide the requisite information with appropriate certifications, you should not expect a final decision prior to 30 June 1990 due to the complexity of the claims already under review.”

Orbas responded to the CO by letter dated March 13, 1990. In this letter Orbas denied that further information was needed to evaluate its claim. On March 23, 1990, Orbas filed this action, contending that the court had jurisdiction pursuant to 41 U.S.C. § 609(a)(1) (1988). Thereafter, on May 4, 1990, the CO issued a final decision on Orbas’ January 15, 1990 claim, converting the termination for default into a termination for convenience.

DISCUSSION

Does the court have jurisdiction pursuant to the Contract Disputes Act (“CDA”)? The relevant language of the CDA for the purposes of this discussion is found within § 605(c). In pertinent part, this subsection provides:

(2) A contracting officer shall, within sixty days of receipt of a submitted certified claim over $50,000—
(A) issue a decision; or
(B) notify the contractor of the time within which a decision will be issued.
(5) Any failure by the contracting officer to issue a decision on a contract claim within the period required will be deemed to be a decision by the contracting officer denying the claim and will authorize the [649]*649commencement of the appeal or suit on the claim as otherwise provided in this chapter____

41 U.S.C. § 605(c).

It is well settled that the “linchpin” for appealing claims and obtaining direct access to this court under the CDA is the CO’s final decision. 41 U.S.C. §§ 605(c), 609(a)(1); Continental Heller Constr. v. United States, 21 Cl.Ct. 471, 473 (1990); Paragon Energy Corp. v. United States, 227 Ct.Cl. 176, 177, 645 F.2d 966, 967 (1981). Absent an actual or “deemed” final decision, this court cannot exercise jurisdiction over the controversy. Boeing Co. v. United States, 26 Cl.Ct. 257 at 259, (1992); Mendenhall v. United States, 20 Cl.Ct. 78, 82 (1990); Claude E. Atkins Enters. v. United States, 15 Cl.Ct. 644, 646 (1988).

Section 605(c)(2) thus “places the burden on the government contracting officer to issue a final decision on a claim within 60 days or notify the contractor when the decision will be issued.” Vemo Co. v. United States, 9 Cl.Ct. 217, 222 (1985). Section 605(c)(5) of the CDA provides that a “deemed decision” can result from the CO’s failure to issue a decision within the time period set forth in the other subsections.

According to the government, dismissal is appropriate because there was neither a final decision nor a deemed final decision by the CO. The decision of May 4, 1990, it asserts, was a nullity because the complaint had already been filed. The March 1, 1990 letter was also sufficient under § 605(c)(2)(B) to notify the contractor of a time “within which a decision will be issued.” In response to this argument, Orbas contends that the CO failed to comply with the express requirements of § 605(c)(2)(A) and (c)(2)(B). It argues that within sixty days of receipt of the claim, the CO neither issued a final decision nor notified the contractor of the time within which a decision would be issued. As a result, the claim was “deemed denied” pursuant to § 605(c)(5).

Since there was no express final decision prior to the initiation of this action, the question becomes whether, within sixty days of the receipt of the claim, the CO notified the contractor of the time within which a decision would be issued. If he did, then Orbas has prematurely filed this action, and the subsequent issuance of a final decision cannot cure the defect. If he did not, then the CO failed to satisfy § 605(c)(2)(B), and this failure amounted to a “deemed decision” denying the claim.

The answer must be found in the CO’s March 1, 1990 letter to Orbas, which stated: “[i]n the event [that] you have already or soon will provide the requisite information with appropriate certifications, you should not expect a final decision prior to 30 June 1990 due to the complexity of the claims already under review.” According to Orbas, a fair paraphrase of this letter is that the final decision will be issued sometime after June 29, 1990. If this is correct, then the letter did not satisfy § 605(c)(2)(B), because the time within which a decision would be issued was open-ended.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

California Department of Water Resources v. United States
128 Fed. Cl. 603 (Federal Claims, 2016)
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Claude E. Atkins Enterprises, Inc. v. United States
27 Fed. Cl. 142 (Federal Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,373, 26 Cl. Ct. 647, 1992 U.S. Claims LEXIS 329, 1992 WL 199821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orbas-associates-v-united-states-cc-1992.