Rhen v. United States

35 Cont. Cas. Fed. 75,672, 17 Cl. Ct. 140, 1989 U.S. Claims LEXIS 95, 1989 WL 59205
CourtUnited States Court of Claims
DecidedJune 2, 1989
DocketNo. 308-88C
StatusPublished
Cited by8 cases

This text of 35 Cont. Cas. Fed. 75,672 (Rhen v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rhen v. United States, 35 Cont. Cas. Fed. 75,672, 17 Cl. Ct. 140, 1989 U.S. Claims LEXIS 95, 1989 WL 59205 (cc 1989).

Opinion

MEMORANDUM OPINION

LYDON, Senior Judge:

Plaintiff, proceeding pro se, challenges the default termination of a contract he had with the Bureau of Land Management, Department of the Interior (BLM). In his complaint, plaintiff sets forth five separate claims for damages he seeks to recover emanating from this default termination. Defendant, after answer, has responded to the complaint by filing a motion for partial summary judgment as to three of the five claims, contending that, as to these three claims, there is no genuine issue as to any material fact and, accordingly, defendant is entitled to judgment in its favor as a matter of law. Plaintiff has filed an opposition to defendant’s motion.

Upon consideration of the submissions of the parties, oral argument being considered unnecessary, the court concludes that defendant’s partial motion for summary judgment should be granted.

I.

On March 5, 1985, the BLM, Portland Oregon District, issued an Invitation for Bids (IFB) for “One Time Through Precom-mercial Thinning.” The contract work involved the cutting and thinning of surplus trees and the cutting of bushes so as to provide additional growing space for existing trees. The IFB called for work to be performed on two different sites in the North Umpqua Recourse Area in the Rose-burg District, Oregon. One work site, known as “Lone Rock” contained 307 acres; the other site, known as “Above The River”, contained 216 acres. Roadways through the two areas of the project were clearly delineated on contract documents. Under the IFB, an unqualified bid on both work sites required the contractor to complete the contract work in sixty days. The bid opening day was April 4, 1985.

[142]*142Plaintiff was the successful low bidder at $42,846.50. His bid covered both work sites and was unqualified. Accordingly, he was required to complete the contract within sixty days. Plaintiff was awarded the contract on April 18, 1985, and the Notice To Proceed with the work became effective April 30, 1985. Plaintiff began work on April 30, 1985.1

Plaintiff’s progress on the contract work was slow and BLM personnel became concerned about the matter. On May 14,1985, an “Instruction,” and on May 22, 1985, a letter were sent to plaintiff by BLM warning him of BLM concern that with his present work force he would not be able to complete all of the contract work within the remaining contract period. Plaintiff was requested to submit a revised work schedule to BLM. On June 28, 1985, the contract time expired and only forty-two percent of the work had been completed.

On June 28, 1985, BLM issued a Show Cause Notice to plaintiff advising that the Government was considering terminating his contract under the default provisions of the contract. Plaintiff was given ten days to respond to this Notice.

Plaintiff responded to the Notice of July 5, 1985. He contended the contract work had not been completed on time because he had trouble locating qualified employees and also had problems with his subcontractors. He also contended that some of his workers were having problems with the BLM project inspector in that the inspector was too strict in requiring adherence to contract requirements.2

On July 16, 1985, BLM terminated plaintiff’s contract for default pursuant to the Default Clause of the contract and so notified plaintiff. In support of this default termination, the contracting officer issued Findings and a Decision on September 27, 1985. The contracting officer found that plaintiff had failed to complete the contract work within the time required by the contract and that his failure in this regard was not the result of any excusable delays.3

On September 22, 1986, plaintiff filed suit in this court contesting the default termination and presenting a number of monetary claims. The suit was dismissed without prejudice by the court, in an unpublished Memorandum Opinion dated February 27, 1987, because plaintiff had never filed monetary claims with the contracting officer. On March 24, 1987, plaintiff filed money claims with the contracting officer. Plaintiff sought to recover approximately $520,446.63, plus interest as damages flowing from termination of his $42,846.50 contract. In his claim to the contracting officer, plaintiff alleged numerous instances of delay on the part of the Government which he claims were responsible for his failure to complete the contract work in a timely manner. No decision having been rendered on these claims by the contracting officer within sixty days, plaintiff, on March 23, 1988, filed the instant action in this court. See in this regard, Vemo v. United States, 9 Cl.Ct. 217, 221-22 (1985).

In his complaint, plaintiff seeks to recover for the alleged improper termination of his contract the following damages:

1) Plaintiff seeks to recover $7,005.84 which he paid the Amwest Surety Insurance Company for completing the terminated contract. This claim had been presented to the contracting officer;
2) plaintiff seeks to recover $11,511.52 representing income he would have earned in performing the contract had it not been terminated. This claim [143]*143had been presented to the contracting officer;
3) plaintiff seeks to recover $1,100.00 for the value of road acreage deleted from the contract. This claim had been presented to the contracting officer;
4) plaintiff seeks to recover $850,000 on the ground he lost his ability to get bonding as a result of the default termination of his contract by BLB. This claim had been presented to the contracting officer but only for $500,-000;
5) plaintiff also seeks interest on the above claims, attorney fees and costs of litigation.

II.

Defendant has moved for partial summary judgment, with supporting documentation, on claims (2), (3) and (4), supra.

A. The $11,511.52 Claim (#2 supra)

As indicated above, plaintiff seeks to recover $11,511.52 on the ground he would have earned this amount had his contract not been terminated. As stated by plaintiff, this claim is one for income he would have made had he been able to complete the contract. Thus, his claim is one for anticipated but unearned profit. Defendant contends that, under the circumstances of this case, plaintiff is not entitled to recover on this claim as a matter of law. Defendant’s position is well taken.

The Default Clause in plaintiff’s contract provides, in substance, that if a default termination is subsequently found to be improper, “the right and obligations of the parties shall be the same as if the termination had been issued for the convenience of the Government.” See Nolan Brothers Inc. v. United States, 405 F.2d 1250, 1254-55, 186 Ct.Cl. 602 (1969). Accordingly, assuming arguendo that plaintiff’s contract was improperly terminated, he would not, as a matter of law, be entitled to recover anticipated profit. This is so because under the contract’s Termination For Convenience Clause, anticipated, but unearned profits are not recoverable. Dairy Sales Corp. v. United States, 593 F.2d 1002, 1005, 219 Ct.Cl. 431 (1979).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morrison Knudsen Corp. v. Fireman's Fund Insurance
175 F.3d 1221 (Tenth Circuit, 1999)
Finley v. United States
39 Cont. Cas. Fed. 76,688 (Federal Claims, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Lucas v. United States
37 Cont. Cas. Fed. 76,269 (Court of Claims, 1992)
C.B.C. Enterprises, Inc. v. United States
37 Cont. Cas. Fed. 76,171 (Court of Claims, 1991)
Essen Mall Properties v. United States
36 Cont. Cas. Fed. 75,942 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,672, 17 Cl. Ct. 140, 1989 U.S. Claims LEXIS 95, 1989 WL 59205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rhen-v-united-states-cc-1989.