Contact International, Inc. v. Sheila E. Widnall, Secretary of the Air Force

106 F.3d 426, 1997 U.S. App. LEXIS 27809, 1997 WL 12922
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 15, 1997
Docket96-1133
StatusUnpublished

This text of 106 F.3d 426 (Contact International, Inc. v. Sheila E. Widnall, Secretary of the Air Force) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contact International, Inc. v. Sheila E. Widnall, Secretary of the Air Force, 106 F.3d 426, 1997 U.S. App. LEXIS 27809, 1997 WL 12922 (Fed. Cir. 1997).

Opinion

106 F.3d 426

41 Cont.Cas.Fed. (CCH) P 77,036

NOTICE: Federal Circuit Local Rule 47.6(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
CONTACT INTERNATIONAL, INC., Appellant,
v.
Sheila E. WIDNALL, Secretary of the Air Force, Appellee.

No. 96-1133.

United States Court of Appeals, Federal Circuit.

Jan. 15, 1997.

Before RICH, CLEVENGER, and SCHALL, Circuit Judges.

SCHALL, Circuit Judge.

DECISION

Contact International, Inc. (Contact) appeals from the August 31, 1995 decision of the Armed Services Board of Contract Appeals (Board) in Contact International Corp., ASB CA No. 44636. In its decision, the Board sustained in part and denied in part Contact's appeal of a contracting officer's final decision denying Contact's claim for additional compensation and for damages for breach of contract under a fixed-price requirements contract between Contact and the United States Air Force (Air Force or government). Pursuant to the contract, Contact was to produce dairy products at a United States government-owned plant in Japan. We affirm.

DISCUSSION

I.

The parties entered into the contract on September 20, 1989. The contract provided for a one-year base performance period, from October 1, 1989, to September 30, 1990, with four one-year options. On September 26, the incumbent contractor, Servrite International, Ltd. (Servrite), filed a bid protest with the General Accounting Office (GAO), challenging the award to Contact. Servrite requested that performance of the new contract be stayed pending a decision on the merits of the protest, but the Air Force determined that the products covered by the contract were urgently needed and allowed Contact to continue performance.1

On November 29, 1989, the Air Force sent GAO a memorandum in which it stated that it was sustaining Servrite's protest. The Air Force informed GAO that, in view of certain discussions which had taken place between the contracting officer and Servrite prior to contract award, it was unable to determine "whether award was made to the offeror whose proposal would have been most advantageous to the Government." The Air Force advised GAO that it would be reopening discussions with Servrite and Contact, the only two offerors, and that it would be requesting the submission of best and final offers. Upon completion of that process, the Air Force wrote, the contract would be awarded "to the offeror whose proposal is most advantageous to the Government consistent with the solicitation's evaluation criteria." In view of the proposed resolution of the dispute, GAO denied Servrite's protest on January 4, 1990.

Citing the November 29 memorandum, the contracting officer informed Contact, by letter dated December 21, 1989, that an amended request for proposals (RFP) would be issued on or about January 20, 1990, and that the resulting contract would begin on July 1. Contact challenged this decision in a protest filed with the Air Force on January 5; the Air Force denied the protest on January 19.2 On February 5, Contact lodged a further protest with GAO, in which Servrite intervened. GAO denied the protest on May 17, stating that the Air Force's proposed corrective action was "necessary in order to preserve the integrity of the competitive procurement system."

On June 7, 1990, the Air Force informed Contact that the amended RFP would issue on or about June 30 and that the new contract would begin on October 1. The amended solicitation issued on July 2, and Servrite was awarded the new contract on September 10. Contact's contract ended by its terms on September 30, 1990, with the Air Force not exercising any of the option years.

On September 27, 1991, Contact submitted a claim to the contracting officer for an equitable adjustment under the contract. Contact also sought to recover damages for breach of contract, on the ground that the Air Force had breached the contract by improperly terminating it. Contact sought to recover (i) costs for inventory which was lost due to the alleged early termination of the contract; (ii) costs arising as a result of the Air Force's failure to make orders within certain estimated volume requirements; (iii) the cost of repairing certain machinery; (iv) non-recurring costs and depreciation; (v) costs relating to pay and fringe benefits for a plant manager; and (vi) profit. After the contracting officer denied the claim, Contact appealed to the Board. The Board sustained the appeal to the extent of the cost of repairing the machinery and costs arising as a result of the Air Force's failure to make orders within estimated volume requirements. In all other respects, the Board affirmed the contracting officer's final decision and denied Contact's appeal.

II.

We review the Board's decision under the standards set forth in the Contract Disputes Act, 41 U.S.C. §§ 601-613 (1994). Under the statute:

the decision of the agency board on any question of law shall not be final or conclusive, but the decision on any question of fact shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.

41 U.S.C. § 609(b). The Board's conclusions of law are not final or conclusive and are reviewed de novo. See Fruin-Colnon Corp. v. United States, 912 F.2d 1426, 1429 (Fed.Cir.1990). Our review of the Board's findings of fact is limited to a determination of whether the findings are arbitrary, capricious, based upon less than substantial evidence, or rendered in bad faith. Roseburg Lumber Co. v. Madigan, 978 F.2d 660, 665 (Fed.Cir.1992).

On appeal, Contact does not challenge the Board's findings of fact. Instead, it argues that the Air Force's actions following award of the contract: (i) amounted to a constructive termination for convenience; (ii) caused a cardinal change, and thus a breach of contract; and (iii) amounted to a constructive change. For the reasons set forth below, we conclude that none of these contentions has merit.

A.

Contact argues that a constructive termination for convenience occurred based upon the Air Force's actions beginning in November of 1989. According to Contact, even though no formal notice of termination for convenience was issued, the Air Force repudiated its commitment to perform for at least one year when it told Contact that it would issue an amended RFP and seek best and final offers and that a new contract would begin in July of 1990.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Air-A-Plane Corporation v. The United States
408 F.2d 1030 (Court of Claims, 1969)
Edward R. Marden Corporation v. The United States
442 F.2d 364 (Court of Claims, 1971)
Government Systems Advisors, Inc. v. The United States
847 F.2d 811 (Federal Circuit, 1988)
Maxima Corporation v. The United States
847 F.2d 1549 (Federal Circuit, 1988)
Fruin-Colnon Corporation v. The United States
912 F.2d 1426 (Federal Circuit, 1990)
Jerome Frank Harris v. United States
106 F.3d 426 (Federal Circuit, 1997)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Wunderlich Contracting Co. v. United States
351 F.2d 956 (Court of Claims, 1965)
International Telephone & Telegraph v. United States
453 F.2d 1283 (Court of Claims, 1972)
C. H. Leavell & Co. v. United States
530 F.2d 878 (Court of Claims, 1976)
Allied Materials & Equipment Co. v. United States
569 F.2d 562 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
106 F.3d 426, 1997 U.S. App. LEXIS 27809, 1997 WL 12922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contact-international-inc-v-sheila-e-widnall-secretary-of-the-air-cafc-1997.