Amertex Enterprises, Ltd. v. United States

108 F.3d 1392, 1997 WL 73789
CourtCourt of Appeals for the Federal Circuit
DecidedMay 2, 1997
Docket96-5070
StatusUnpublished
Cited by1 cases

This text of 108 F.3d 1392 (Amertex Enterprises, Ltd. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amertex Enterprises, Ltd. v. United States, 108 F.3d 1392, 1997 WL 73789 (Fed. Cir. 1997).

Opinion

108 F.3d 1392

41 Cont.Cas.Fed. (CCH) P 77,048

NOTICE: Federal Circuit Local Rule 47.6(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
AMERTEX ENTERPRISES, LTD., Plaintiff-Appellant,
v.
The UNITED STATES, Defendant-Appellee.

96-5070.

United States Court of Appeals, Federal Circuit.

Feb. 24, 1997.
Rehearing Denied; Suggestion for Rehearing In Banc Declined
May 2, 1997.

Before NEWMAN, MICHEL and SCHALL, Circuit Judges.

MICHEL, Circuit Judge.

Amertex Enterprises, Ltd. ("Amertex") appeals the consolidated, post-trial decision of December 15, 1995 of the Court of Federal Claims, Nos. 90-684, 91-1700, and 92-402, denying its claim for cardinal change breach of a contract, granting its claim for an equitable adjustment for delay caused by the United States ("government"), holding that the government's termination for default was justified, and offsetting the equitable adjustment with the amount of unliquidated progress payments due to the justified termination. The case was submitted for decision after oral argument on December 5, 1996. Because we agree with the trial court that Amertex waived its cardinal change claim by entering into bilateral modifications, and because the trial court did not reversibly err in its calculation of delay damages, or holding of justified default termination, we affirm.

BACKGROUND

The detailed facts of the case are set out in the opinion of the Court of Federal Claims. Amertex Enterprises, Ltd. v. United States, Nos. 90-684 C, 91-1700, and 92-402 (Fed.Cl.1995). In brief, Amertex was awarded a government contract for the production of chemical warfare protective suits ("chemsuits") on February 25, 1985. A total of 2,415,885 chemsuits were to have been produced by December 29, 1986. In the words of the Court of Federal Claims, "[f]rom its inception, this procurement was plagued by poor decisions, mistakes, and miscommunication that delayed and disrupted Amertex's performance of its obligations." During the course of performance, the government issued 42 modifications and eight amendments to the contract, totaling over 100 changes to the specifications for the chemsuits. Also during the course of performance, and after many of these unilateral modifications and amendments, Amertex and the government entered into bilateral modifications of the contract which provided for a revised payment scheme and delivery schedule. The government eventually terminated the contract for default on January 6, 1989, over two years after the original deadline. Amertex had delivered fewer than half of the chemsuits it had agreed to deliver in the original contract.

Amertex submitted two claims to the Contracting Officer, one challenging the termination for default, and the second alleging a breach of the contract through cardinal change and seeking an equitable adjustment based on delay and disruption allegedly caused by the government. Both claims were denied, and Amertex filed suit in the United States Court of Federal Claims, which denied Amertex's cardinal change claim and default termination challenge, but granted in part its claim for an equitable adjustment. This appeal timely followed.

DISCUSSION

Decisions of the Court of Federal Claims are subject to only limited review. Factual findings are reviewed for clear error, while legal conclusions are reviewed de novo. Alger v. United States, 741 F.2d 391, 393 (Fed.Cir.1984).

I.

Amertex first appeals the holding that the series of changes that the government made to the contract did not constitute a cardinal change. This court reviews the holding of a cardinal change de novo. See, e.g., AT & T Communications, Inc. v. Wiltel, Inc., 1 F.3d 1201, 1207-08 (Fed.Cir.1993). A cardinal change:

occurs when the government effects an alteration in the work so drastic that it effectively requires the contractor to perform duties materially different from those bargained for. By definition, then a cardinal change is so profound that it is not redressable under the contract, and thus renders the government in breach.

AT & T Communications, 1 F.3d at 1205 (citing Allied Materials & Equip. Co. v. United States, 569 F.2d 562, 563-64 (Ct.Cl.1978)). As to Amertex's cardinal change claim, the Court of Federal Claims stated:

Notwithstanding the evidence supporting plaintiff's plausible and potentially convincing cardinal change assertion, plaintiff's position on this issue is fatally undercut by the bilateral modification made to the delivery schedule in 1988.

Although Amertex argues that, when presented with the bilateral modifications, it "could not ... walk away" from the contract, it has neither pleaded nor proven duress. The signed modifications evidence a meeting of the minds and, since the modifications changed both parties' obligations, are supported by consideration. Thus, the bilateral modifications are enforceable contracts which replace the parallel provisions of the original contract. As noted above, the bilateral modifications included modifications to the delivery schedule and the payment scheme. By agreeing to these modifications, Amertex implicitly agreed to a changed specification and added costs it accrued thereby. As stated by the Court of Federal Claims, "[i]n essence, Amertex promised to produce the modified chempro suit, with all changes which had been made to July 1988 and given the numerous other government-caused difficulties, on a schedule contemplating half the pace as the original contract." Moreover, by advancing payment due dates to delivery installment dates, Amertex bargained for and received an infusion of working capital that was needed in light of performance difficulties but that was not contemplated in the original payment scheme. Since Amertex agreed to the changes, it implicitly agreed that the changes were within the changes clause of the contract. There can only be a cardinal change if the government required Amertex to perform materially different duties from those bargained for in the contract as modified. Amertex does not so allege.

Amertex argues that Air-A-Plane Corp. v. United States, 408 F.2d 1030 (Ct.Cl.1969), suggests a different result. In Air-A-Plane, a plaintiff was allowed to pursue both an equitable adjustment through the Armed Forces Board of Contract Appeals ("ASBCA") and a cardinal change claim through the Court of Claims. In rejecting the government's argument that the plaintiff was estopped from pursuing its cardinal change claim by virtue of its equitable adjustment claim, the court stated:

This is an instance of an imposed election of remedies which seems to us unfair to contractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Becho, Inc. v. United States
47 Fed. Cl. 595 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
108 F.3d 1392, 1997 WL 73789, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amertex-enterprises-ltd-v-united-states-cafc-1997.