Semac Electric Co. v. Skanska USA Building, Inc.

195 Conn. App. 695
CourtConnecticut Appellate Court
DecidedFebruary 11, 2020
DocketAC41054
StatusPublished
Cited by6 cases

This text of 195 Conn. App. 695 (Semac Electric Co. v. Skanska USA Building, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Semac Electric Co. v. Skanska USA Building, Inc., 195 Conn. App. 695 (Colo. Ct. App. 2020).

Opinion

*********************************************** The “officially released” date that appears near the be- ginning of each opinion is the date the opinion will be pub- lished in the Connecticut Law Journal or the date it was released as a slip opinion. The operative date for the be- ginning of all time periods for filing postopinion motions and petitions for certification is the “officially released” date appearing in the opinion.

All opinions are subject to modification and technical correction prior to official publication in the Connecticut Reports and Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the latest version appearing in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative.

The syllabus and procedural history accompanying the opinion as it appears in the Connecticut Law Journal and bound volumes of official reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced and distributed without the express written permission of the Commission on Official Legal Publica- tions, Judicial Branch, State of Connecticut. *********************************************** SEMAC ELECTRIC COMPANY, INC. v. SKANSKA USA BUILDING, INC. (AC 41054) Alvord, Devlin and Norcott, Js.

Syllabus

The plaintiff subcontractor, E Co., sought to recover damages from the defendant, S Co., for, inter alia, breach of contract in connection with a dispute arising from a project relating to the expansion and renovation of a hospital. Pursuant to its contract with S Co., E Co. agreed to perform all electrical work for the project. The contract provided that E Co. had a duty to coordinate with S Co., that E Co. had made allowances for all hindrances and delays to its work, and that E Co. would work within S Co.’s schedule, which S Co. may revise from time to time. S Co. had the right to direct a change in E Co.’s work on written notice and, during the course of the project, thirty-eight change orders were issued. After several months, E Co. sent S Co. a notice, alleging a cardinal change to the contract due to issues that arose during the preceding months and asserting that it could only continue to perform under the contract if S Co. agreed to additional financial terms. S Co. responded that E Co.’s refusal to proceed under the contract constituted default and, the next day, S Co. terminated E Co. E Co. alleged that S Co. had breached the contract by its wrongful termination of E Co., and S Co. filed a counterclaim, alleging, inter alia, breach of contract. S Co. also filed a third-party complaint against K and T, the chief financial officer and president of E Co., respectively, alleging, inter alia, fraudulent conduct. The case was tried to the court, which rendered judgment in part for S Co. on its counterclaim, and in favor of K and T on the third-party complaint. On S Co.’s appeal and E Co.’s cross appeal to this court, held: 1. The trial court properly rejected E Co.’s claim that there had been a cardinal change in the contract terms and properly concluded that E Co. breached the contract by abandoning the project: the court properly focused on the nature and impact of the delays on the work expected of and performed by E Co., which were not extraordinary in a project of this magnitude, and neither the character nor the nature of the work expected of or performed by E Co. was altered in any way, and E Co. was compensated for the changes in its work up until the time that it issued its notice of cardinal change to S Co., E Co. was required to anticipate unforeseen modifications to E Co.’s sequence of construction and the schedule parameters of the contract when it signed the contract, as the contract language demonstrated that the parties contemplated the possibility of scheduling delays and changes; moreover, there was no evidence that the change orders altered the nature of E Co.’s work, and, in executing each change order, E Co. attested that it was compen- sated for associated costs and delays, and it was clear that the changes were not so profound that they were not redressable under the contract, as they were, in fact, redressed via the change orders. 2. The trial court properly concluded that S Co. materially breached its contract with E Co. by failing to provide E Co. with a forty-eight hour cure period before terminating its contract with E Co.: even though S Co. claimed that the court erred in assuming that it had terminated E Co. pursuant to the contract provision requiring it to give E Co. forty- eight hours to cure its breach, because S Co. pleaded in its counterclaim that it had declared E Co. in default pursuant to the contract, the court properly held the parties to their contractual obligations; moreover, S Co.’s reliance on certain common-law principles overlooked the clear contractual language requiring a cure period, which did not include any exceptions, and which outlined the procedure if E Co. abandoned the project or defaulted on its obligations and the court correctly determined that S Co. should be held to the contract provisions because to hold otherwise would excuse S Co.’s noncompliance with the contract and would create a new and different agreement, which courts cannot do; furthermore, the court’s enforcement of the cure period did not render meaningless another provision of the contract stating that S Co.’s con- tractual remedies were not exclusive, because S Co. could not turn to the common law to avoid an express contractual obligation. 3. The trial court’s award of damages was not erroneous: this court disagreed with S Co.’s claim that, due to E Co.’s material breach, S Co. was excused from further performance of its contractual obligations and was entitled to expectation damages, because S Co. also breached the contract by failing to afford E Co. a forty-eight hour cure period, transforming its termination for cause of E Co. into a termination for convenience and, accordingly, S Co. could not claim entitlement to a common-law remedy after forfeiting its right to a contractual remedy as a result of its own breach; moreover, E Co. could not prevail on its claim that the court erred in not awarding a termination payment pursuant to the contract, because, although the court concluded that E Co. was entitled to a termination payment, the court found that E Co.’s billing practices were too irregular to award damages on the basis of its invoices, which the contract had provided for, and, instead, calculated the payment by determining the percentage of the project E Co. had completed and multiplying that percentage by the contract price; although potentially imprecise, it could not reasonably be argued that this method ran afoul of the contract or was unfair to E Co. 4. The trial court did not err in finding that K and T did not commit fraud when they swore under oath to the accuracy of invoices submitted to S Co. for goods and services they represented to S Co. that they had paid to other subcontractors, but actually never did pay; K’s and T’s conduct strained the bounds of fraud, revealing, at best, gross incompe- tence, but the court nevertheless found that, on the basis of its observa- tion of K’s and T’s demeanor and attitude, neither K nor T acted with fraudulent intent, and this court does not second-guess the court’s credi- bility assessments. Argued October 16, 2019—officially released February 11, 2020

Procedural History

Action to recover damages for, inter alia, breach of contract, and for other relief, brought to the Superior Court in the judicial district of Hartford, Complex Litiga- tion Docket, where the defendant filed a counterclaim; thereafter, the court, Young, J., granted the defendant’s motion to implead Kevin Pope et al.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Krausman v. Liberty Mutual Ins. Co.
236 Conn. App. 109 (Connecticut Appellate Court, 2025)
Finnochio Brothers, Inc. v. 587 CTA, LLC
Connecticut Appellate Court, 2024
Li v. Yaggi
212 Conn. App. 722 (Connecticut Appellate Court, 2022)
Centerplan Construction Co., LLC v. Hartford
343 Conn. 368 (Supreme Court of Connecticut, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
195 Conn. App. 695, Counsel Stack Legal Research, https://law.counselstack.com/opinion/semac-electric-co-v-skanska-usa-building-inc-connappct-2020.