Jones & Laughlin Steel Co. v. Abner Doble Co.

123 P. 290, 162 Cal. 497, 1912 Cal. LEXIS 562
CourtCalifornia Supreme Court
DecidedApril 2, 1912
DocketS.F. No. 5790.
StatusPublished
Cited by17 cases

This text of 123 P. 290 (Jones & Laughlin Steel Co. v. Abner Doble Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones & Laughlin Steel Co. v. Abner Doble Co., 123 P. 290, 162 Cal. 497, 1912 Cal. LEXIS 562 (Cal. 1912).

Opinion

SHAW, J.

This is an action to recover the sum of $27,641.21, alleged to be due as the reasonable value of certain building material sold and delivered by plaintiff to the defendant at its request. The materials were to be used by the defendant in the construction of certain buildings upon its land. Plaintiff also claimed a lien therefor upon the land and build *499 ing and certain other lien claimants were made parties defendant. The appeal is by the Abner Doble Company alone. The only dispute is in relation to the sum for which judgment was given, and the liens and the other claims are not material to our consideration of the case.

The complaint alleges the following facts: In 1906 the defendant ordered from plaintiff, whose place of business was Pittsburg, Pennsylvania, all the structural steel, metal window frames, sash, doors, and wire glass and other metal material required for a warehouse, a forge shop, and a lavatory, to be erected by defendant according to plans and drawings prepared and to be prepared by plaintiff, based on general suggestions in letters and certain outline or preliminary plans theretofore written and furnished by defendant. Plaintiff prepared the plans and they were sent to and approved by defendant. No price or specific time for delivery was agreed upon. It was agreed that payment was to be made thirty days after date of shipment, with the privilege to defendant of six months’ additional time by giving notes due in that time at five per cent annual interest. Plaintiff furnished the materials ordered. The reasonable value of that used in the warehouse is $19,176.33, of which $3819.80 was paid. That used in the forge shop was worth $10,323.80, of which $21.84 was paid. That used in the lavatory was worth $1982.72, none of which was paid. The total balance unpaid was $27,641.21, all of which was past due. In pursuance of the agreement for credit some notes" were given by defendant to plaintiff, which plaintiff tendered for such disposition as the court deemed proper.

The answer of the Abner Doble Company admits that a contract was made between said defendant and plaintiff for the furnishing of the materials alleged. It avers as a-counter cl aim that it was agreed that plaintiff would draw and furnish to defendant “all the detailed plans and specifications’’ for the aforementioned buildings, that the said plans and specifications were to be for “a good, first-class, substantial steel framed building, of sufficient strength to carry, on one half of the second floor of the warehouse, a weight of five hundred pounds to the square foot, and on the other half one hundred and fifty pounds to the square foot”; and that all said material waé to be delivered by the plaintiff in San Francisco, in condition for placing in said buildings, the materia] for the *500 warehouse to be delivered between August 1, 1906, and October 15, 1906, and that for the forge shop on or about September 13, 1906. It then avers that plaintiff did not deliver said materials until eight months after the times agreed upon as aforesaid; that the building, as planned by plaintiff, and the material as constructed by plaintiff was not strong enough to carry the weights above mentioned; that the doors were not made as planned, or of good material and . could not be used in the buildings, and that by reason of these breaches of the contract the defendant has suffered damage, to wit: from deprivation of the use of said buildings during the delay in completion thereof caused by said delay in shipment, in the sum of sixteen thousand dollars; by reason of the insufficient strength of the building, in the sum of ten thousand dollars; by reason of defective doors, in the sum of three thousand dollars; in all, twenty-nine thousand dollars.

The answer also denies that plaintiff delivered “all” of the materials agreed upon. This is an insufficient denial and is equivalent to an admission that substantially all were delivered. The omission of a single rivet or bolt would satisfy the denial. There is a denial that the value exceeds $16,982.71, but it is conceded that the proof was. sufficient to support the findings on this point. The principal points relied on by appellant relate to the counterclaim,- under the claim that the findings thereon are contrary to the evidence.

The court found that the plaintiff did not agree to furnish “specifications” for the buildings, but only plans and drawings; that the plans and drawings were prepared by plaintiff and were sent to and approved by the defendant; that no specific time was agreed on for the deliveries, except that they were to be furnished as speedily as circumstances would permit ; that plaintiff substantially performed its contract, except that there were certain minor defects, for which allowance was made. As to these the findings are that the value of the material furnished, less payments thereon, was, for the warehouse, $15,300.98; for the forge shop, $10,301.96, and for the lavatory $1982.72, making the total $27,585.66. The minor errors in the warehouse material caused defendant to expend $964.14, and it would cost $140 to remedy the defects in the doors. Deducting the $1104.14 for these defects the bálance remaining is $26,481.52, for which, with interest, judgment *501 was given. The court also found that plaintiff agreed to furnish no plans or drawings for the buildings, other than working plans showing the details of the erection and construction of the material which plaintiff was to furnish, and that plaintiff did not agree that the plans it prepared should provide a second floor strong enough to bear five hundred pounds, or one hundred and fifty pounds, to the square foot, or any other weight; that only such portion of the material to be furnished by plaintiff was to be fabricated by plaintiff as might be necessary to enable the defendant to conveniently and in the usual manner erect the same upon its lot, and that there was no agreement that all the material was to be framed by plaintiff. It is claimed that these findings are not sustained by the evidence.

1. There is no evidence that specifications were to be furnished by the plaintiff. The evidence on the subject related to plans and detail drawings, and they were furnished.

2. The plans and drawings were sent to defendant long before the material was furnished, and they were either expressly approved, or received without objection, and acted on by defendant, after full opportunity to ascertain their character. The only objection, if it can be called such, which is called to our attention, was made in a letter written several months after the plans and drawings were received by defendant and after they had been repeatedly examined by its officers in charge of the work. The finding that the plans and drawings were approved by defendant is amply supported by the evidence.

3. With respect to the alleged agreement as to time of deliveries there is some conflict. We must take that most favorable to the plaintiff, because it is presumed that the trial court did so. In May, 1906, Abner Doble, as agent for defendant, had a conversation with Geddes, who was a special agent of plaintiff for the sale of a different kind of material from that sold to defendant by plaintiff. Doble said his company was making designs for a warehouse and forge shop to be erected on its lot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Galeb Paving v. D.L. Falk Construction CA1/2
California Court of Appeal, 2014
Roundup Cattle Feeders v. Horpestad
603 P.2d 1044 (Montana Supreme Court, 1979)
Williams v. Elliott
273 P.2d 953 (California Court of Appeal, 1954)
Brooks v. Fidelity Savings & Loan Ass'n
128 P.2d 711 (California Court of Appeal, 1942)
California Corrugated Culvert Co. v. Stewart
8 P.2d 1013 (California Supreme Court, 1932)
Morel v. Simonian
284 P. 694 (California Court of Appeal, 1930)
Easom v. General Mortgage Co.
281 P. 514 (California Court of Appeal, 1929)
Sun Oil Co. of California v. Union Drilling & Petroleum Co.
280 P. 535 (California Supreme Court, 1929)
Cambridge Co. v. City of Elsinore
206 P. 1021 (California Court of Appeal, 1922)
Thomas Haverty Co. v. Jones
197 P. 105 (California Supreme Court, 1921)
Murray v. California Conservating Co.
193 P. 959 (California Court of Appeal, 1920)
Pueblo v. Zamorano
28 P.R. Dec. 722 (Supreme Court of Puerto Rico, 1920)
Roebling Construction Co. v. Doe Estate Co.
165 P.2d 547 (California Court of Appeal, 1917)
Boscus v. Bohlig
162 P. 100 (California Supreme Court, 1916)
Lapp-Gifford Co. v. Muscoy Water Co.
134 P. 989 (California Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
123 P. 290, 162 Cal. 497, 1912 Cal. LEXIS 562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-laughlin-steel-co-v-abner-doble-co-cal-1912.