Murray v. California Conservating Co.

193 P. 959, 49 Cal. App. 625
CourtCalifornia Court of Appeal
DecidedOctober 19, 1920
DocketCiv. No. 3538.
StatusPublished

This text of 193 P. 959 (Murray v. California Conservating Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murray v. California Conservating Co., 193 P. 959, 49 Cal. App. 625 (Cal. Ct. App. 1920).

Opinion

RICHARDS, J.

This is an appeal from a judgment in favor of the plaintiff for the sum of $2,305.23. The facts out of which the defendant’s alleged liability arose were the following: In the month of September, 1917, the defendant had completed a building in connection with its packing plant in Hayward, which was to be used for packing and canning tomato products. On the top floor of this building was a room equipped with twenty-five large copper kettles, which were to be used in heating tomato pulp for the purpose of exhausting a certain quantity of water therefrom as to make the product fit for commercial purposes. It was found that when this portion of the plant was put in operation the said room became filled with steam so as to make it impossible for men to remain at work therein for any considerable length of time. It became necessary to remedy this condition immediately, and with that end in view the defendant’s superintendent of the plant requested the plaintiff to call at the plant on the afternoon of September 27, 1917, for the purpose of consultation as to how to effectually remove the practical difficulties of the situation. The plaintiff suggested a system of ventilation by the use of fans and motors, and it was agreed that he should investigate the matter and report with respect to such system and the cost of installing the same. A few days later the plaintiff submitted a proposition in writing in which, representing the company with which he was connected, it was proposed to furnish and install certain fans and motors of specified sizes and power, together with the switch-boxes, starting devices, belting, and wires necessary to connect the same with the defendant’s wiring system already installed in the building. By the terms of this proposition all necessary connecting, framing, carpenter work, housing, and the furnishing of all labor and material necessary for the installation of said motors and fans except that above specified was to be furnished by the defendant as the owner of the building. The plaintiff’s proposition embraced the following statement: “It is the intention and understanding *627 that the three exhaust fans on the roof will exhaust the air and surplus steam from the room directly helow and the 2-24" fans in the window spaces will deliver fresh air into the room, thus making the work room as habitable as it is ordinarily expected of a room of its kind. Above work for the sum of $1,500.” The defendant, acting through its said superintendent, accepted the foregoing proposition, and the work of installing the ventilating system was at once entered upon and, in so far as the plaintiff was concerned was completed on or about October 4, 1917. The system was at once put in operation, and for a portion of the first day apparently accomplished the purpose for which it was installed, namely, that of clearing the room of steam. Toward the close of said day, however, it was found that the motors stopped and refused to further function. The cause of this stoppage was apparently due to the fact that the defendant had not properly or sufficiently done the work of constructing certain conduits and housings for the protection of the motors and other material which the plaintiff had installed from the effect of the steam arising from the boiling mixture. When this fact was discovered a further oral agreement was made between the plaintiff and the superintendent of the defendant by which certain additional work -was to be done by the former for the purpose of remedying these discovered defects. The plaintiff proceeded to do this extra work at an expense to him of $805.23. In the meantime, however, the defendant had not done certain work which it was to do for the purpose of housing the motors, and the result was that they again refused to function after a short period of trial on account of their contact with the steam of the superheated room. Thereupon the defendant, without further consultation with the plaintiff, removed all of the material used in the ventilating system installed by the plaintiff, and informed him that it did not wish him to do anything further in relation to the matter. The plaintiff demanded payment of the sum of $1,500 claimed to be due upon his accepted proposition, and the further sum of $805.23 for the extra work performed. These demands being by the defendant refused the plaintiff instituted the present action.

The complaint filed herein was in the form of the common count for work and labor done and performed and material *628 furnished by plaintiff to defendant, at the special instance and request of the latter, of the reasonable value of $2,305.23. The answer of the defendant consisted in specific denials of the averments of the plaintiff’s complaint, and the cause went to trial upon the issues thus framed. At the time of trial the defendant presented and was permitted to file a further and separate answer, alleging in substance, though not in express terms, the agreement between the parties with reference to the installation of said ventilating system, and then proceeding to aver that such ventilating system so installed under said agreement had proven unsatisfactory, and had failed to so exhaust the air and surplus steam from the premises, or to so deliver fresh air into the same as to render the same habitable or to make it possible for the workmen of defendant to continue their labors in the said room, and that for that reason the defendant had been compelled to' remove and did remove the plaintiff’s ventilating system from the premises.

Upon the introduction of evidence pro and con upon the issues thus framed the cause was presented to the jury under the instructions of the court, and the jury presently returned a verdict in the plaintiff’s favor for the full sum demanded in his complaint. From the judgment entered upon such verdict the defendant prosecutes this appeal.

The first contention of the appellant is that the trial court was in error in giving to the jury the following instruction: “If you find from the evidence that a portion of the work incidental to the ventilating system was to be done by the defendant corporation, then there was an implied contract on the part of the defendant to perform its share of such work in such manner as to enable the plaintiff to complete his share of the work in the manner agreed upon. And if you find that the defendant failed to perform in a workmanlike manner its share of the work, and such failure prevented plaintiff from completing the work, then your verdict should be in favor of plaintiff and against defendant.”

And again: “If the ventilating apparatus failed to ventilate the building because of careless or unskillful installation by the employees of the defendant of the wiring system, or the failure to house, or the careless or unskillful housing, *629 by the employees of the defendant of any of the motors which constituted part of such ventilating system, then the defendant, and not the plaintiff, is answerable for such failure.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones & Laughlin Steel Co. v. Abner Doble Co.
123 P. 290 (California Supreme Court, 1912)
Brown v. Crown Gold Milling Co.
89 P. 86 (California Supreme Court, 1907)
Griffith v. Happersberger
25 P. 137 (California Supreme Court, 1890)

Cite This Page — Counsel Stack

Bluebook (online)
193 P. 959, 49 Cal. App. 625, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murray-v-california-conservating-co-calctapp-1920.