Rialto Construction Co. v. Reed

118 P. 473, 17 Cal. App. 29, 1911 Cal. App. LEXIS 10
CourtCalifornia Court of Appeal
DecidedAugust 24, 1911
DocketCiv. No. 579.
StatusPublished
Cited by7 cases

This text of 118 P. 473 (Rialto Construction Co. v. Reed) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rialto Construction Co. v. Reed, 118 P. 473, 17 Cal. App. 29, 1911 Cal. App. LEXIS 10 (Cal. Ct. App. 1911).

Opinion

*31 KERRIGAN, J.

In this case there are two appeals, both from the judgment, one being taken by plaintiff, and the other by the defendant.

A brief outline of the facts of the ease is as follows: On September 20, 1905, C. E. Loss entered into a contract with the Ocean Shore Railway Company to perform all the grading work, track-laying and surfacing for the company’s double track railroad from its initial point in San Francisco to Scott Creek in Santa Cruz county, being a distance of about sixty-seven miles. The contract, among other things, contained a classification of the materials to be worked, said materials being classified as earth, loose rock, solid rock, etc. On October 2, 1905, C. E. Loss sublet certain parts of the work, constituting what were known as sections 4 and 5 thereof, to Mahoney Bros, and Malley, copartners, the predecessors and assignors of plaintiff. In January, 1906, Ma-honey Bros, and Malley, on the one part, and the defendant on the other, confirmed in writing a previous oral agreement between them, whereby the defendant was to perform that portion of the work known as section 4. Prior to February 27, 1906, Mahoney Bros, and Malley had transferred to plaintiff all their interest in the contract of October 2, 1905, and on that day plaintiff and defendant entered into a contract whereby the defendant was to perform the work on section 4. This contract, which took the place of the one between defendant and Mahoney Bros, and Malley, is the one by which the rights of the parties hereto are to be determined.

It provided in part as follows: ‘ ‘ The said Rialto Construction Co. agrees to furnish the said Reed, or his order, with the necessary hay and grain for the said stock, and supplies for the men engaged upon the work, at cost price, and also agrees to pay weekly the time checks issued to his employees by the said Reed for work performed upon section 4, in accordance with the contract. ... It is understood that all money earned by said Reed shall be first applied to the payment of said time checks, and the said supplies and the said hay and grain, and all other bills incurred by said Reed in the prosecution of this work, before any of it shall be used by said Reed for any other purpose. The said Reed is to be *32 paid for the performance of said work as follows: earth, 18c per cubic yard; loose rock, 28c per cubic yard; solid rock, 50c per cubic yard.”

Each of the contracts mentioned provided that the estimate of the engineer of the Ocean Shore Railway Company, both as to classification and quantity of materials moved, as also the construction placed by said engineer upon the contract and specifications, were to be final and conclusive, and binding upon the parties.

Under the contract between the parties hereto of February 27th defendant performed certain excavating and grading work upon said section 4, and was engaged in the performance of this work at the time of the earthquake occurring in San Francisco and vicinity in April, 1906, at which time operations were suspended by direction of the railway company, and have not been resumed by the defendant. In the following month the chief engineer prepared a classification and final estimate of the work done by defendant.

Plaintiff alleges that it disbursed under the contract for the account of the defendant the sum of $21,965.10, upon which it has been reimbursed $15,622.78, leaving a balance of $6,342.32, which is the amount sued for by plaintiff.

To the complaint defendant interposed a counterclaim for $9,906.57, based upon an alleged erroneous classification by the chief engineer of the work involved. The case was tried with a jury, which rendered the following verdict: “We, the jury in the above-entitled cause, find a verdict in favor of the plaintiff in the sum of $6,842.32. We further find for the defendant $4,500 because of erroneous classification.”

In accordance with the verdict a judgment was duly entered. From that part thereof awarding plaintiff the sum of $6,842.32 the defendant has appealed; and from the part awarding $4,500 to the defendant the plaintiff has appealed. The two appeals will be considered together.

The contract sued on provides that the chief engineer of the railway company is empowered to decide, and' his decision is made final and conclusive, as to the classification and quantity of materials moved, and plaintiff is correct in stating that this provision of the contract is binding on the parties thereto in the absence of an averment and proof of fraud or such gross mistake as to imply fraud. (Cook v. *33 Foley, 152 Fed. 41, [81 C. C. A. 237] ; Martinsburg etc. R. R. Co. v. March, 114 U. S. 549, [5 Sup. Ct. Rep. 1035, 29 L. Ed. 255]; Chicago etc. R. Co. v. Price, 138 U. S. 185, [11 Sup. Ct. Rep. 290, 34 L. Ed. 917] ; Memphis Trust Co. v. Brown-Ketchum Iron Works, 166 Fed. 398, [93 C. C. A. 162].) But contrary to plaintiff’s contention there is in this case an allegation in the counterclaim appropriate in all respects to raise the question of gross mistake; and we also think without hesitation, after having carefully read all the testimony in the case, consisting of over five hundred pages, that the evidence is sufficient to sustain the implied finding of the jury that the estimate certified by the chief engineer of the railway company was palpably inaccurate. It would be tedious and not worth while to review or even summarize the evidence. The jury, believing, as they evidently did, the testimony introduced by the defendant on the subject, it was for them to say whether the erroneous estimate made by the chief" engineer was as to such classification a mere error of figures, or in judgment, or such a negligent or careless mistake as to indicate bad faith. They adopted the latter view, and under the circumstances of the case we cannot disturb their finding.

The court, at one place in its charge, instructed the jury: “That the engineer’s estimates are not conclusive upon the defendant; but defendant is entitled to be paid the prices called for in his contract for the work which he performed under the contract.”

It may be conceded that this instruction standing alone does not correctly state the law applicable to the facts of the case; but immediately following that instruction the court said: “I further charge you that before you can set aside the certificate of the chief engineer of the Ocean Shore Railway Company, which, by the terms of the contract between the parties, was made final as to yardage and classification, you are entitled to have submitted to you clear and convincing evidence to overcome the presumption that the certificate correctly stated the facts in that respect. Mere difference in the classification reached by the Ocean Shore engineer and that claimed by the defendant does not justify you in setting aside such certificate. The difference must be so large, the disregard of the defendant’s rights must be so *34

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Datta v. Staab
343 P.2d 977 (California Court of Appeal, 1959)
Pullen v. Heyman Bros.
162 P.2d 961 (California Court of Appeal, 1945)
Wenzel & Henoch Const. Co. v. Metropolitan Water Dist.
18 F. Supp. 616 (S.D. California, 1937)
American Trust Co. v. Coryell
43 P.2d 1102 (California Supreme Court, 1935)
Monson v. Fischer
5 P.2d 628 (California Court of Appeal, 1931)
Guarantee Title & Trust Co. v. Willis
297 P. 445 (Arizona Supreme Court, 1931)
Odell v. Colmor Irrigation & Land Co.
280 P. 398 (New Mexico Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
118 P. 473, 17 Cal. App. 29, 1911 Cal. App. LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rialto-construction-co-v-reed-calctapp-1911.