Brown v. Aguilar

259 P. 735, 202 Cal. 143, 1927 Cal. LEXIS 325
CourtCalifornia Supreme Court
DecidedSeptember 14, 1927
DocketDocket No. S.F. 11647.
StatusPublished
Cited by29 cases

This text of 259 P. 735 (Brown v. Aguilar) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Aguilar, 259 P. 735, 202 Cal. 143, 1927 Cal. LEXIS 325 (Cal. 1927).

Opinion

PRESTON, J.

By the complaint in this action it is alleged that on June 29, 1922, plaintiff’s assignor, a contractor, entered into a written agreement with defendant whereby said contractor agreed to furnish the necessary labor and materials required for the construction of a one-story brick and concrete garage in San Francisco, and said defendant agreed to pay to the contractor therefor the sum of $3,000; that said contractor furnished the necessary labor and materials and constructed said garage and fully performed all of the terms and conditions of said agreement on his part to be performed, “except such, if any, as were waived or changed by defendant; and that one Frank S. Holland, who was the architect and agent employed by defendant to draw plans for and supervise the construction of said garage, after the completion of said garage issued as such architect, his certificate stating that the final payment was due under said agreement, and during the progress of said construction issued his certificate for the two progressive payments as provided in said agreement”; that defendant entered into possession of the garage and paid on account of said $3,000 the sum of $1,000, leaving a balance of $2,000 due, owing and unpaid; that said contractor duly assigned said agreement and all rights thereunder to this plaintiff, wherefore plaintiff prayed judgment against said defendant in amount of $2,000.

Defendant filed an answer, counterclaim, and cross-complaint; also first, second, and third amended answers. The articles of agreement signed by defendant and said contractor are set forth in full in paragraph I of the third amended answer. It is further alleged therein that said garage was not constructed in accordance with the terms, plans or specifications of said agreement; that inferior and unsuitable materials were used; that the garage building was negligently and carelessly erected partly upon land of the next adjacent property owner, necessitating reconstruction or removal by defendant; that defendant, by reason of failure *146 of said contractor to complete said building within the stipulated time, lost $450 in prospective rentals, covering a period of eighteen months. Said pleading “admits that one Frank S. Holland who was the architect and agent employed by defendant to draw plans for and supervise the erection of said garage issued his certificate stating that the final payment was due under said agreement and during the progress of said construction issued his certificates for two progressive payments as provided in said agreement,” but it is alleged that said certificates were issued by said architect improperly and in error.

The court found for plaintiff on all points. It found that the garage was properly constructed, without encroaching upon the adjacent owner’s property; that proper materials were used; that the delay in completion was excusable, being due to inclement weather and to obstructive action of labor organizations; that there was no evidence showing loss of prospective rentals; that said architect during the progress of said construction properly issued his certificate for the two progressive payments as provided in said agreement, and properly issued his certificate stating final payment was due; and that such slight changes as were made in the specifications were made by defendant, through said architect. Judgment was accordingly rendered for plaintiff in amount of $2,236.88.

The first question is: Did the contractor fully perform, or at least substantially perform, said contract so as to enable respondent to recover under the doctrine of substantial performance? Appellant sets forth much testimony in an effort to show delay in completion, improper encroachment and many other variations from the drawings and written specifications. These are all questions of fact upon which we are bound by the findings of the trial court when supported by proper evidence. In other words, it is unnecessary for us to review the testimony at length herein. It is sufficient to state that there is evidence in abundance to support the findings, and each of them, and they are, therefore, conclusive upon appeal as to these matters.

Furthermore, it would seem that there was indeed such a performance by the contractor of his obligations under the contract as would entitle respondent to recover under the doctrine of substantial performance. This doctrine is well *147 stated in the following quotation from Connell v. Higgins, 170 Cal. 541, 556 [150 Pac. 769, 774], in which case a similar situation was involved: “The criticism is that the jury were not informed what was meant by the term substantial performance and that they were, therefore, left to infer, if they chose, that if the plant, as constructed, would do the work which the owner desired it to do, the plaintiff could recover as for completion, altho it might, in many particulars, vary from the plans and specifications, or lack completion as the plans and specifications required. The defendant did not offer any instruction on this subject, as he might well have done. The definition of substantial performance is difficult to give in general terms. It is usually a question to be determined in each case with reference to the existing facts and circumstances. In 2 Elliott on Contracts, section 1607, it is defined as follows (p. 912):

“ ‘Substantial performance means that there has been no wilful departure from the terms of the contract, and no omission of any of its essential parts, and that the contractor has in good faith performed all of its substantive terms. If so, he will not be held to have forfeited his right to recovery by reason of trivial defects or imperfections in the work performed. If the omission is so slight that it cannot be regarded as an integral or substantive part of the original contract, and the other party can be compensated therefor by a recoupment for damages, the contractor does not lose his right of action; and this rule is peculiarly applicable in a case where the other party has received the benefit of what has been done, and is enjoying the fruits of the work. It is the sound and settled rule that the right of a party to enforce a contract will not be forfeited or lost by reason of technical inadvertence, or unimportant omissions or defects. A substantial performance must be established, in order to entitle the party claiming the benefit of the contract to recover; but this does not mean a literal compliance as to the details that are unimportant. There must be no wilful or intentional departure and the defects of performance must not pervade the whole or be so essential as substantially to defeat the object which the parties intend to accomplish. Whether, in any case, such defects or omissions are substantial, or merely unimportant mistakes that have been or may be corrected, is generally a *148 question of fact.’ This we believe to be a correct statement of the law on the subject.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herzog v. Super. Ct.
California Court of Appeal, 2024
Coral Farms, L.People v. Mahony
California Court of Appeal, 2021
Thurman v. Bayshore Transit Management, Inc.
203 Cal. App. 4th 1112 (California Court of Appeal, 2012)
Security Pacific National Bank v. Matek
175 Cal. App. 3d 1071 (California Court of Appeal, 1985)
Bulmash v. Davis
597 P.2d 469 (California Supreme Court, 1979)
Acoustics, Inc. v. Trepte Construction Co.
14 Cal. App. 3d 887 (California Court of Appeal, 1971)
Joslin v. Marin Municipal Water District
429 P.2d 889 (California Supreme Court, 1967)
A. Teichert & Son, Inc. v. State of Cal.
238 Cal. App. 2d 736 (California Court of Appeal, 1965)
Kerr Land & Timber Co. v. Emmerson
233 Cal. App. 2d 200 (California Court of Appeal, 1965)
Meredith v. Marks
212 Cal. App. 2d 265 (California Court of Appeal, 1963)
Muller v. Muller
209 Cal. App. 2d 704 (California Court of Appeal, 1962)
Bause v. Anthony Pools, Inc.
205 Cal. App. 2d 606 (California Court of Appeal, 1962)
Rubino v. Board of Trustees
191 Cal. App. 2d 366 (California Court of Appeal, 1961)
Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
Hagginwood Sanitary District v. Downer Corp.
179 Cal. App. 2d 756 (California Court of Appeal, 1960)
Retail Clerks' Union v. Superior Court
339 P.2d 839 (California Supreme Court, 1959)
Zar v. Zar
316 P.2d 685 (California Court of Appeal, 1957)
Garrado v. Collins
288 P.2d 620 (California Court of Appeal, 1955)
Johnson v. Comptoir Franco-Belge D'Exportation Des Tubes D'Acier
288 P.2d 151 (California Court of Appeal, 1955)
Williams v. Elliott
273 P.2d 953 (California Court of Appeal, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
259 P. 735, 202 Cal. 143, 1927 Cal. LEXIS 325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-aguilar-cal-1927.