Pease & Sons, Inc. v. Turner Construction Company

CourtCourt of Appeals of Washington
DecidedJuly 23, 2024
Docket58748-3
StatusUnpublished

This text of Pease & Sons, Inc. v. Turner Construction Company (Pease & Sons, Inc. v. Turner Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pease & Sons, Inc. v. Turner Construction Company, (Wash. Ct. App. 2024).

Opinion

Filed Washington State Court of Appeals Division Two

July 23, 2024 IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II PEASE & SONS, INC., a Washington No. 58748-3-II corporation,

Respondent,

v.

TURNER CONSTRUCTION COMPANY; UNPUBLISHED OPINION

Appellant.

LIBERTY MUTUAL INSURANCE COMPANY, Bond No. 015050441 and Bond No. 015050440; TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, Bond No. 106425855 and Bond No. 106425854; FIDELITY AND DEPOSIT COMPANY OF MARYLAND / ZURICH AMERICAN INSURANCE COMPANY, Bond No. 9194346 and Bond No. 9194345; FEDERAL INSURANCE COMPANY, Bond No. 8239-43-69 and Bond No. 8239-43-68; THE CONTINENTAL INSURANCE COMPANY; Bond No. 929626860 and Bond No. 9296266859; XL SPECIALTY INSURANCE COMPANY, Bond No. US00073098SU16A and Bond No. US00073097SU16A; METROPOLITAN PARK DISTRICT OF TACOMA, WASHINGTON,

Defendants. PEASE & SONS, INC., a Washington corporation,

Third-Party Plaintiff,

GERDAU REINFORCING STEEL, a general partnership, and CMC STEEL FABRICATORS, INC., a foreign corporation, Third-Party Defendants. No. 58748-3-II

CHE, J. ⎯ Turner Construction appeals a bench trial judgment awarding its subcontractor,

Pease & Sons, claims for overtime, attorney fees, and costs.

Metropolitan Park District of Tacoma (MetroParks) hired Turner as the prime contractor

to build the Pacific Rim Aquarium. Pease submitted a bid for the concrete construction work on

the aquarium. To submit a bid, Pease had to accept Turner’s subcontract without modification,

which included a term limiting the time to bring a breach of contract claim to within one year of

a subcontractor’s substantial completion of its work. The information given to prospective

bidders included Turner’s proposed schedule for the project, which did not factor in requirements

from MetroParks such as how long concrete had to cure before supporting forms could be

removed, and requirements for the design of the aquarium tanks that increased the complexity of

construction. Turner hired Pease to complete the concrete work.

The project experienced delays and fell far behind Turner’s planned schedule. At

Turner’s direction, Pease and other contractors worked overtime to try to mitigate the delays.

Turner blamed Pease and other subcontractors for the delays, while the subcontractors blamed

Turner’s misleading scheduling. Pease finished its work on the project in early 2018, but

MetroParks did not certify that the aquarium was substantially complete until June 2018.

In April 2019, Pease sued Turner for overtime and other claims stemming from breach of

the subcontract. Turner counterclaimed against Pease for breach of the subcontract. After a

bench trial, a trial court dismissed Turner’s counterclaims and awarded Pease damages for

overtime, while dismissing Pease’s other claims due to waiver and failure to comply with

2 No. 58748-3-II

subcontract notice requirements. The trial court also awarded Pease attorney fees, costs, and

prejudgment interest.

Turner appeals, arguing that (1) Pease filed its complaint outside the one-year limitation

period in the subcontract, (2) the trial court erred by ruling that the subcontract limitation period

was unconscionable and unenforceable, (3) Pease did not adequately notify Turner of its

overtime claims, (4) Pease waived its overtime claims through lien releases in pay applications,

(5) “pay-if-paid” clauses in the subcontract limited Pease’s recovery, and (6) the trial court erred

by awarding Pease attorney fees and costs. Pease responds that Turner waived its contract

limitation period, lien release, and “pay-if-paid” defenses. Both parties seek appellate attorney

fees and costs.

We affirm. We hold that the trial court’s findings supported its conclusion that Pease’s

claim was timely. Because we affirm on this ground, we need not reach the questions about

whether the contract limitation period was unconscionable or whether Turner waived that

defense. Further, substantial evidence supported the trial court’s findings that Turner directed

Pease to work overtime, that Pease did not have to separately notify Turner of the costs of

working overtime, and that Pease did not waive its overtime claims through lien releases.

Overall, we hold that the trial court’s findings supported its conclusions that Pease was entitled

to damages for overtime. And the “pay-if-paid” clauses do not limit Pease’s recovery. Finally,

we hold that the trial court did not err by awarding Pease attorney fees and costs, we deny

Turner’s request for appellate attorney fees, and we grant Pease’s request for appellate attorney

3 No. 58748-3-II

FACTS

I. BACKGROUND

A. Bid Process

MetroParks is a municipal corporation that manages recreation sites and services around

Tacoma, including the Point Defiance Zoo. Turner is a New York corporation that performs

construction work in Washington.

In 2015, MetroParks hired Turner as general contractor/construction manager (GM/CM)

to lead construction on the new Pacific Rim Aquarium at the Point Defiance Zoo & Aquarium.

Turner had retainage and performance bonds with Liberty Mutual Insurance Company, Travelers

Casualty and Surety Company of America, Fidelity and Deposit Company of Maryland/Zurich

American Insurance Company, Federal Insurance Company, The Continental Insurance

Company, and XL Specialty Insurance Company (collectively, “the Sureties”).

1. Prime Contract

The prime contract between Turner and MetroParks “required Turner to provide

recommendations to Metro Parks on constructability, construction time requirements,

construction and construction trades phasing and coordination, [and] a site work plan and work

schedule.” Clerk’s Papers (CP) at 1734 (Findings of Fact (FOF) 32). Turner also had to solicit

subcontractors for each “bid package” of trade work (such as excavation, concrete, mechanical,

electrical, and plumbing) that the project required. And the prime contract required Turner to

manage construction, including “scheduling the construction work and coordinating [] all

subtrade work.” CP at 1734 (FOF 32).

4 No. 58748-3-II

The prime contract provided that the aquarium would “be deemed Substantially

Complete when the tank exhibits have been completed, tested, commissioned[,] and accepted by

the Owner as ready to accept introduction of live marine animal wildlife specimens and the

Owner’s staff may occupy the building.” Ex. 91 at 221.

MetroParks also imposed constraints on how the aquarium was to be built. These

constraints included a prohibition on using shotcrete (a kind of concrete that is sprayed instead of

poured) in tank walls; a prohibition on horizontal joints between concrete slabs in the tank walls,

which made pouring those walls more complex; and requirements that concrete cure for 7 days

in architectural walls and 14 days in tank walls before supporting forms could be removed.

2. Concrete Work Bid Manual

Turner provided informational bid documents to prospective bidders for roughly 30 bid

packages of subtrade work. The bidding manual for the concrete package included a preliminary

“rolled up” schedule and work sequence. The “rolled up” schedule summarized each component

of the project, but did not include every individual activity, or all of the tasks that other non-

concrete subcontractors would need to perform.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bignold v. King County
399 P.2d 611 (Washington Supreme Court, 1965)
US Life Credit Life Ins. v. Williams
919 P.2d 594 (Washington Supreme Court, 1996)
Foote v. VIKING INSURANCE CO.
790 P.2d 659 (Court of Appeals of Washington, 1990)
Nationwide Mutual Fire Insurance v. Watson
840 P.2d 851 (Washington Supreme Court, 1992)
Cook v. Brateng
262 P.3d 1228 (Court of Appeals of Washington, 2010)
King v. Snohomish County
47 P.3d 563 (Washington Supreme Court, 2002)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
LAKEVIEW v. Apartment Sales Corp.
6 P.3d 74 (Court of Appeals of Washington, 2000)
Sime Construction Co. v. Washington Public Power Supply System
621 P.2d 1299 (Court of Appeals of Washington, 1981)
Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)
Skinner v. Holgate
173 P.3d 300 (Court of Appeals of Washington, 2007)
SCOCCOLO CONST. v. City of Renton
145 P.3d 371 (Washington Supreme Court, 2006)
General Construction Company v. Public Utility District No. 2
380 P.3d 636 (Court of Appeals of Washington, 2016)
U.S. Life Credit Life Insurance v. Williams
129 Wash. 2d 565 (Washington Supreme Court, 1996)
King v. Snohomish County
146 Wash. 2d 420 (Washington Supreme Court, 2002)
Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Scoccolo Construction, Inc. v. City of Renton
158 Wash. 2d 506 (Washington Supreme Court, 2006)
Barton v. Department of Transportation
308 P.3d 597 (Washington Supreme Court, 2013)
1519-1525 Lakeview Boulevard Condominium Ass'n v. Apartment Sales Corp.
101 Wash. App. 923 (Court of Appeals of Washington, 2000)
Skinner v. Holgate
141 Wash. App. 840 (Court of Appeals of Washington, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Pease & Sons, Inc. v. Turner Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pease-sons-inc-v-turner-construction-company-washctapp-2024.