J. R. Youngdale Construction Co. v. United States

504 F.2d 1124, 20 Cont. Cas. Fed. 83,423, 205 Ct. Cl. 578, 1974 U.S. Ct. Cl. LEXIS 22
CourtUnited States Court of Claims
DecidedOctober 23, 1974
DocketNo. 92-73
StatusPublished
Cited by3 cases

This text of 504 F.2d 1124 (J. R. Youngdale Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. R. Youngdale Construction Co. v. United States, 504 F.2d 1124, 20 Cont. Cas. Fed. 83,423, 205 Ct. Cl. 578, 1974 U.S. Ct. Cl. LEXIS 22 (cc 1974).

Opinion

Per Curiam :

Tbis case comes before the court on defendant’s motion, filed April 8, 1974, requesting that the court adopt, as the basis for its judgment in this case, the recommended decision of Senior Trial Judge Mastin G. "White, filed January 22, 1974, pursuant to Eule 166(c) on plaintiff’s motion and defendant’s cross-motion for summary judgment. Upon consideration thereof, without oral argument, it appears that the trial judge by order of March 6, 1974, made certain amendments to the said recommended decision, that plaintiff has filed no request for review by the court of either the recommended decision of January 22, 1974, or the order of March 6, 1974, and that the times for so doing pursuant to the Eules of the Court have expired. Since the court agrees with the trial judge’s recommended decision, as amended, as hereinafter set forth, it hereby grants defendant’s motion of April 8, 1974, and adopts the amended recommended decision as the basis for its judgment in this case. Therefore, plaintiff’s motion and the defendant’s cross-motion for summary judgment are denied without prejudice; and pursuant to 28 U.S.C. § 1491, as amended by Public Law 92-415 (86 Stat. 652), the plaintiff’s aggregate claim is remanded to the Armed Services Board of Contract Appeals for the holding of such hearing or hearings as may be deemed advisable and for a determination, in the first instance, as to whether a waiver of the plaintiff’s 6-day delay in mailing the appeal is warranted, and, if such waiver is granted, for a determination on the merits of the plaintiff’s aggregate claim. Further judicial proceedings are suspended for a period of not to exceed 6 months pending the completion of the remand proceedings. The attorney of record for the plaintiff is designated to advise the court of the status of the remand proceedings at intervals of 90 days or less.

OPINION OP TRIAL JUDGE

White, Senior Tried Judge:

The plaintiff in this case asks the court to review the action of the Armed Services Board of Contract Appeals (“ASBCA”) in dismissing as untimely, [580]*580an appeal which the plaintiff had taken from a decision by the contracting officer under Contract No. N62474-70-C-0615 (“the contract”) between the plaintiff and the defendant (represented by a contracting officer of the Naval Facilities Engineering Command, Department of the Navy). The ASBCA did not hold a hearing for the reception of oral or documentary evidence in connection with the consideration of the appeal,1 but dismissed the appeal on the basis of documents that were available to the ASBCA. The factual statements in this opinion are based on the same documents.

The contract involved the construction by the plaintiff of barracks for enlisted men at the Naval Auxiliary Air Station, Fallon, Nevada. The plaintiff was to be paid $1,504,500 for the work.

The contract contained the standard “disputes” provision that is customarily found in Government construction contracts. It stated (among other things) that “The decision of the Contracting Officer [on a dispute concerning a question of fact arising under the contract] shall be final and conclusive unless, within 30 days from the date of receipt of such copy, the Contractor mails or otherwise furnishes to the Contracting Officer a written appeal addressed to the head of the agency involved.”

On January 29, 1971, the plaintiff proposed to the Navy Department that the “mix design * * * [for precast lightweight concrete be] made up with a naturalite material in lieu of man-made aggregate material.” The Navy Department’s Resident Officer in Charge of Construction Contracts at the Naval Auxiliary Air Station, Fallon, Nevada (“the resident officer”), responded on April 8, 1971, by informing the plaintiff “that the contractor’s proposed use of ‘naturalite’ as a lightweight concrete aggregate as forwarded by contractor’s Submittal No. 1 dated 29 January 1971 is disapproved,” and by directing the contractor “to use lightweight concrete aggregate which complies with the applicable portions of the subject contract specification, Section 3A., Concrete Construction.” Section 3A of the contract [581]*581specifications related to cast-in-place lightweight concrete and required that the aggregate be either expanded shell, expanded clay, expanded slate, or expanded slag.

A telegram dated March 10, 1971, from the plaintiff to the resident officer stated in part as follows:

We are forthwith proceeding with revising our mix design to comply with the Governments demand so as to preclude further unnecessary delays to the project. However, we are doing so under protest as we consider Governments demand to be a change within the realm of Clause 3, Changes of the General Provisions of our contract.
All costs incurred as a result of Governments action stated herein above will be submitted as soon as same are ascertainable, together with complete justification therefor.

In a letter dated April 28,1971, and addressed to the resident officer, the plaintiff requested the issuance of a change order to cover the added expense allegedly incurred because of the Government’s requirement that man-made aggregate be used for precast lightweight concrete, and also requested a 30-day extension of the time prescribed in the contract for the completion of the work under the contract. Accompanying this letter was a detailed statement of the additional costs claimed by the plaintiff, totaling $20,728.

On August 26,1971, and again on November 19,1971, the plaintiff wrote to the resident officer and requested information concerning the status of the aggregate claim. The resident officer apparently did not reply to either of these communications. However, on December 8, 1971, the Officer in Charge of Construction, Western Division, Naval Facilities Engineering Command, wrote to the plaintiff and denied the claim for additional compensation in the amount of $20,728, and also the claim for a 30-day time extension.

In a letter dated December 29, 1971, and addressed to the Commander of the Naval Facilities Engineering Command, the plaintiff requested reconsideration of the rejection of the claim which the plaintiff had submitted on April 28, 1971. There does not seem to have been any reply to the plaintiff’s communication of December 29, 1971. The plain[582]*582tiff wrote to the same officer again on March 1, 1972, and asked for information concerning the status of the matter. By means of a letter dated March 14, 1972, the plaintiff was informed that its claim had been forwarded “for a contracting officer’s decision.”

The contracting officer’s decision, denying the plaintiff’s aggregate claim, was dated November 21, 1972, and it was received by the plaintiff on November 27,1972.

The plaintiff prepared a written appeal from the contracting officer’s decision and mailed the appeal on January 2, 1978, or 6 days after the expiration of the 30-day period prescribed in the “disputes” provision of the contract for the taking of appeals from decisions by the contracting officer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. R. Youngdale Constr. Co., Inc. v. United States
536 F.2d 369 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
504 F.2d 1124, 20 Cont. Cas. Fed. 83,423, 205 Ct. Cl. 578, 1974 U.S. Ct. Cl. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-r-youngdale-construction-co-v-united-states-cc-1974.