Abbett Electric Corp. v. United States

162 F. Supp. 772, 142 Ct. Cl. 609, 1958 U.S. Ct. Cl. LEXIS 150
CourtUnited States Court of Claims
DecidedJune 4, 1958
DocketNo. 591-53
StatusPublished
Cited by19 cases

This text of 162 F. Supp. 772 (Abbett Electric Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abbett Electric Corp. v. United States, 162 F. Supp. 772, 142 Ct. Cl. 609, 1958 U.S. Ct. Cl. LEXIS 150 (cc 1958).

Opinion

Laramore, Judge,

delivered the opinion of the court:

This is a suit to recover the increased costs of performance on a Government, contract. The increased costs are claimed to have resulted from delays caused by the defendant’s failure to give proper notice to proceed as required by the terms of the contract. The facts upon which plaintiff predicates its suit are as follows:

In April 1950, the Bureau of Keclamation, hereinafter referred to as the Bureau, invited bids for the construction of a 230-kilovolt electrical transmission line between Bio Vista and Tracy in the Central Valley of California. The invitation to bid provided that the work was to be divided into two schedules. Schedule No. 1 covered the construction of foundations and the erection of steel towers for the transmission lines. Schedule No. 2 consisted of two parts; Part I provided for the stringing of conductors and overhead ground wires on the towers to be erected under Schedule No. 1, and Part II called for the stringing of conductors and overhead ground wires for the Sacramento and San Joaquin Biver crossings.

Plaintiff submitted a low bid for the work called for under Schedule No. 2, and on May 31, 1950, the plaintiff and the Bureau, acting for the United States, entered into a unit price contract for the work called for by that schedule. The contract was a standard form Government contract which required the defendant to supply the necessary conductors, ground wire, insulators and hardware needed by [611]*611tbe plaintiff for the installation of the transmission line. The specifications which were attached to and made a part of the contract contained the following provision:

22. Commencement, prosecution, and completion of worlc. The contractor shall begin work within twenty (20) calendar days after date of receipt of notice to proceed and shall complete all of the work within the following number of calendar days from the date of receipt of such notice: Schedule No. 1, three hundred and five (805) days; and Schedule No. 2, three hundred and sixty-five (365) days; Provided, That if award of contract for the work under Schedule No. 2 is made to a contractor other than the contractor awarded the contract for work under Schedule No. 1, notice to proceed for the work under Schedule No. 2 will be issued at the discretion of the contracting officer any time within two hundred and forty (240) calendar days for the work under Part I, and two hundred and seventy-five (275) calendar days, for the work under Part II, after date of award of the contract, and the contractor under Schedule No. 2 shall complete all work under Part I within one hundred and twenty-five (125) calendar days and all work under Part II within ninety (90)' calendar days, from the date of receipt by him of such notice. * $ ‡ ¥

Immediately after the consummation of the contract, levees protecting one of the islands in the San Joaquin River broke which caused flooding of a portion of the land over which the transmission line was to be strung. The Bureau upon learning that the levees, which were privately owned and maintained, were not to be rebuilt decided to reroute a portion of the line covered by plaintiff’s contract. It also redesigned the transmission towers increasing the height of their foundations, and new rights-of-way had to be negotiated over the rerouted area.

Plaintiff heard of the flooding and wrote the Bureau on July 26, 1950, asking for the approximate location of the rerouted lines and whether the river crossings were to remain as planned. This letter also requested some idea as to the starting and completion time on the contract. In response the Bureau, on July 28, 1950, sent plaintiff a drawing showing the new routing of the line and advised it that the river [612]*612crossings were about the same as previously specified. The Bureau then stated:

It is estimated, by this office, that the. tower erection for the Rio Vista-Tracy Section of the line will be well enough advanced to enable you to begin stringing operations about October 1. It is estimated that the river crossing towers should be available for stringing approximately December 15. We will endeavor to inform you well in advance of the issuance of Notice to Proceed so that you may make your plans accordingly.

The Bureau, however, did not give the changes to the contractor for the river crossing towers until September 13,1950, and the line towers contractor did not receive its changes until December 21,1950. On November 24,1950, the Bureau notified plaintiff that the proposed dates for issuance of the notices to proceed contained in its letter of July 28,1950, had to be advanced to March 1, 1951, for the line route and to February 15,1951, for the river crossings.

On December 22,1950, the Bureau wrote plaintiff stating that under the contract the Bureau was required to issue a notice to proceed on Part I (line route) within 240 calendar days after the award of the contract and that this time expired on January 26,1951. The Bureau desired to withhold issuance of the notice until work under Schedule No. 1 (construction of the towers) had further progressed. Plaintiff replied agreeing to a postponement upon the condition that the Bureau “reimburse us for any additional costs that we might incur due to increased wages and working conditions demanded and awarded to the Local Unions having jurisdiction”. Thereafter on January 25, 1951, plaintiff received a notice to proceed with its work under Part I. This letter read, in material part, as follows:

Pursuant to the provisions of paragraph 22 of the specifications, you are hereby notified to proceed with the work covered by this contract. The date you receive this letter, as shown on the registry return receipt, will be the effective date in computing the time within which completion of the contract is required.
Inasmuch as the work covered by Schedule 1 of subject specifications is not sufficiently advanced for you to begin your stringing operations, it will be necessary for [613]*613us to grant an extension of time for the completion of your contract. This delay will be made the subject of a Findings of Fact which will be issued at a later date.

On March 1,1951, plaintiff was sent a similar letter regarding the work to be performed under Part II of its contract. The effect of these letters was to give literal notice to proceed as required under the specifications to the contract while at the same time suspending the work which the defendant had a right to do under paragraph 14 of the specifications, page 7.

On August 21,1951, plaintiff was notified that on September 1,1951, it could begin work on Part 1 and that an extension of time for performance would be granted from the date on which notice to proceed was issued until such time as it was possible for plaintiff to proceed. Such an extension on Part I was in fact granted from January 27 to August 31, 1951. A similar letter was received by plaintiff with respect to Part II directing work to begin on the river crossings October 22, 1951. Plaintiff was also granted an extension of time for the period from March 3 to October 21,1951.

As a result of these delays plaintiff was required to carry on its work in unseasonable weather which slowed and inhibited its performance. Realizing that such was the case the defendant further extended the time for performance to the dates upon which each part of the work was formally accepted, i. e.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ruby Emerald Construction Company
Armed Services Board of Contract Appeals, 2018
Optimum Services, Inc.
Armed Services Board of Contract Appeals, 2016
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Precision Pine & Timber, Inc. v. United States
62 Fed. Cl. 635 (Federal Claims, 2004)
Yankee Atomic Electric Co. v. United States
42 Cont. Cas. Fed. 77,396 (Federal Claims, 1998)
Aetna Cas. & Sur. Co. v. Doleac Elec. Co.
471 So. 2d 325 (Mississippi Supreme Court, 1985)
Higgins v. City of Fillmore
639 P.2d 192 (Utah Supreme Court, 1981)
Merritt-Chapman & Scott Corp. v. The United States
439 F.2d 185 (Court of Claims, 1971)
Luria Brothers & Company, Inc. v. The United States
369 F.2d 701 (Court of Claims, 1966)
Luria Bros. & Co. v. United States
369 F.2d 701 (Court of Claims, 1966)
Utah Construction & Mining Co. v. United States
339 F.2d 606 (Court of Claims, 1964)
A. S. Schulman Electric Co. v. United States
145 Ct. Cl. 399 (Court of Claims, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
162 F. Supp. 772, 142 Ct. Cl. 609, 1958 U.S. Ct. Cl. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abbett-electric-corp-v-united-states-cc-1958.