A. S. Schulman Electric Co. v. United States

145 Ct. Cl. 399, 1959 U.S. Ct. Cl. LEXIS 94, 1959 WL 7587
CourtUnited States Court of Claims
DecidedApril 8, 1959
DocketNo. 234-53
StatusPublished
Cited by3 cases

This text of 145 Ct. Cl. 399 (A. S. Schulman Electric Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. S. Schulman Electric Co. v. United States, 145 Ct. Cl. 399, 1959 U.S. Ct. Cl. LEXIS 94, 1959 WL 7587 (cc 1959).

Opinion

Opinion

per curiam:

This is a suit for increased costs under a Government contract. The increased costs are -claimed to have resulted from delays occasioned by the defendant’s failure to give effective notice to proceed, as required by the terms of the contract.

The facts upon which plaintiff relies are substantially the same as those in the case of Abbett Electric Corporation v. United States, 142 C. Cls. 609. In that case, as in the present case, the contract provided a time in which notice -to proceed would be issued. In the Abbett case, as in this -case, notice to proceed was issued by letter which included notice of suspension of the work under the contract. In this climate we held in the Abbett case that the Government had breached the contract by not giving an effective notice to proceed, and that the costs occasioned by the delay growing out of the breach should be borne by the Government.

We now adhere to our former ruling and hold the Gov-ernment breached the instant contract. As a result, plaintiff was delayed and suffered increased costs in the amount ■of $14,547.48, for which it should recover in this action, and judgment will be entered in this amount.

It is so ordered.

FINDINGS OF FACT

The court, having considered the evidence, the report of Trial Commissioner W. Ney Evans, and the briefs and .argument of counsel, makes findings of fact as follows:

, 1. Among the installations of the Central Valley Project ■of California are the Shasta Dam, in the upper reaches of the Sacramento Diver, and the Tracy Pumping Plant, near the mouth of the river. Shasta Dam includes a plant for the generation of electricity. Two transmission lines (described in the evidence as the east side line and the west side line) ■carry electric power from Shasta to Tracy. The instant case [401]*401is concerned with a contract for stringing the wires on towers over a section of the west side line.

2. Separate contracts were made by the Bureau of Reclamation for the manufacture of the towers, for some of the materials to be used in setting up the towers and transmission lines, and for the erection of the towers and the stringing of the wires.

The invitation for bids for the manufacture of steel towers and appurtenances1 for the west line was issued on September 2, 1949. After some delay for refinements in specifications and checking quantities, the opening of bids was set for October 18,1949, and a contract (dated November 15, 1949) was made with a San Francisco steel manufacturer. Deliveries under the contract were to begin in March 1950, and, as far as material here, were to be completed by July 15, 1950.2

3. Invitations for bids for the erection (including the stringing of wires) of the west side transmission line were issued during the early months of 1950. The work was divided among geographic sections, of which the contract in suit (for 42 miles of the line) was an example.

These contracts for the erection of the line were offered to bidders in two schedules. Schedule 1 called for the erection of the towers. Schedule 2 called for stringing the wires. Bidders were permitted to bid on either schedule, singly, or on both schedules together, for the section of the line offered.

For the section involved in this suit, extending from Madison to Rio Vista (and sometimes hereinafter referred to as the Madison-Rio Vista section), separate contracts were made for the two schedules. The contract for the erection of the towers (dated March 8,1950) was awarded to an individual (James H. McFarland) who is hereinafter referred to as McFarland.3

[402]*4024. Part of the east side line had been erected in 1949 and some of it was under construction in 1950. Before the contract described in the preceding finding was made (on March 8, 1950), plaintiff had become the subcontractor for stringing wires on two sections of the east side line and was already at work on one of them.

The section on which plaintiff was at work extended for a distance of approximately 55 or 60 miles, from Elverta to Oroville.4 The towers on that section had been erected in 1949. Plaintiff began the stringing of wires in early 1950 and worked on through the spring, completing the work in the summer.

The second section on which plaintiff held the subcontract for stringing the wires was another 55- to 60-mile stretch from Perkins to Tracy.5 When plaintiff finished the El-verta-Oroville section in the summer of 1950, it moved its men and equipment to the Perkins-Tracy section, and completed that work early in January 1951.

Meanwhile, plaintiff was negotiating for the subcontract on the 18-mile strip between Elverta and Perkins.6 The negotiations culminated in November 1950 with a subcontract for this section, thereby giving plaintiff responsibility, under subcontracts, for stringing the wires over the entire distance (128 to 138 miles) from Tracy to Oroville.

The Madison-Bio Vista section of the west side line was 25 or 30 (air) miles from the Elverta-Perkins and Perkins-Tracy sections of the east side line.

5. Notice to proceed was issued to McFarland on March 28, 1950. His contract called for completion within 340 days from March 29, 1950, or on or before March 4, 1951.7

6. By the contract in suit, dated April 11, 1950, plaintiff undertook to “* * * furnish the materials, and perform the work for stringing conductors and overhead ground wires, under Schedule No. 2 * * * for 230-kilovolt lines * * * [403]*403Madison-Rio Vista Section * * * for tbe consideration of payments to be made to the contractor at the unit prices stated in said schedule, in strict accordance with the specifications, schedules, and drawings * * The contract further provided that “the work shall be commenced and shall be completed as provided in paragraph 22 of Specifications No. 2883.” 8

7. (a) The contract contained many of the standard articles of Government contracts, such as those relating to Changes, Changed Conditions, and Extras (Articles 3,4, and 5), Delays (Article 9), Other contracts (Article 13), and Disputes (Article 15). The contract is in evidence as plaintiff’s Exhibit No. 1, and is incorporated herein by reference. Of the articles listed above, only the last three are deemed material here.9

(b) Article 9 (Delays — Damages) provided for the payment of liquidated damages10 by the contractor for failure to complete the work within the specified time, and qualified the requirement by providing that the contractor should not be charged with liquidated damages “because of any delays * * * due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God * * * acts of the Government, acts of another contractor in the performance of a contract with the Government, * * * and unusually severe weather * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Utah Construction & Mining Co. v. United States
339 F.2d 606 (Court of Claims, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
145 Ct. Cl. 399, 1959 U.S. Ct. Cl. LEXIS 94, 1959 WL 7587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-s-schulman-electric-co-v-united-states-cc-1959.