Cuyahoga Contracting Co. v. City of Port Huron

233 F. 346, 147 C.C.A. 282, 1916 U.S. App. LEXIS 2465
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 9, 1916
DocketNo. 2709
StatusPublished

This text of 233 F. 346 (Cuyahoga Contracting Co. v. City of Port Huron) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cuyahoga Contracting Co. v. City of Port Huron, 233 F. 346, 147 C.C.A. 282, 1916 U.S. App. LEXIS 2465 (6th Cir. 1916).

Opinion

KILLITS, District Judge.

The appellant, Cuyahoga Contracting Company, an Ohio corporation, on February 10, 1902, entered into a contract with the city of Port Huron, Mich., for the construction of a canal in the rear of the city of Port Huron extending from Take Huron to Black river. It is unnecessary to set out the contract in full. Those provisions necessary to be understood for the purpose of this decision may be summarized as follows:

Appellant, known in the contract as the party of the second part, agreed to start the actual work of constructing a canal within 30 days of the time of executing the contract, to make fair monthly progress in carrying on the undertaking, and to fully complete and finish the canal, bridges and other work embodied in the terms of the contract within one year from the date thereof.

For failure, neglect or refusal to go on with the work or to carry "out the reasonable instructions of the city engineer, it was provided that the city might serve written notice upon the party of the second part “to carry out such instructions and if within ten (10) days thereafter, said party of the second part shall fail to satisfy” the city “of its ability and intention to carry out such instructions and to complete the work within the time agreed upon, then in that case the party of the first part shall have the right to declare this contract forfeited,” the money due or becoming due to the party of the second part on the con-. tract to be thereby forfeited to the city as liquidated damages, with the privilege to the city to let the work to other parties without incurring any liability. This feature of the contract provided also that any expense above the unpaid balance of the contract price, incurred by the city under these circumstances in completing the work, should constitute a breach of the bond of the second party and that the sec*ond party and its sureties should become liable therefor.

Damages in the sum of not more than $15 per day were stipulated for each and every month that the work was delayed after the expiration [348]*348of the time of performance provided by the contract. The canal was to be completed according to plan A on file in the city engineer’s office and the appellant, the second party, was to excavate and remove the material, of “whatever name or nature (except solid rock), required for the construction of such canal” included within the dimensions set forth in the plan.

If solid rock were found (and solid rock was defined to be “rock in its original formation and not broken rock or boulders, detached from such formation”) the second party was to be compensated therefor at the rate of $1.15 per cubic yard as an extra; but this provision was coupled with the condition:

“That said second party is to excavate and remove the material, of whatever nature or name, for the construction of the said canal without additional compensation, except such solid rock as may be found in layers, if any there be.”

An additional provision was to the effect:

“That all excavation will be classed as earth excavation except solid rock, should there be any, and nothing will be allowed for cave-ins, landslides or upheavals beyond the line of excavation occurring before the completion and acceptance of the canal.”

It was provided that on or before the 10th day of the month 90 per cent, of the estimate of the previous month’s work should be paid by the city to the party of the second part, the remaining 10 per cent, to be withheld until after the completion of the work.

The specifications were made part of the contract and appear in the record. No part of their terms is material for this decision, save that the city reserved therein the right to make alterations in the plans and details of the work when to do so seemed advantageous, and it was—

“to be distinctly understood that any increase or reduction of quantities, resulting from such, alterations, is not to be assumed as a basis of a claim against the city for damages for loss of prospective profits.”

The work progressed very slowly, and at the expiration of the limit for completion set by the contract, namely, February 10, 1903, about 22 per cent, only of the total amount of work to be done had been accomplished. At the company’s request, at that time, for a year’s extension of time, the city granted less than 10 months, or until December 1, 1903. By the first of August of the second year about 12 per cent, additional of the total amount of work had been done, wherefore, at that time, about a third only of the entire contract had been •completed. The August estimate was not promptly made. There is some dispute in the record whether one was made at all, but no payment was ever made for work done in July, 1903, which was approximately of the value of $4,000 at the contract rate. On the 18th of August, following an investigation of the work in behalf of the city, the canal commission passed a resolution reciting that the Cuyahoga Contracting Company had failed and neglected to progress with the work as provided in its contract and expressing the opinion of the commission that the contractor had not the ability or intention to complete the work within the time agreed upon as extended. The commission therefore [349]*349recommended to the city that notice as provided in the contract be given to the company and that the latter satisfy the city “of its ability and intention to carry on said work and complete the same within the time agreed upon.” A notice authorized by the council of the city and pursuant to this resolution was served upon the president of th,e Cuyahoga Contracting Company August 19, 1903, whereupon the company, August 21, 1903, served notice upon the city of its intention to abandon the contract. No effort was made by the company to meet the city’s request for information as to the company’s intentions or as to the prospect, in its opinion, 'that it would be able to finish the work by December 1, 1903. The notice of abandonment by the company was the only reply to the city’s notice of August 19.

In the work preliminary to the advertising for bids for this improvement the city engineer had made a profile of the proposed excavation, the data for which, as to character of soil and material, to be encountered in the excavation, having been obtained by borings. The contract did not make this profile part of its terms nor were either the profile or its representations embodied in the specifications. It appears, however, that one Rosenstock, the representative of the Cuyahoga Contracting Company, upon whose reports to his employer the contract was entered into by the latter, had himself, prior, to the letting of the contract, seen the profile and had examined the borings. He also had familiarized himself with the surface indications and topographical peculiarities along the proposed route. In the actual work of excavation, so far as done, it was early discovered by the company that the profile indications were misleading to .the point that materials difficult to be excavated existed in substantially greater amounts than appeared upon the profile. After the contract had been signed and the lines staked out, the city, near the northeast end of the excavation, made a change in the route which placed the contractor to some substantial inconvenience in excavating, through its inability to deposit excavated material on one side of the line because of the proximity of a cemetery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanitary Dist. of Chicago v. Ricker
91 F. 833 (Seventh Circuit, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
233 F. 346, 147 C.C.A. 282, 1916 U.S. App. LEXIS 2465, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cuyahoga-contracting-co-v-city-of-port-huron-ca6-1916.