Harlev v. Sanitary District of Chicago

107 Ill. App. 546, 1903 Ill. App. LEXIS 490
CourtAppellate Court of Illinois
DecidedJanuary 26, 1903
StatusPublished
Cited by6 cases

This text of 107 Ill. App. 546 (Harlev v. Sanitary District of Chicago) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harlev v. Sanitary District of Chicago, 107 Ill. App. 546, 1903 Ill. App. LEXIS 490 (Ill. Ct. App. 1903).

Opinion

Mb. Justice Windes

delivered the opinion of the court.

The principal and controlling question in this case is as to whether the appellee, by its proceedings looking to a forfeiture of the contract between it and Harlev, set out in the statement, was^ justified. If the contract was rightfully forfeited, then there is no right of recovery shown, and the learned trial judge committed no error in directing a verdict for appellee. FTo contention is made on behalf of appellee but that a prima facie case for appellant is shown by the evidence, except upon the theory that appellant had not complied with his contract as to the rate of progress of his work thereunder. No claim is made in the argument for appellee, that there was any right of forfeiture by reason of the failure of Harlev to comply with the provisions in the contract, viz: Division “D” No. 20 of the specifications with regal’d to the character of the work and in keeping the same under bis control—not subletting all or any part of it, and Division “ M,” which provides, among other things, that Harlev should not lose control of the work from any cause; nor is any claim made that he failed to comply with any other provision of the contract, except that relating to his rate of progress.

We have set out in the statement many of the provisions of the contract which have no direct bearing upon the decision of the case, in view of the conclusions reached by us, so that the magnitude of the undertaking, the many and formidable difficulties to be met in its performance, and the necessity for careful and deliberate procedure on the part of the representatives of appellee in its efforts to forfeit the contract, may be made to clearly appear and be appreciated.

It is well settled and needs no citation of authorities to sustain the proposition, that forfeitures are not favored by the law, and that when the right thereto is asserted, such right must be clearly and unquestionably established before the courts will enforce them.

It appears from the evidence that Harlev, in the performance of his contract, had cleared about 170 acres of land included in the canal right of way of section one, which was covered with a dense growth of timber—very .many large trees and underbrush, had removed most of the stumps and grubbed a large portion of it, all of which the evidence tends to show was necessary to be done in order to comply with the contract. Section 8 of the specifications, quoted in the statement, makes it the duty of the contractor to “remove all trees, stumps, buildings, fences, or other incumbrances within 150 feet of the center line of the channel,'or that may be in the way of any collateral or subsidiary work herein specified.” He had consumed in doing this work, some ten months and upward of time, at least four months of it being when a large part of the ground was flooded by water or the ground was frozen, making it impossible to do parts of this work, and impracticable to do any of it when the ground was so frozen or flooded. It also appears that in doing this clearing and grubbing, he had from 75 to 130 men employed, and that they worked in shifts, night and day. Also, there is much evidence that the number of men employed was all that could practically, reasonably and profitably have been employed in the doing of this work. Many men of experience in such matters testified, in effect, that employing all the men who could economically and profitably have worked on the land in clearing it and disposing of the timber, it would require from seven to ten months to do the workj some of the witnesses putting the time as high as twelve months.

Before the attempted forfeiture Harlev had excavated from the main channel 109,540 cubic yards of glacial drift, and before the contract of August 30, 1893, by which he was relieved of the construction of the river diversion, he had excavated on that part of his contract some 6,000 cubic vards of glacial drift. After making the contract of August 30, 1893, at the request of appellee, Harlev used the greater part of his working force in the construction of the river diversion, which he completed November 16, 1893. The total amount of excavation of glacial drift taken from the river diversion, and which, it appears, was necessary to have been done before any work of consequence was done upon the main channel, was 164,493 cubic yards. As early as November, 1893, appellant had and was using in the work on the main channel two steam shovels, a sixty horsepower engine, dumb carts, cables and inclines to pull the dirt from the shovels, three steam centrifugal pumps and other engines,about sixty wheel scrapers, some slip scrapers and wheelbarrows, shovels and picks to run 3,000 men. He also had buildings to lodge the men, barns for the horses, an office building, tool house, blacksmith shop, three sets of blacksmith’s tools, a boarding house and kitchen. Two steam shovels would excavate from 1,500 to 2,000 cubic yards per day, and while the evidence shows they did not excavate that amount following the month of November, 1893, and up to the time of the attempted forfeiture, appellant was building a levee to protect the work which, it seems, was necessary and he was required to do under his contract.

There is evidence tending to show that appellant did not, after he begun active work in excavating on the main channel, which was in June, 1893, proceed as rapidly and diligently as the plant and means to prosecute the work that he had provided for that purpose, would seem to have enabled him to do, and certainly he did not succeed in making the progress that was deemed necessary, under the contract, by the chief engineer of appellee and his assistants and by appellee’s board of trustees. There is, however, ample evidence indicating that appellant in good faith was proceeding, and did proceed, up to the time of the attempted forfeiture, to carry out his contract according to its terms. In a report as to progress on many sections of the canal, including section 1, made by the superintendent of construction to the chief engineer July 26, 1893, it is stated that the contractors on section 1 “are making more determined efforts to open up this work, and evince a disposition to do all in their power to comply with their contract.” The evidence as to the actual amount of work done by Harlev, thereafter and up to the time of the attempted forfeiture, both in the river diversion and the main channel evinces a continuance of this same disposition. If this is true, certainly, in all fairness and justice, he should not by a forfeiture of the contract be deprived of his right to complete it and of any supposed benefits or profits that he might have gained therefrom, unless some rule of law, under the clear provisions of the contract, construed unfavorably to a forfeiture, demands such a result.

There being no claim by appellee that there was any basis for its attempted forfeiture of the contract, except on account of the alleged failure of Harlev to make the rate of progress required, we are of opinion, from a consideration of the whole evidence, that claim is untenable. Even if it be conceded, as is contended by appellee (which we do not) that the chief engineer was empowered, under the contract, to decide whether appellant made the requisite rate of progress, that the chief engineer was justified by the facts in so deciding, and that the evidence in this record shows that appellant failed to make the rate of progress required by the contract, still appellee had no right to forfeit the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Saballus v. Timke
460 N.E.2d 755 (Appellate Court of Illinois, 1983)
Citerella v. United Illuminating Co.
266 A.2d 382 (Supreme Court of Connecticut, 1969)
Norris v. Elmdale Elevator Co.
185 N.W. 696 (Michigan Supreme Court, 1921)
Griffiths v. Sanitary District
174 Ill. App. 100 (Appellate Court of Illinois, 1912)
Winslow Bros. v. Robinson
173 Ill. App. 84 (Appellate Court of Illinois, 1912)
Sanitary District of Chicago v. McMahon & Montgomery Co.
110 Ill. App. 510 (Appellate Court of Illinois, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
107 Ill. App. 546, 1903 Ill. App. LEXIS 490, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harlev-v-sanitary-district-of-chicago-illappct-1903.