Gray v. La Societe Francaise De Bienfaisance Mutuelle

63 P. 848, 131 Cal. 566, 1901 Cal. LEXIS 1171
CourtCalifornia Supreme Court
DecidedFebruary 12, 1901
DocketS.F. No. 1755.
StatusPublished
Cited by6 cases

This text of 63 P. 848 (Gray v. La Societe Francaise De Bienfaisance Mutuelle) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gray v. La Societe Francaise De Bienfaisance Mutuelle, 63 P. 848, 131 Cal. 566, 1901 Cal. LEXIS 1171 (Cal. 1901).

Opinion

COOPER, C.

This action was brought to foreclose a contractor’s lien for work and labor done and materials furnished in supplying all of the concrete and artificial stone work for the building of the defendant known as the “French Hospital” in the city and county of San Francisco. The case was tried before the court, and findings filed upon which judgment was entered for defendants. Plaintiff made a motion for a new trial which was denied and this appeal is from the order denying the motion.

It is claimed that the evidence is insufficient to sustain the findings in two- important particulars which we will discuss in the order as set forth in the briefs. On the seventh day of October, 1893, the plaintiff’s assignor, a corporation, entered into a contract in writing with defendant corporation, by the terms of which the said assignor of plaintiff agreed to furnish labor, tools, materials, and appliances and perform and complete all the excavating, concrete, artificial stone work, cementing, and other work as shown and described in the plans and specifications made by the architects and signed by the parties at the time of making the said contract, all for the sum of twenty-five thousand eight hundred and eighty-five dollars. The work was performed and the contract price paid as agreed upon. The contention here is not as to the amount to be paid under the contract, and which was paid thereunder, but is as to an item of sixteen hundred and eighty-four dollars and fifty cents, which is particularly stated in finding 4 as follows, to wit:

“That immediately after the execution of said written contract the said Gray Brothers’ Artificial Stone Paving Company entered upon the performance thereof, under said articles of agreement and specifications, and while they were so engaged in the early part of December, 1893, William Mooser, one of the said architects, requested said corporation orally to carry up the concrete walls eighteen inches higher than called for by the original plans and specifications, and that said corporation subsequently complied with said request, and did carry up said concrete walls eighteen inches higher than called for *568 ■by said plans and specifications, and in so doing put in six thousand seven hundred and thirty-eight cubic feet of concrete wall, of the value of .sixteen hundred and eighty-four dollars and fifty cents.”

The court found in effect that this item was for extra work and was not agreed to in writing, nor requested by defendant nor its building committee, and that for this reason plaintiff could not recover therefor. The main contention of appellant is that the item was for services performed under the original contract and was not for extras, and that the work was done at the request of the architect of defendant, and that for this reason the defendant is responsible. The contention is mainly based upon the following clause in the specifications which were a part of the contract, to wit: “If, in the opinion of architects, any particular place should require more cement or more thickness of floor or concrete than is called for, the contractor will have to do the same, and the cost of said work to be determined by the architects.”

We think, without regard to the question as to whether or not the contested item is for extras or was incurred under the authority of the contract and said quoted clause in the specifications, the defendant is not liable. Immediately following the clause quoted from the specifications and as a part of the same sentence is the following: “But no extra work shall be allowed except where a written order from architects is procured, approved by the building committee.” The court found “that the request of the architect therefor was never approved by the building committee, nor was the cost or value thereof ever fixed or agreed upon or prearranged.” This finding is supported by the evidence. It follows that even if the original contract and the specification quoted authorized the carrying up of the concrete walls eighteen inches higher, it could only be a charge against defendant when done under a written order from the architect, approved by the building committee. The defendant cannot be bound outside the terms of its contract. The plaintiff agreed that no extra work should be allowed except upon a written order from the architect, approved by the building committee. It did not procure such order, and therefore must be held to the terms of its contract. The above is *569 the correct interpretation of the specification and was the true intent of the parties as shown by the other parts of the contract. It is provided in the eighth clause that “should the owner or the architect at any time during the progress of the work request any alterations to, or omissions from this contract, or the plans or specifications, either of them shall be at liberty' to do so only by written agreement.” It is provided in the ninth clause: “The rule of practice to be observed in the fulfillment of the last foregoing paragraph (8) shall be that upon the demand of either the contractor, owner, or architect, the character and valuation of any or all changes, omissions, or extra work, shall be agreed upon and fixed in writing, signed by the owner or architect and the contractor prior to execution.”

And in the specifications after the clause hereinbefore quoted in specification 5 it is provided: “And in all cases where any alterations or additions (if any) shall involve any increase of expenditure not included or provided for in the drawings, specifications, or contract, then authority in writing shall be necessary and cost prearranged before such work shall be undertaken; neither will the same be paid for, nor any allowance be made in any respect thereof, unless the work in question shall have been executed under the authority of such written order, and said order be produced at the first settlement of extra account subsequent to the date- thereof. Said written order to be given by architects and approved by building committee.”

It thus appears that the parties over and over again bound themselves that no extras or extra work should be charged for unless agreed to in writing as provided in the contract and specifications. There is no evidence of any agreement in writing as to the item in contest. There is no evidence that it was for work done by virtue of any change of plans approved by the building committee. Hot only this, but the court finds “that neither the defendant nor any of its officers, nor its board of trustees or its building committee, or any member thereof, ever knew of said oral request of the architect, or that said extra work was being done, or had been done until a considerable time subsequent to the doing of said extra work.”

This finding is supported by the evidence, and is entirely *570 inconsistent with the contention of appellant’s counsel that the defendant waived the provisions of the.contract requiring all increases in expenditure to be .in writing.

In J. M. Griffith Co. v. Los Angeles (Cal., Sept. 3, 1898), 54 Pac. Rep. 383, the plaintiff had contracted with the defendant for a fixed price to construct a certain sewer leading from the city of Los Angeles to the Pacific Ocean.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A. Teichert & Son, Inc. v. State of Cal.
238 Cal. App. 2d 736 (California Court of Appeal, 1965)
Bavin & Burch Co. v. Bard
255 P. 200 (California Court of Appeal, 1927)
Contra Costa Construction Co. v. City of Daly
192 P. 178 (California Court of Appeal, 1920)
Carter v. A. I. Root, Inc.
121 N.W. 952 (Nebraska Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
63 P. 848, 131 Cal. 566, 1901 Cal. LEXIS 1171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gray-v-la-societe-francaise-de-bienfaisance-mutuelle-cal-1901.