J. M. Griffith Co. v. City of Los Angeles

54 P. 383, 6 Cal. Unrep. 119, 1898 Cal. LEXIS 1050
CourtCalifornia Supreme Court
DecidedSeptember 3, 1898
DocketL. A. No. 390
StatusPublished
Cited by5 cases

This text of 54 P. 383 (J. M. Griffith Co. v. City of Los Angeles) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. M. Griffith Co. v. City of Los Angeles, 54 P. 383, 6 Cal. Unrep. 119, 1898 Cal. LEXIS 1050 (Cal. 1898).

Opinion

BRITT, C.

On April 24, 1893, the city of Los Angeles, defendant here, and certain persons, who may be called the “contractors,” executed several instruments in writing, which for present purposes we may regard as a single contract, whereby the contractors agreed to construct (at their own cost for labor and material) sections 3 and 6a of an outfall sewer leading from said city to the Pacific Ocean, for which construction the city agreed to pay them the aggregate sum of $77,450. Said contractors constructed said sections of sewer, and received most of the compensation provided in the contract. They assigned to the plaintiff, a corporation, their claims against the city for some unpaid balances, and for the value of certain alleged extra materials used by them in the work aforesaid. This is an action on the claims so assigned. Plaintiff had judgment below for some hundreds of dollars, but failed as to the bulk of its demand.

1. By the terms of the said contract the conduit in said sections of sewer was to be a pipe constructed of redwood staves bound with steel bands, and it was provided that the city might retain ten per cent of the price specified in said contract for the space of six months after the completion of the work and its acceptance by the city, “during which time the contractors are -obliged to keep the pipe in repair,” and that in case of their default in that particular the city should make the repairs, using so much of the sum retained as might be necessary for that purpose. On February 23, 1894,' the city and said contractors made a further agreement in writing, reciting that said sections 3 and 6a of the sewer were completed and ready for acceptance by the city, and providing that in lieu of retaining ten per cent of the contract price for application to repairs after acceptance, as allowed in the prior contract of April 24, 1893, the city should withhold the sum of $5,000, and that if at any time during such period of six months after acceptance of said sections any repairs [121]*121should, in the opinion of the city council, become necessary on said sections, or either of them, the council might at once make the same, and deduct the cost thereof from said sum of $5,000; also, “that at the expiration of six months the city shall pay the said contractors the said sum of $5,000, or so much thereof as has not been paid for the purposes above mentioned. ’ ’ The city retained said sum, and has never paid the same to said contractors, or to the plaintiff, their assignee. The court found that the city expended for repairs on said sections of the sewer to August 23, 1894, inclusive, the sum of $1,894.35, and prior to October 7, 1894, its expenditure in that behalf exceeded $5,000; also, that work on such repairs was begun by the city on July 10, 1894, and continued until February 20, 1895. Plaintiff contends that it should recover the sum of $3,105.65, which is the excess of the amount retained by the city above the payments made for repairs up to August 23, 1894; plaintiff claiming this date to mark the end of the period of six months, during which the city could rightfully expend for repairs any part of said sum of $5,000 withheld as aforesaid. This contention is founded mainly on the clause of the instrument of February 23, 1894, that “at the expiration of six months the city shall pay to the contractors the said sum of $5,000, or so much thereof as has not been used for the purposes above mentioned.” Particular clauses of a contract are subordinate to its general intent (Civ. Code, sec. 1650), and the contracts before us afford a clear case for the application of the principle. The plain object of said instrument of February 23, 1894, understood in connection with the cognate provisions (which it modified) in the contract of April, 1893, was to indemnify the city, to the amount of $5,000, for the cost of repairing defects which might be disclosed in sections 3 and 6a of the sewer during six months next following acceptance thereof by the city, and which the city should at once proceed to make good. The city began the work of repairs well within the period of six months. The continued prosecution thereof involved a cost exceeding the sum retained by it under the several contracts. The good faith of its conduct is in nowise impugned. We think, therefore, that the general intent of the indemnifying provisions of the contracts ought not to be -overridden by the particular clause that at the expiration of six months the city should pay to the contractors so much of the sum withheld ‘ ‘ as [122]*122has not been used for the purposes above mentioned.” On the theory urged by plaintiff, if the whole line of pipe had collapsed on the last day of the six months during Avhieh the city was allowed to repair at the contractors’ expense, the city would still have been obliged to pay over the indemnifying fund, unless it could on that day actually expend it in replacing the ruin. We conclude that the judgment denying plaintiff’s claim to any part of said sum of $5,000 was right.

2. Said contract of April 24, 1893, contained the following: “The amount herein agreed to be paid for said work is in full for said sections of sewer complete. No extras are to be allowed, except in case of a change in route or plans, and in that case the payment of the same shall be as stated in the specifications hereto attached.” In the specifications referred to it was provided that: “The city engineer reserves the right to make any desired change in the plans, but the changes so made, Avith the price to be added to or deducted from the contract price, shall be agreed upon between the parties hereto and indorsed upon the contract; and, if they shall be unable to agree upon a price for such alterations, then the city engineer shall fix a fair and reasonable valuation upon such work, and this valuation shall be indorsed upon the contract, and when so indorsed shall he binding upon the parties thereto. If not so indorsed, then the original price shall be neither increased nor diminished.” On the request of the city engineer, who had direction of the work, the contractors used in the construction of said sections of sewer a large number of steel bands for the pipe, in addition to those required by the specifications. It may be admitted, without deciding, that such action of the engineer was a change of plans, so far as his authority in that* behalf extended. It does not appear that the city council had any information of the use or intention to use the additional hands until after said sections of sewer were completed, when the contractors presented an account against the city for the same as extras, at the rate of eighty-five cents each, amounting to $4,012. The city engineer certified that seventy cents each was a just price for them. No indorsement respecting such bands or the price was made on the contract. The court found that they were worth $3,304, the value certified by the engineer. Plaintiff claims that it [123]*123should have had judgment therefor. Occasion for said additional material seems to have arisen through no fault of the contractors. The contract, however, was plain that no extras should be allowed except on change of route or plans, and, in case the engineer should change the plans, still no extra payment was provided for, unless the changes so made, with the price to be added to or deducted from the contract price, “shall be agreed upon between the parties hereto,” viz., the city and the contractors. If they could not agree on the price, then the engineer should fix the same. These provisions evidently mean that no changes of plan should become a part of the contract, to be paid for by the city, unless it should agree thereto.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
54 P. 383, 6 Cal. Unrep. 119, 1898 Cal. LEXIS 1050, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-m-griffith-co-v-city-of-los-angeles-cal-1898.