Pickard & Butters etc. v. Buttonwillow Recreation etc. CA5

CourtCalifornia Court of Appeal
DecidedDecember 28, 2020
DocketF078801
StatusUnpublished

This text of Pickard & Butters etc. v. Buttonwillow Recreation etc. CA5 (Pickard & Butters etc. v. Buttonwillow Recreation etc. CA5) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pickard & Butters etc. v. Buttonwillow Recreation etc. CA5, (Cal. Ct. App. 2020).

Opinion

Filed 12/28/20 Pickard & Butters etc. v. Buttonwillow Recreation etc. CA5

NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIFTH APPELLATE DISTRICT

PICKARD & BUTTERS CONSTRUCTION, INC., F078801

Plaintiff and Appellant, (Super. Ct. No. BCV-15-100179)

v. OPINION BUTTONWILLOW RECREATION & PARK DISTRICT,

Defendant and Respondent.

APPEAL from a judgment of the Superior Court of Kern County. David R. Lampe, Judge. Law Offices of F. Glenn Nichols and F. Glenn Nichols for Plaintiff and Appellant. Clifford & Brown, John R. Szewczyk and Daniel T. Clifford for Defendant and Respondent. -ooOoo- INTRODUCTION This appeal involves a dispute between a general contractor and a public agency over a public works contract for the improvement of a park in the unincorporated community of Buttonwillow. Plaintiff Pickard & Butters Construction, Inc. (PBC) filed suit against Buttonwillow Recreation & Park District (District) for, among other claims, breach of contract and for prompt payment penalties under Public Contract Code section 7107. PBC sought the unpaid balance due on the contract and additional sums for extra work outside the scope of the contract performed at District’s request, and prompt payment penalties. Prior to trial, the court granted District’s motion in limine and excluded any evidence PBC performed extra work without a written change order based on theories of oral modification or waiver of the contract’s written change order requirement, or evidence that PBC was entitled to payment for such extra work based on estoppel. In making this ruling, the court relied on two appellate cases: Katsura v. City of San Buenaventura (2007) 155 Cal.App.4th 104 (Katsura) and P&D Consultants, Inc. v. City of Carlsbad (2010) 190 Cal.App.4th 1332 (P&D Consultants), review denied April 13, 2011. We conclude the written change order requirement in the parties’ contract did not, as a matter of law, preclude PBC’s claims for extra work pursuant to theories of oral modification, waiver, or by the doctrine of estoppel. Thus, PBC was entitled to present evidence supporting application of these theories and we reverse the judgment and remand for a new trial. We express no view whether PBC is entitled to any compensation for alleged extra work under any of these theories. FACTUAL AND PROCEDURAL BACKGROUND I. The Park Improvement Project After a competitive bidding process required by statute, District awarded PBC a contract to update a 12-acre park in Buttonwillow, an unincorporated area in Kern

2. County. The parties executed an agreement on October 21, 2013, for a total of $913,921.40. The plans and specifications for the project were designed for District by Meyer Civil Engineering, Inc. (MCE), whose principal Richard Meyer was the engineer of record on the project. Meyer retained the services of Brett Dawson, a licensed Civil Engineer, to supervise the construction work. A. Relevant Contract Provisions Under the terms of the contract, PBC was to complete the work within 180 days followed by a 60-day maintenance period. The original agreed upon completion date was April 28, 2014. Under section C-8, the contract provided that the engineer was to “give all orders and directions contemplated under the Contract.” The engineer had authority to reject all work and materials which did not conform to the proper execution, and any discrepancies or misunderstandings as to the contract specifications were to be referred to the engineer who was to decide the matter in accordance with the true intent and meaning of the contract. The contract also allowed the engineer to make necessary changes and request extra work by written order. Section C-10 was devoted to the topic of “Extra Work.” If the engineer ordered work or materials outside the scope of the plans and specifications, the contractor was to perform such work. The contract stated that “[s]uch labor, materials and/or equipment will be classed as extra work and shall be ordered in writing before such work is started. No extra work will be paid for unless ordered in writing.” If the price for extra work could not be ascertained before the order for extra work issued, the contractor could proceed with the extra work pursuant to the contract’s schedule for compensable extra work costs. In the event of a dispute between the engineer and the contractor over the scope of the contract, section C-29 stated a condition precedent to a contractor’s claim of extra costs: “(b) Claims for Extra Cost – If the Contractor claims that any instructions by

3. drawings, or otherwise involve extra cost under this contract, he shall give the Engineer written notice thereof within fifteen (15) calendar days after the receipt of such instructions. Each such claim shall be in reasonable detail and shall state fully the basis of the claim and the amount of alleged extra cost incurred. Claims not so made within said period shall be deemed waived.” Within the first ten days of each calendar month during the project, the engineer was to provide to District a written estimate of all work done under the contract to date, together with any amounts due the contractor for extra work or approved claims for extra costs. District would then pay the contractor 95 percent of the amount of each progress estimate, payable by the 13th day of the succeeding month. The remaining five percent was to be retained until final completion and acceptance of the work under the contract. B. Change Order Process Followed During the contract work, there were many items of extra work District approved and PBC completed. There were 17 change order requests (CORs) made by PBC, which were forwarded to Dawson. At trial, Dawson could recall only nine of the 17 CORs. For CORs 2 through 10, Dawson took the requests to District’s monthly board meeting, made a recommendation to approve or deny, and District made a decision as to the extra work. Dawson then apparently orally directed PBC to undertake the work. After District board meetings where extra work was approved, the next monthly pay estimate issued by Dawson would reflect line items labeled as contract change orders. The monthly pay estimate, prepared by Dawson and signed by both Dawson and PBC’s principal, Mark Butters, would indicate whether those line items of approved changes, along with other work within the scope of the contract, had been completed. If PBC completed change order items, they were marked on the estimate as items to pay; if the items were not yet completed, the estimate would indicate they had been approved but nothing was owing. The pay estimate was then sent to District for approval and payment. District’s monthly board meeting minutes show when it approved the extra work for PBC’s CORs 2 through

4. 10, but no written authorization by Dawson was furnished to PBC between the time District’s board voted to approve and when the approval appeared on the next month’s pay estimate.1 C. Disputes About Project Specifications, Extra Work, and Completion The contract was executed on October 21, 2013, and work commenced soon afterward. Disputes about the specifications arose quickly, one of which was whether native soil or imported soil was required for excavated tree wells. Another dispute centered on extra turf grading work Dawson asked PBC to perform along Highway 58 and Meadows Street. District’s board approved $5,000 for this work, it was listed as an approved change order on pay estimate 5, but then was removed from pay estimate 6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Retired Employees Ass'n of Orange County, Inc. v. County of Orange
266 P.3d 287 (California Supreme Court, 2011)
M. F. Kemper Construction Co. v. City of Los Angeles
235 P.2d 7 (California Supreme Court, 1951)
Frank T. Hickey, Inc. v. Los Angeles Jewish Community Council
276 P.2d 52 (California Court of Appeal, 1954)
C. F. Bolster Co. v. J. C. Boespflug Construction Co.
334 P.2d 247 (California Court of Appeal, 1959)
Bares v. City of Portola
269 P.2d 239 (California Court of Appeal, 1954)
Nathan H. Schur, Inc. v. City of Santa Monica
300 P.2d 831 (California Supreme Court, 1956)
Miller v. McKinnon
124 P.2d 34 (California Supreme Court, 1942)
Weeshoff Construction Co. v. Los Angeles County Flood Control District
88 Cal. App. 3d 579 (California Court of Appeal, 1979)
Healy v. Brewster
251 Cal. App. 2d 541 (California Court of Appeal, 1967)
G. L. Mezzetta, Inc. v. City of American Canyon
93 Cal. Rptr. 2d 292 (California Court of Appeal, 2000)
Condon-Johnson & Associates, Inc. v. Sacramento Municipal Utility District
57 Cal. Rptr. 3d 849 (California Court of Appeal, 2007)
KATSURA v. City of San Buenaventura
65 Cal. Rptr. 3d 762 (California Court of Appeal, 2007)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
City of Long Beach v. Mansell
476 P.2d 423 (California Supreme Court, 1970)
Domar Electric, Inc. v. City of Los Angeles
885 P.2d 934 (California Supreme Court, 1994)
Huskinson & Brown, Limited Liability Partnership v. Wolf
84 P.3d 379 (California Supreme Court, 2004)
Children's Hospital Central California v. Blue Cross of California
226 Cal. App. 4th 1260 (California Court of Appeal, 2014)
McIntyre v. Colonies-Pacific, LLC
228 Cal. App. 4th 664 (California Court of Appeal, 2014)
Green Valley Landowners Ass'n v. City of Vallejo
241 Cal. App. 4th 425 (California Court of Appeal, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Pickard & Butters etc. v. Buttonwillow Recreation etc. CA5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pickard-butters-etc-v-buttonwillow-recreation-etc-ca5-calctapp-2020.