Condon-Johnson & Associates, Inc. v. Sacramento Municipal Utility District

57 Cal. Rptr. 3d 849, 149 Cal. App. 4th 1384
CourtCalifornia Court of Appeal
DecidedMay 8, 2007
DocketC050715
StatusPublished
Cited by27 cases

This text of 57 Cal. Rptr. 3d 849 (Condon-Johnson & Associates, Inc. v. Sacramento Municipal Utility District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Condon-Johnson & Associates, Inc. v. Sacramento Municipal Utility District, 57 Cal. Rptr. 3d 849, 149 Cal. App. 4th 1384 (Cal. Ct. App. 2007).

Opinion

Opinion

BLEASE, Acting P. J.

Public Contract Code section 7104 1 requires that a local public entity that has contracted for public work involving an excavation deeper than four feet issue a change order altering the contractor’s cost of performing the work when the subsurface conditions at the jobsite materially differ from those “indicated” in the contract. (§ 7104, subds. (a)(2) & (b).)

Plaintiff Condon-Johnson & Associates, Inc.. (Condon-Johnson), was the low bidder on a contract with defendant Sacramento Municipal Utility District (SMUD) to construct 13 concrete foundations for piers to relieve the pressure caused by the moving hillside behind a powerhouse owned by the utility. The contract required Condon-Johnson to bore holes through the hillside to the site of the pier foundations. The contract contains a changed conditions clause incorporating the requirements of section 7104.

The contract sets forth soil boring information for the “p[iir]pose of determining what type of rock may be encountered . . . .” The information includes the boring logs from two test borings by SMUD adjacent to the jobsite and the results of compression testing of two rock samples selected by SMUD from one of the borings. The contract represents the samples as “the most competent core samples” recovered from the borings and asserts the results of the compression tests are provided “to give additional information as to what may be expected in the pier drilling.”

The contract also contained general disclaimers that, inter alia, provided “[i]t is the sole responsibility of the Contractor to evaluate the jobsite and make his own technical assessment of subsurface soil conditions for determining the proposed drilling process, equipment and make his own financial impact assessment prior to bidding.”

*1387 When Condon-Johnson encountered a type of rock during drilling materially different (harder) than the test samples, which increased the cost of drilling, it sought a change order, SMUD refused and Condon-Johnson brought this action. Before trial, the court granted in limine motions excluding the disclaimers from jury consideration, reasoning they were in conflict with section 7104. The jury awarded Condon-Johnson the sum of $1,265,166 on the basis of the remaining contract provisions.

The sole issue on appeal is whether the trial court properly excluded the disclaimers from jury consideration. Resolution of the issue turns on the meaning of the term “indicated” in section 7104 and incorporated in the changed conditions clause of the contract.

We will conclude that “indicated” refers to contract information provided prospective bidders from which an inference reasonably might be drawn as to the actual subsurface conditions at the work site. In this case the contract set forth the soil boring information for a purpose that invited Condon-Johnson to infer that the type of rock in the test samples would be the type of rock that may be “expected” or “encountered” in performing the work. Since the disclaimers wholly denied responsibility for the subsurface conditions indicated, in violation of section 7104, they were properly excluded from jury consideration.

We will affirm the judgment.

FACTUAL AND PROCEDURAL BACKGROUND

In the 1960’s, SMUD constructed the Camino powerhouse on the South Fork of the American River as a source of hydroelectric power. After its completion, SMUD noticed the hillside on which the powerhouse was built was moving and exerting pressure on the back wall of the powerhouse. SMUD designed a system to relieve the pressure caused by the moving hillside, which included the construction of 13 concrete pier foundations behind the powerhouse.

Originally, SMUD solicited contractors to bid on the project through a process known as an “invitation to bid.” SMUD received only one bid, which was deemed nonresponsive. The lack of bids was due to SMUD’s requirement that the winning contractor use an oscillator/rotator drill for the project, which few contractors had.

In April 2002, SMUD again solicited bids for the project, this time through a “request for proposal.” The requirement of an oscillator was removed, and bidding contractors were required to propose the means and method for completing the project.

*1388 The initial version of the contract contained a clause that provided: “The District has performed soil boring along the penstock, adjacent to the jobsite. The subsurface description and boring logs are provided in Appendix D.[ 2 ] The core samples taken from these borings . . . are actually closer to the powerhouse than the proposed pier locations. Based on the historical photo, included in the Technical Conditions, the District expects much less backfill at pier locations as compared to the sample locations. It is the intension of the District to provide the soil boring information for the pfurjpose of determining what type rock may be encountered and not for determining the profile of backfill to rock.”

During a meeting with potential bidding contractors, a contractor asked to take pieces of rock from one of SMUD’s core boxes and have compression tests run on them. Rather than have the contractor take the samples, SMUD allowed the contractor to select samples from its core boxes on which SMUD would run the tests, and the results would be published in an addendum to the request for proposal to be distributed to all potential bidding contractors. Later that month, SMUD published addendum No. 1 and incorporated it into the contract. The addendum provided: “The District has completed compression testing on two samples from the M-2 boring, at 20.0 and 25.7 feet. These tests were completed to give additional information as to what may be expected in the pier drilling. These samples were selected, by the District, on the basis of visually appearing to be the most competent core samples in the M-l and M-2 recovery.”

Ultimately, SMUD received bids from four or five contractors, and in July 2002 awarded the contract to Condon-Johnson.

The contract required Condon-Johnson to install 13 reinforced concrete pier foundations behind the powerhouse two meters in diameter and between 62 and 82 feet in depth. As is relevant here, the contract included the following clauses: (1) “GC-35 Changed Conditions At The Jobsite,” which entitled Condon-Johnson to equitable adjustments if “[sjubsurface . . . conditions at the jobsite differed] materially from those indicated in th[e] Contract” (changed conditions clause); 2 3 (2) “SC-2 Location,” which, in *1389 addition to specifying' the location of the powerhouse, informed Condon-Johnson that SMUD would not make extra payment if the contractor failed to determine existing conditions and that SMUD made no guarantee concerning information not included in the plans and specifications and information provided by others, including SMUD personnel, about the conditions which may impact the work and/or costs; 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spring Oaks Capital SPV, LLC v. Fowler
California Court of Appeal, 2026
Cavalry SPV I, LLC v. Poalston
California Court of Appeal, 2025
Nelson v. Golden Queen Mining Company CA5
California Court of Appeal, 2025
Yaffee v. Skeen
California Court of Appeal, 2024
Malinowski v. Martin
California Court of Appeal, 2024
Oshodin v. Fire Insurance Exchange CA2/4
California Court of Appeal, 2024
Vazquez v. Los Angeles United School Dist. CA2/1
California Court of Appeal, 2023
Isom v. MacCarthy CA2/4
California Court of Appeal, 2023
Honetschlager v. Kozeychuk
California Court of Appeal, 2022
Calm Creek v. Juhan CA4/1
California Court of Appeal, 2022
Nilson v. White CA4/1
California Court of Appeal, 2021
Plascencia v. Deese
California Court of Appeal, 2021
Brown v. TGS Management Co., LLC
California Court of Appeal, 2020
Winslett v. 1811 27th Avenue, LLC
California Court of Appeal, 2018
Winslett v. 1811 27th Ave., LLC
237 Cal. Rptr. 3d 25 (California Court of Appeals, 5th District, 2018)
Kim v. Toyota Motor Corp.
California Court of Appeal, 2016
Kim v. Toyota Motor Corp.
197 Cal. Rptr. 3d 647 (California Court of Appeals, 2nd District, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
57 Cal. Rptr. 3d 849, 149 Cal. App. 4th 1384, Counsel Stack Legal Research, https://law.counselstack.com/opinion/condon-johnson-associates-inc-v-sacramento-municipal-utility-district-calctapp-2007.