Wilson v. Los Angeles County Metropolitan Transportation Authority

1 P.3d 63, 96 Cal. Rptr. 2d 747, 23 Cal. 4th 305, 2000 Daily Journal DAR 6173, 2000 Cal. Daily Op. Serv. 4657, 2000 Cal. LEXIS 4551
CourtCalifornia Supreme Court
DecidedJune 12, 2000
DocketS077461
StatusPublished
Cited by144 cases

This text of 1 P.3d 63 (Wilson v. Los Angeles County Metropolitan Transportation Authority) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson v. Los Angeles County Metropolitan Transportation Authority, 1 P.3d 63, 96 Cal. Rptr. 2d 747, 23 Cal. 4th 305, 2000 Daily Journal DAR 6173, 2000 Cal. Daily Op. Serv. 4657, 2000 Cal. LEXIS 4551 (Cal. 2000).

Opinion

Opinion

BROWN, J.

We consider in this case whether the lowest responsible bidder that is wrongfully denied a public contract has a cause of action for monetary damages against the public entity, and if so, whether those damages include bid preparation costs and lost profits. We conclude bid preparation costs but not lost profits are available under a theory of promissory estoppel. We therefore reverse the judgment of the Court of Appeal.

I. Factual and Procedural Background

In April 1994, the Los Angeles Metropolitan Transportation Authority (MTA) solicited bids to build the Red Line Hollywood/Highland station and tunnels. The lowest bid was from Tutor-Saliba-Perini (Tutor-Saliba), but plaintiff Kajima/Ray Wilson (Kajima) successfully protested Tutor-Saliba receiving the award because Tutor-Saliba had not attained MTA’s goal regarding use of Disadvantaged Business Enterprises (DBE). Ultimately, none of the submitted bids were deemed responsive, and MTA exercised its right to reject all bids. (Pub. Util. Code, § 130232, subd. (a) [“The commission, at its discretion, may reject any and all bids and readvertise.”].) Tutor-Saliba filed suit challenging this action.

*309 In November 1994, MTA solicited new bids for the same public project. This solicitation set a minimum DBE goal of 30 percent of the total amount bid. The three lowest bids came from Kajima at $68,912,089, Tutor-Saliba at $69,887,867 and Kiewit-Shea at $72,970,345. The contract was awarded to Tutor-Saliba despite the fact that its bid was almost $1 million more than Kajima’s. (See Pub. Util. Code, § 130232, subd. (a) [contracts in excess of $25,000 required to be awarded to the “lowest responsible bidder”].) Kajima again protested. Tutor-Saliba’s suit against MTA with regard to the April 1994 solicitation was subsequently dismissed.

MTA justified its selection on the ground that Tutor-Saliba, but not Kajima, satisfied the DBE participation goal. Kajima fell below the goal because it identified Manual Tejeda Trucking (Tejeda) as a “broker” in its bid, while Tutor-Saliba identified Tejeda as a “subcontractor.” Unknown to Kajima, MTA had an unwritten policy granting only a 5 percent DBE credit of bid amounts designated for entities identified as “brokers,” while awarding 100 percent credit of bid amounts for those identified as “subcontractors.” Had Kajima received the same percentage credit for the work to be performed by Tejeda as did Tutor-Saliba, Kajima’s DBE credit would have exceeded the 30 percent goal.

Kajima filed suit against MTA, seeking an injunction, issuance of a writ of mandate or prohibition, and damages. Kajima sought $93,411 for its round 1 bid and protest expenses, $134,092 for its round 2 bid and protest expenses, $1,298,589 in unabsorbed overhead expenses, and $1,544,034 in lost profit on the MTA contract. The total damages sought were $3,070,126, plus prejudgment interest.

Following a bench trial, the court issued a peremptory writ of mandate, ordering MTA to cease using its 5-percent-broker policy in connection with DBE credits, “instead of evaluating the amount of work proposed to be subcontracted to the ‘broker.’ ” In addition, the court awarded Kajima $44,869 in round 2 bid expenses, $89,223 in round 2 bid protest expenses, $300,000 in unabsorbed overhead, $350,000 in lost profits, and $139,829.74 in prejudgment interest. The total judgment entered was $923,921.74.

The Court of Appeal affirmed. It first concluded MTA’s application of the 5 percent policy to Kajima’s bid was arbitrary, violated federal *310 regulations, and was an abuse of discretion. MTA does not challenge this ruling here. It further held that the trial court acted within its discretion in awarding lost profits under a promissory estoppel theory. It stated, “We see no reason to draw a bright line in public works cases to preclude recovery of any specific type of damages under all circumstances, including lost profits .... Instead, because of the equitable nature of the [promissory estoppel] remedy, each case should be addressed on its merits to determine if the trial court has abused its discretion.” Finally, the court concluded MTA had waived the issue of overhead costs on appeal. MTA’s petition for rehearing was denied.

We granted MTA’s petition for review to determine whether the lowest responsible bidder who is wrongfully denied a public contract has a cause of action for monetary damages against the public entity, and if so, whether those damages include lost profits. We consider only whether Kajima was properly awarded its bid preparation costs and lost profits. While the trial court also awarded Kajima its round two bid protest costs and overhead costs, MTA has waived review of those issues.

II. Discussion

A. Background

In California, under the doctrine of promissory estoppel, “A promise which the promisor should reasonably expect to induce action or forbearance on the part of the promisee or a third person and which does induce such action or forbearance is binding if injustice can be avoided only by enforcement of the promise. The remedy granted for breach may be limited as justice requires.” (Rest.2d Contracts, § 90, subd. (1), p. 242; see C & K Engineering Contractors v. Amber Steel Co. (1978) 23 Cal.3d 1, 6 [151 Cal.Rptr. 323, 587 P.2d 1136] [§ 90 “has been judicially adopted in California”].) Promissory estoppel is “a doctrine which employs equitable principles to satisfy the requirement that consideration must be given in exchange for the promise sought to be enforced.” (Raedeke v. Gibraltar Sav. & Loan Assn. (1974) 10 Cal.3d 665, 672 [111 Cal.Rptr. 693, 517 P.2d 1157].)

In Drennan v. Star Paving Co. (1958) 51 Cal.2d 409, 412 [333 P.2d 757], a subcontractor withdrew its bid prior to acceptance by the general contractor, but after the general contractor had used the bid in his master bid for the *311 job, and was awarded the public contract. We concluded there was no contract between the general contractor and subcontractor, but nonetheless held the subcontractor’s bid enforceable under a theory of promissory estoppel because of the general contractor’s reasonable and detrimental reliance. (Id. at pp. 413-415.) We noted that the subcontractor “had reason to expect that if its bid proved the lowest it would be used by [the general contractor]. It induced ‘action . . . of a definite and substantial character on the part of the promisee’ ” (id. at p. 413) because the general contractor was now bound to perform that portion of the job for the amount stated in the subcontractor’s bid. (Id. at p. 415.) We concluded “it is only fair that plaintiff should have at least an opportunity to accept defendant’s bid after the general contract has been awarded to him.” (Ibid.)

In City of Inglewood-L.A. County Civic Center Auth. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaur v. Pabla CA5
California Court of Appeal, 2024
McGill v. Hearthstone CA Properties I CA6
California Court of Appeal, 2024
Aegis Asset Management v. CBRE CA1/2
California Court of Appeal, 2024
In re Uber Technologies Wage and Hour Cases
California Court of Appeal, 2023
Shenoi v. Maya CA4/3
California Court of Appeal, 2023
County of Santa Clara v. Superior Court
California Supreme Court, 2023
Blaser v. Cal. State Teachers' Retirement System
California Court of Appeal, 2022
Wright v. Old Gringo, Inc.
S.D. California, 2019
Mercury Ins. Co. v. Lara
California Court of Appeal, 2019
Mercury Insurance Co. v. Lara
California Court of Appeal, 2019
Ponte v. County of Calaveras
California Court of Appeal, 2017
Roy Allan Slurry Seal, Inc. v. Am. Asphalt S., Inc.
388 P.3d 800 (California Supreme Court, 2017)
Newport Harbor Ventures, LLC v. Morris Cerullo World Evangelism
6 Cal. App. 5th 1207 (California Court of Appeal, 2016)
Flintco Pacific, Inc. v. TEC Management Consultants, Inc.
1 Cal. App. 5th 727 (California Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
1 P.3d 63, 96 Cal. Rptr. 2d 747, 23 Cal. 4th 305, 2000 Daily Journal DAR 6173, 2000 Cal. Daily Op. Serv. 4657, 2000 Cal. LEXIS 4551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-v-los-angeles-county-metropolitan-transportation-authority-cal-2000.