St. Francis Electric v. Dept. of Transportation CA3

CourtCalifornia Court of Appeal
DecidedJuly 26, 2024
DocketC098129
StatusUnpublished

This text of St. Francis Electric v. Dept. of Transportation CA3 (St. Francis Electric v. Dept. of Transportation CA3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Francis Electric v. Dept. of Transportation CA3, (Cal. Ct. App. 2024).

Opinion

Filed 7/26/24 St. Francis Electric v. Dept. of Transportation CA3 NOT TO BE PUBLISHED California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA THIRD APPELLATE DISTRICT (Sacramento) ----

ST. FRANCIS ELECTRIC, LLC, C098129

Plaintiff and Appellant, (Super. Ct. No. 34-2022- 80003922-CU-WM-GDS) v.

DEPARTMENT OF TRANSPORTATION,

Defendant and Respondent;

ALFARO COMMUNICATION CONSTRUCTION, INC.,

Real Party in Interest and Respondent.

California law requires public agencies to conduct a competitive bidding process before awarding contracts on certain projects. This process involves an agency publicly advertising that it seeks bids for a project, publicly opening any submitted bids at an assigned time, and, in general, awarding the project contract to the lowest responsible bidder. Typically, bidders participating in this process cannot withdraw their bids after submitting them. But in some cases, a bidder may seek to withdraw its bid based on a mistake. In that event, however, under Public Contract Code section 5105 (section 5105), the bidder is “prohibited from participating in further bidding on the project on

1 which the mistake was claimed . . . .” This restriction serves to disqualify those who seek to withdraw their bids from rebidding the same project. In this case, the Department of Transportation (Caltrans) concluded that a company that withdrew its bid on a project due to a mistake could participate in further bidding after Caltrans rejected all bids on the project, modified the project in some respects, and again advertised for bids. Caltrans reasoned that the changes it made to the project rendered section 5105’s prohibition on further bidding inapplicable. Another bidder on the project, St. Francis Electric, LLC (St. Francis), objected to Caltrans’s decision and asked the trial court to find the decision unlawful. It argued that the initial project and the revised project, although different in minor respects, remained the same for purposes of section 5105 and so the statute’s prohibition on further bidding applied. The trial court, however, disagreed and ruled in Caltrans’s favor. Applying a deferential standard of review, we affirm. BACKGROUND In September 2021, Caltrans advertised a project for the installation of fiber optic cable systems and other improvements on State Routes 51 and 99. Caltrans described the project as follows in the notice to bidders: “For Construction on State Highway in Sacramento County in and near Elk Grove and Sacramento on Route 99 from Grant Line Road to Route 50 and on Route 51 from Route 50 to 0.1 mile south of the Fort Sutter Viaduct. “[¶] . . . [¶] “Contract No. 03-0H6704 “03-Sac-51, 99-0.0/0.1, 10.0/R24.3 “Project ID 0316000005 “Federal-Aid Project “ACNH-X067(084)E” (Some capitalization omitted.)

2 The bid package included, among other things, nearly 400 pages consisting of a notice to bidders, special provisions, and standard specifications. Alfaro Communications Construction, Inc. (Alfaro) submitted the lowest bid on the project. But a couple of days after Caltrans reviewed the submitted bids, Alfaro asked to withdraw its bid, citing a mathematical error in its listed labor costs. Caltrans agreed to allow Alfaro to withdraw. It afterward rejected all bids and informed the bidders, including St. Francis, that the scope of the work and funding for the project would be reevaluated and the project readvertised. In February 2022, following some modifications to the project requirements and specifications, Caltrans again advertised the project for bids. The general project description and contract number remained the same: “For Construction on State Highway in Sacramento County in and near Elk Grove and Sacramento on Route 99 from Grant Line Road to Route 50 and on Route 51 from Route 50 to 0.1 mile south of the Fort Sutter Viaduct. “[¶] . . . [¶] “Contract No. 03-0H6704 “03-Sac-51, 99-0.0/0.1, 10.0/R24.3 “Project ID 0316000005 “Federal-Aid Project “ACNH-X067(084)E” (Some capitalization omitted.) The revised bid package, like the initial bid package, included a notice to bidders, special provisions, and standard specifications. But this time, these materials were 30 pages longer. Once more, Alfaro submitted the lowest bid on the project. St. Francis, the second lowest bidder, filed a written protest with Caltrans of the award to Alfaro, arguing that because Alfaro had earlier withdrawn its bid on the initial project advertised in 2021, it

3 could not bid on the revised project advertised in 2022. It reasoned this followed from section 5105’s prohibition on a bidder that withdraws a bid on a project from participating in further bidding on the same project. Caltrans rejected St. Francis’s protest in a June 2022 letter. It concluded that the initial and revised projects were different, reasoning that “in addition to other changes made to the rebid version of [the project], Caltrans made the following material changes: (1) Providing additional working days; (2) Allowing for possible 55-hour lane closures; (3) Revising the plans to reflect common industry installation process(es); and (4) Increasing the Disadvantaged Business Enterprise (DBE) goal.” Elaborating on the first reason, Caltrans noted that the original solicitation allowed between 100 to 140 working days, but the revised solicitation allowed 130 to 180 working days. And elaborating on the third reason, it wrote that the original plan sheets set borehole spacing at 500-foot intervals, but the revised plan sheets set borehole spacing at closer to 300-foot intervals. St. Francis afterward filed a petition for writ of mandate and complaint with the trial court, seeking, among other things, to have the court set aside Caltrans’s decision. The trial court denied its request for relief. While the court acknowledged that many aspects of the original project and the revised project were identical, it concluded that the change in working days, the change in potential borehole spacing, and the increase in the DBE goal were all substantive changes supporting Caltrans’s determination that the two projects were different for purposes of section 5105. The court added that Alfaro had described several other differences between the two projects. But it found it unnecessary to consider these additional differences, finding the reasons Caltrans identified sufficient to rule in its favor. St. Francis timely appealed.

4 DISCUSSION I Mootness We start with Caltrans’s claim that this matter is moot. A few days before oral argument, Caltrans moved to dismiss this appeal on the ground of mootness. It stated that it formally accepted Alfaro’s completed work for the project over two months before, and it provided a declaration from its manager for this project confirming the same. It then argued that this appeal is therefore moot, for the only relief St. Francis seeks on appeal is to invalidate the award of the project to Alfaro and to have the project awarded to itself. We reject Caltrans’s argument and deny its motion to dismiss. St. Francis, it is true, sought in its petition and complaint to invalidate the award of the project to Alfaro. But it also sought a declaration of the parties’ rights, attorney fees under Code of Civil Procedure section 1021.5, and “[s]uch other relief as the Court deems just and proper”— which it later argued included bid preparation costs and bid protest costs. At the trial level, moreover, Caltrans agreed that should St. Francis succeed on its petition, “it may seek costs of bid preparation.” Alfaro said the same.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western States Petroleum etc. v. State Bd. of Equalization
304 P.3d 188 (California Supreme Court, 2013)
McKinny v. Board of Trustees
642 P.2d 460 (California Supreme Court, 1982)
Topanga Assn. for a Scenic Comm. v. CTY OF LOS ANGELES
522 P.2d 12 (California Supreme Court, 1974)
Western States Petroleum Assn. v. Superior Court
888 P.2d 1268 (California Supreme Court, 1995)
Estate of Kalal
121 Cal. App. 3d 841 (California Court of Appeal, 1981)
Colombo Construction Co. v. Panama Union School District
136 Cal. App. 3d 868 (California Court of Appeal, 1982)
Golden Drugs Co., Inc. v. Maxwell-Jolly
179 Cal. App. 4th 1455 (California Court of Appeal, 2009)
Mike Moore's 24-Hour Towing v. City of San Diego
45 Cal. App. 4th 1294 (California Court of Appeal, 1996)
Jumaane v. City of Los Angeles
241 Cal. App. 4th 1390 (California Court of Appeal, 2015)
Quinchard v. Board of Trustees
45 P. 856 (California Supreme Court, 1896)
San Diegans for Open Gov't v. City of San Diego
242 Cal. Rptr. 3d 541 (California Court of Appeals, 5th District, 2018)
United Grand Corp. v. Malibu Hillbillies, LLC
248 Cal. Rptr. 3d 294 (California Court of Appeals, 5th District, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
St. Francis Electric v. Dept. of Transportation CA3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-francis-electric-v-dept-of-transportation-ca3-calctapp-2024.