Bares v. City of Portola

269 P.2d 239, 124 Cal. App. 2d 813, 1954 Cal. App. LEXIS 1813
CourtCalifornia Court of Appeal
DecidedApril 28, 1954
DocketCiv. 8419
StatusPublished
Cited by3 cases

This text of 269 P.2d 239 (Bares v. City of Portola) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bares v. City of Portola, 269 P.2d 239, 124 Cal. App. 2d 813, 1954 Cal. App. LEXIS 1813 (Cal. Ct. App. 1954).

Opinion

*814 SCHOTTKY, J.

Appellant, a licensed general contractor doing business as Ted Bares Construction Company, was the successful bidder for the job of constructing certain sewerage system improvements for respondent city of Portola. Plans and specifications had been prepared and furnished to appellant and other prospective bidders when bids were solicited by respondent city. Upon the acceptance of appellant’s bid, the parties entered into a written contract.

Appellant’s bid, which was submitted to the eity, contained the following provisions:

“The undersigned [appellant] has examined the location of the proposed work and is familiar with the plans and specifications and the local conditions at the place where the work is to be done.
“The undersigned understands that the quantities as set forth under the foregoing units are approximate only and are for the purpose of comparing bids and fixing the amount of bonds and agrees that these quantities may be increased or decreased, or the relative amounts of the various items varies without claim for damage or loss of anticipated profit, and that payment will only be made on the basis of the actual quantities of work performed.”

The specifications, which are a part of the contract, provide in part as follows :

‘‘ The City reserves the right to make alterations by addition to or omission from the contract, specifications or drawings, which change or modification shall in no way affect or make void the contract. The difference in cost of the work affected by such change will be added to or deducted from the amount of said contract price, as the case may be, by a fair and reasonable valuation, which shall be determined in one or more of the following ways :
“ . . . No extra work shall be performed or change be made except upon a written order from the Engineer pursuant to authorization by the City Council stating that the extra work or change is authorized, and no claim for an addition to the contract sum shall be valid unless so ordered.” (Italics added.)

The contract, itself, provides:

“That said Contractor agrees to receive and accept as full compensation for furnishing all materials and for doing all the work embraced and contemplated in this agreement the *815 prices as set forth in the proposal submitted to the City-Council of the City of Portola on the-day of-, 1949, and the true copy thereof hereto attached; also, for all loss or damage arising out of the nature of said work, or from the action of the elements or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until the acceptance thereof by the Owner; and for all risks connected with the work, and for well and faithfully completing the work and the whole thereof, in the manner and according to the said plans and specifications and the requirements of the engineer under them, to-wit: The prices as set forth in the Proposal for—- . .

Appellant admitted that he was familiar with the provisions set forth above.

The contract was entered into on or about July 25, 1949, and appellant commenced the work on or about September 19, 1949, and continued to work on the job until July 15,

1950, when it was completed. Respondent city accepted the completed job on September 13, 1950.

It appears from the record that as the work progressed there were deviations from the plans, and certain difficulties were encountered because of the location of underground lines which were not correctly shown in the plans. Appellant testified to the folhnving items as exceeding the performance required of him under the contract or as involving additional expense due to errors in the plans or specifications: (1) appellant was required by the city engineer to abandon, back-fill and relocate a ditch when appellant, in excavating, struck a water line which was incorrectly shown in the plans (cost: $225) ; (2) in the area near the Western Pacific roundhouse, appellant was required by the city engineer to dig certain ditches deeper than was indicated in the plans (cost: $5,840); (3) appellant encountered unexpected difficulties in installing five manholes, owing to interference from other lines which were incorrectly shown in the plans (cost: $250); (4) in installing seven other manholes, appellant was required to excavate to greater depths than those shown in the plans (cost: $440); (5) appellant was required by the city engineer to backfill a ditch which exposed a city water line not shown in the plans, the backfilling being done to protect the line from freezing during the winter months and it being necessary to re-dig the ditch in the spring (cost: $400); (6) appellant was required by the city engineer to dig another ditch *816 (along Main Street) deeper than was indicated in the plans (cost, $365); and (7) appellant was required by the specifications to order more pipe, not readily resalable, than was actually used on the job and paid for by respondent city (cost: $147.86). The amount shown as “cost” in connection with each of the above items was the actual cost or a reasonable charge, according to the uneontradieted testimony of appellant. The total of these amounts is $7,667.86.

A dispute having arisen as to the amount due appellant, appellant commenced an action against respondents city of Portola and city council of city of Portola to recover the sum of $10,715.51 alleged to be due appellant for labor and materials furnished in performance of the contract. Appellant in his brief states that respondent city paid $3,047.66 of that amount, leaving a disputed balance of $7,667.85. This is the total of the amounts claimed for the seven items specified above, as set out in the third to the ninth causes of action, inclusive, in appellant’s complaint. The first and second causes of action show different amounts, the first being a common count for materials furnished and services rendered, and the second being an action on the contract for the contract price, and both showing a total claim of $37,996.50 (apparently including the seven amounts), less a payment of $27,428.85, leaving a balance of $10,567.65, and the latter cause of action also admitting an additional tender by respondent city of $3,047.65 as final payment under the contract. It appears that the city did make progress payments totaling $27,428.85, and a final payment of $3,047.65, or total payments of $30,476.50. However, in view of appellant’s statement we may assume that the only amounts now in dispute are those claimed for the seven items specified above.

The case was tried before the court, sitting without a jury, and the trial court found that the items in question, hereinbefore enumerated, were not in excess of the performance required of appellant under the contract, and found further that in making his bid appellant did not rely upon the plans, specifications, surveys, drawings, cuts or profiles prepared by the city engineer, but instead examined the location of the proposed work and assumed all responsibility for errors and omissions in the plans, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acoustics, Inc. v. Trepte Construction Co.
14 Cal. App. 3d 887 (California Court of Appeal, 1971)
A. Teichert & Son, Inc. v. State of Cal.
238 Cal. App. 2d 736 (California Court of Appeal, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
269 P.2d 239, 124 Cal. App. 2d 813, 1954 Cal. App. LEXIS 1813, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bares-v-city-of-portola-calctapp-1954.