Enterprise Planing Mill Co. v. Methodist Episcopal Church

158 N.W. 386, 100 Neb. 29, 1916 Neb. LEXIS 128
CourtNebraska Supreme Court
DecidedJune 3, 1916
DocketNo. 18646
StatusPublished
Cited by9 cases

This text of 158 N.W. 386 (Enterprise Planing Mill Co. v. Methodist Episcopal Church) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Enterprise Planing Mill Co. v. Methodist Episcopal Church, 158 N.W. 386, 100 Neb. 29, 1916 Neb. LEXIS 128 (Neb. 1916).

Opinion

Letton, J.

This is an action in equity for the purpose of establishing an equitable lien on certain church property in Sterling on the ground that the officers of the church induced plaintiff to refrain from filing a mechanic’s lien by promising to pay the debt if such lien was not filed. It is also [30]*30alleged that by reason of the promise the lien was not filed, the time for filing has expired, defendant refuses to pay the debt, and that unless a lien is allowed plaintiff will lose the amount due. The vice-president of plaintiff corporation testified that a promise and agreement was made by two members of the building committee of the church that if he would not file a lien they would see the debt was paid or furnish security for its payment. That such a promise or agreement was ever made was denied by the men by whom it was said to be made, though the fact that they did not desire a lien filed and had so stated to the officer mentioned was admitted, and that he had requested payment or security. It is shown that the account was left with them in order to consult the third member of the committee, who was absent, and that six days before the time for filing the lien expired it was returned to the plaintiff with the words: “O. K. as to lien, but not as to amount due from L. A. Schlosser, contractor.” This was signed “C. E. Zink, Stanley Ostrander, and E. Ross Hitchcock, Committee.” The vice-president testifies that, when the paper thus indorsed was returned to Lincoln, he showed it to his partner, who said in effect that, this made them safe now, and that this was his idea also, and therefore no lien was filed. The paper was received by plaintiff on the 7th of April, and the time for filing a lien expired on April 13.

The district court, which had the witnesses before it, found for the defendant. It evidently believed the testimony of the members of the committee that they refused to give security as requested and sent back the account marked “O. K. as to lien” to indicate they had no objections to a lien being filed, and that this was done promptly so as to allow the lien to be filed within the time allowed. It is clear from the testimony on behalf of plaintiff that, on account of a mistake being made by its officers as to the force of the memorandum written on the account, it failed to file a lien. No deceit or fraud is shown on the part of the committee. The church paid the contractor [31]*31more than was due him for labor and material before the account was presented to the committee. The committee then had no power to mortgage or bind the church property.

Plaintiff has not sustained the burden of proof as to the disputed fact. Under such circumstances there is no ground for the interposition of a court of equity. The conclusion reached by the district court was right under the proofs, and its judgment is

Affirmed.

Morrissey, C. J., and Rose, J., dissenting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bath v. Bath
35 N.W.2d 509 (Nebraska Supreme Court, 1949)
Dier v. Dier
4 N.W.2d 731 (Nebraska Supreme Court, 1942)
Micek v. Omaha Steel Works
287 N.W. 645 (Nebraska Supreme Court, 1939)
Lautenschlager v. Lautenschlager
279 N.W. 200 (Nebraska Supreme Court, 1938)
Hole v. Hamp
278 N.W. 480 (Nebraska Supreme Court, 1937)
Olson Construction Co. v. Commercial Building & Investment Co.
256 N.W. 22 (Nebraska Supreme Court, 1934)
Maryland Casualty Co. v. Geary
244 N.W. 797 (Nebraska Supreme Court, 1932)
Astuto v. V. Ray Gould Co.
242 N.W. 375 (Nebraska Supreme Court, 1932)
Southern Surety Co. v. Parmely
236 N.W. 178 (Nebraska Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
158 N.W. 386, 100 Neb. 29, 1916 Neb. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/enterprise-planing-mill-co-v-methodist-episcopal-church-neb-1916.