Meyers v. Wood

65 S.W. 174, 95 Tex. 67, 1901 Tex. LEXIS 118
CourtTexas Supreme Court
DecidedNovember 21, 1901
DocketNo. 1043.
StatusPublished
Cited by18 cases

This text of 65 S.W. 174 (Meyers v. Wood) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meyers v. Wood, 65 S.W. 174, 95 Tex. 67, 1901 Tex. LEXIS 118 (Tex. 1901).

Opinion

BROWN, Associate Justice.

The Court of Civil Appeals for the First Supreme Judicial District have certified to this court the following statement and questions:

“In above styled cause, pending in this court on appeal from the District Court of Lamar county, the record discloses that appellees, J. W. Wood and J. H. Hancock, each brought suit against appellants, M. and M. L. Meyers, and Staggs & Pearson, a firm of contractors, to recover upon accounts for material furnished by appellees in the construction by said contractors of a building upon premises owned by appellants, and to establish and foreclose a materialman’s lien upon said premises. By agreement of parties, the two suits were consolidated and tried as one, and the trial in the court below resulted in a judgment in favor of appellees for the amount of their respective claims. The appellants, in the court below, filed general and special pleas in defense of plaintiffs’ suit and also filed cross-bill in which they sought to recover against Staggs & Pearson and their bondsmen, Caviness and Wilson, damages for the failure of said Staggs & Pearson to complete their contract for the erection of appellants’ building in the time specified in said contract, and also to recover of said Staggs & Pearson the sum of $517 as overpayment on their said contract, which amount appellants claim to have paid said contractors by mistake. The cross-bill alleges that by the terms of said contract said defendants, Staggs & Pearson, agreed and covenanted to complete said building and have same ready for occupancy by the 15th day of November, 1899, but that said building had not yet been fully completed by said defendants' in accordance with their said contract, and that no portion of same was ready for occupancy prior to the 2d day of February, 1900that appellants had tenants ready to occupy said building on November 15, 1899, and that by the failure of said defend-1 ants to complete said building within the time specified and agreed upon in said contract, appellants had lost two and one-half months rent of same and had been thereby damaged in the sum of $175. This pleading also alleges the execution of a bond by the defendants, Caviness and Wilson, to secure appellants in the performance by said Staggs & Pearson of their contract undertaking, and the consequent liability of said Caviness and Wilson for the failure of said Staggs & Pearson to comply with their contract. It is further alleged in said cross-bill that the payments to the contractors were to be made on estimates made by W. B. Barry, the architect of said building, as the work progressed, the final payment To be made within ten days after the contract is filed.’ This plea also alleges that appellants had, prior to the completion of said building, paid to the contractors and upon orders issued by them $517 in excess of the contract price of the building, the amount in excess of said contract price having been paid by mistake. In answer to this cross-bill, the bondsmen, Caviness and Wilson, filed general demurrer and also a special plea in which it is alleged that by the terms of the contract between appellants *69 and Staggs & Pearson, appellants ‘were to retain in their possession 25 per cent of the contract price of said building until same was completed, that they have failed, neglected and refused to retain in their possession 25 per cent of the contract price of said building, but have, these defendants allege, paid to the contractors, Staggs & Pearson, a sum greatly in excess of 75 per cent of the contract price that they, under the contract, were authorized to pay them/ by reason of which said bondsmen claim to have been released from all liability. In reply to this’ answer, appellants filed a supplemental answer which contains the following allegations :
“‘Defendants admit that they have paid to Staggs & Pearson more than 75 per cent of the contract price for the erection of said building. Defendants allege that the right to retain 25 per cent of contract price as expressed in said contract was and is a right exclusive to these defendants, and the payment of said amount in excess of 75 per cent was in no way violative of said contract and did not change the liability of the surety. And all of the amount paid by the defendants to Staggs & Pearson, except about twenty dollars, was used for labor and material in constructing said house and enabled Staggs & Pearson to do what they did on said building for a much less sum than they could have done but for said payments/
“Upon this state of the pleading, the trial court sustained the general demurrer of the bondsmen, Caviness and Wilson, to appellants’ cross-bill. Upon the trial in the court below, appellees introduced in evidence the accounts filed by them in the office of the county clerk for the purpose of perfecting their materialmen’s lien. These accounts fail to show "the dates upon which any of the items in the accounts were furnished the contractors. The Hancock account was sworn to on May 2, 1900, as shown by the certificate of the notary who took the affidavit, but none ■of the items in the account are dated and the affidavit does not show the date upon which any of said material was furnished. The Wood account-bears the date of January 31, 1900, at the top of the first page, but noj dates are given in the account showing when the various items were furnished, nor does the affidavit, which was made on April 30, 1900, show’ the date upon which any of the material was furnished. This account’ contains, among others, the following items:
“‘Bill of sash and doors per contract...............$640.00
“‘Feb. 3rd. To bill of mill work (contract)........ 175.00’
“Appellants objected to the introduction of said accounts upon the following grounds:
“ ‘1. Because of a material variance between the allegations in plaintiffs’ petitions and the record evidence offered and admitted.
“ ‘2. Because it does not appear from the bill of particulars when the material was furnished by plaintiffs in the construction of appellants’ house.
“ ‘3. Because it does not appear what material was furnished by jplaintiffs.
*70 ‘4. Because said bills of particulars as shown by the record are not such as are required by the statutes of the State of Texas.’
“It was shown by parol testimony that said accounts were both filed in the office of the county clerk within the time prescribed by the statute, and that appellee Wood gave appellants written notice at the time the' several items in his account were furnished and appellee Hancock had delivered appellants a copy of his account before same was filed. Ho-itemized statement' showing the items comprised in the bill of sash and doors, $640, and bill of mill work, $175, was ever presented to appellants,, but it was shown that Barry, the architect and agent of appellants, prepared from the details of the building contract a list of the various articles included in this bill and same was ordered by Wood for Staggs &. Pearson in bulk and was so charged to them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wiseman Hardware Co. v. R. L. King Construction Co.
387 S.W.2d 79 (Court of Appeals of Texas, 1965)
Maryland Casualty Co. v. Barron-Britton, Inc.
327 S.W.2d 769 (Court of Appeals of Texas, 1959)
Turner Roofing & Supply Co. v. United Pacific Insurance Co.
289 S.W.2d 407 (Court of Appeals of Texas, 1956)
Capitol Steel & Iron Co. v. Standard Accident Insurance Co.
299 S.W.2d 738 (Court of Appeals of Texas, 1952)
Houston Fire & Casualty Ins. Co. v. Col-Tex Refining Co.
231 S.W.2d 468 (Court of Appeals of Texas, 1950)
Hill v. Praetorians
219 S.W.2d 564 (Court of Appeals of Texas, 1949)
Friedman v. American Surety Co. of New York
154 S.W.2d 659 (Court of Appeals of Texas, 1941)
Aetna Casualty & Surety Co. v. Hawn Lumber Co.
97 S.W.2d 460 (Texas Supreme Court, 1936)
Ormsby Chevrolet Co. v. White
60 S.W.2d 517 (Court of Appeals of Texas, 1933)
Union Indemnity Co. v. Rockwell
57 S.W.2d 90 (Texas Commission of Appeals, 1933)
Cook v. Yandell Realty Co.
275 S.W. 850 (Court of Appeals of Texas, 1925)
Hemphill v. Gleason
272 S.W. 275 (Court of Appeals of Texas, 1925)
Compton v. Jennings Lumber Co.
266 S.W. 569 (Court of Appeals of Texas, 1924)
Banner Oil & Gas Co. v. Gordon
235 S.W. 945 (Court of Appeals of Texas, 1921)
Gordon-Jones Const. Co. v. Welder
201 S.W. 681 (Court of Appeals of Texas, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
65 S.W. 174, 95 Tex. 67, 1901 Tex. LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meyers-v-wood-tex-1901.