H., E. & W. T. R'y Co. v. Snelling

59 Tex. 116, 1883 Tex. LEXIS 117
CourtTexas Supreme Court
DecidedApril 9, 1883
DocketCase No. 1347
StatusPublished
Cited by10 cases

This text of 59 Tex. 116 (H., E. & W. T. R'y Co. v. Snelling) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H., E. & W. T. R'y Co. v. Snelling, 59 Tex. 116, 1883 Tex. LEXIS 117 (Tex. 1883).

Opinion

Stayton, Associate Justice.—

This suit was brought by R. P. Snelling against the appellant to recover a balance due on two accounts, one between appellant and Harper & Snelling, a firm of which he was a member, and which had been dissolved by the death of Harper; Snelling claiming a recovery in his individual capacity, by virtue of a transfer from the legatee and executrix of Harper. This Harper & Snelling claim was for the construction of forty miles of appellant’s road, in divisions of twenty-five, and ten, and five miles. The other account was for the construction of fifteen or fifteen and a half miles more of the road by the plaintiff Snelling himself, being the ten remaining miles of the fifteen mile contract of Harper & Snelling undone at Harper’s death, and five or five and a half more miles then constructed by Snelling. Plaintiff set out lengthy itemized account.

Defendant pleaded the general issue. It also pleaded that at the death of Harper a full and complete settlement was had between it and R. P. Snelling and Mrs. Harper of all these matters and accounts up to the fortieth mile of the road, embracing all the items of debit and credit up to that time, which it had fully complied with and satisfied by paying Mrs. Harper the amount due her, $10,824.40, and passing up to Snelling’s credit on its books, as agreed, the balance due him then of $3,481.57, he remaining with it as a contractor, and undertaking to do the work himself from then on. It also pleaded a long itemized account of payments and offsets to plaintiff’s account, claiming to have paid him in full.

The plaintiff denied that there had been such settlement as was alleged by the defendant, and alleged that if it should be found that there had been a settlement, that in the settlement various items of the account sued on had been omitted by mistake from the settlement.

There was much testimony introduced by the respective parties as to whether or not there was any settlement made after the death of Harper, and if so, as to whether matters embraced in the account sued upon were embraced in that settlement. This testimony was [118]*118conflicting. After submitting to the jury the question as to whether or not there had been such a settlement as was set up by the defendant, the court instructed the jury: “ If you find, as the defendant claims, that the Harper settlement, as it is called in the testimony, was intended by the parties to be a full settlement of all matters as between Harper & Snelling on the one hand, and the railroad company on the other, up to that date, yet if you further believe from the evidence that Harper & Snelling had done other work, or furnished other material, which were not brought into that settlement, and were not discussed in it, but were forgotten or overlooked by the parties, then, to the extent of the value of such other work or material, the plaintiff is entitled to recover in this suit.”

The giving of this charge is assigned as error. This charge in effect informed the jury that if, by mutual mistake of the parties, . items of account sued upon in this cause were not brought into that settlement, then the same might be considered by them.

This charge is believed to have stated the rule applicable to the ease correctly; for while it is true that a stated account will be held conclusive between parties where no fraud or mistake is shown, “but if there has been any mistake, or omission, or accident, or fraud, or undue advantage, by which the account stated is vitiated, and the balance is incorrectly fixed, a court of equity will not suffer it to be conclusive between the parties, but will allow it to be opened and re-examined.” Story’s Equity, 523.

In this case it does not appear that the condition of the parties had in any manner been so altered by any settlement made, or attempted to be made, as to render it inequitable or oppressive upon either party to consider the accounts between them, as in some cases it is found to be, where vouchers have been surrendered, or other evidence of the true state of the accounts have been rendered inaccessible.

Harper & Snelling having contracted to construct fifteen miles of the defendant’s road, which had been located, surveyed and profiled, for the gross sum of 017,600, the same being from the end of the first thirty-five miles of road to the end of the fiftieth mile, and ■five miles of the road which they had thus contracted to construct having been completed upon the lines contemplated by the parties at the time the contract was made, prior to the death of Harper,

■ Snelling contracted to complete the remaining ten miles in accordance with the original agreement made between the railway company and Harper and himself.

After that agreement was made by Snelling, the railway company [119]*119changed the line of its road for the ten miles remaining to be constructed, and upon this new line, at the direction of the company, Snelling constructed the road, which he alleged required a greater expenditure of labor, material and time than would have been requisite to construct the road over the line contemplated by the contracts, and for this he sought extra compensation.

There was evidence tending to show that it was more difficult and expensive to construct the road where constructed, than it would have been on the line originally contemplated, and with reference to which the contract was made. There was, howevei*, some conflict of testimony upon this question, and the court charged the jury as follows: As to what has been termed the lump’ contract, you are charged that if you believe from the evidence that Harper & Snelling agreed with the defendant to construct its road from the thirty-fifth to the fiftieth mile for $47,600, on aline then established by defendant, and known to Harper & Snelling, then defendant had no right afterwards to change that line, without their consent, so as to materially increase the cost of construction above what it would have been on the old line. And if you believe that Harper & Snelling built the first five miles under that contract before Harper’s death, and that Snelling then contracted to complete the lump contract for the same sum, less the cost of the first five miles, as the parties had agreed on, then the defendant had no right to change the line of location, without Snelling’s consent, so as to materially increase the cost. And if you believe defendant did so change the line without Snelling’s consent, and that said change cost Snelling more to construct the road than it would have cost him to construct it on the old line, then he is entitled to recover in this suit such additional cost.”

The giving of this charge is assigned as error.

If the line of the road was changed after the contract was made, and Snelling was requested to construct it upon the new line, and did so, the law would imply an agreement to compensate him for such additional cost of construction as the new line imposed, in the absence of some agreement to the contrary.

But in ease of such deviation from contract, by consent, which completion upon the new line by the contractor, without protest, would seem to imply, it would seem that the original contract, so far as can. be, should regulate the price for the work; and that when this cannot be done in reference to the whole work, that then, as to extra work, the contractor would be entitled to recover upon a quantum meruit.

[120]*120The rule is thus stated by Hr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cohen v. Lewis
44 S.W.2d 468 (Court of Appeals of Texas, 1931)
Morrison v. Sewell
4 S.W.2d 1029 (Court of Appeals of Texas, 1927)
B. F. & C. M. Davis Co. v. W. E. Callaghan Const. Co.
298 S.W. 273 (Texas Commission of Appeals, 1927)
Mood v. Methodist Episcopal Church
296 S.W. 506 (Texas Commission of Appeals, 1927)
Mood v. Methodist Episcopal Church South
289 S.W. 461 (Court of Appeals of Texas, 1926)
Dodson v. Watson
220 S.W. 771 (Texas Supreme Court, 1920)
Hayden v. City of Astoria
164 P. 729 (Oregon Supreme Court, 1917)
Watson v. Dodson
143 S.W. 329 (Court of Appeals of Texas, 1911)
City St. Improvement Co. v. Kroh
110 P. 933 (California Supreme Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
59 Tex. 116, 1883 Tex. LEXIS 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-e-w-t-ry-co-v-snelling-tex-1883.