Hayden v. City of Astoria

164 P. 729, 84 Or. 205, 1917 Ore. LEXIS 225
CourtOregon Supreme Court
DecidedMay 1, 1917
StatusPublished
Cited by11 cases

This text of 164 P. 729 (Hayden v. City of Astoria) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hayden v. City of Astoria, 164 P. 729, 84 Or. 205, 1917 Ore. LEXIS 225 (Or. 1917).

Opinion

Mr. Justice McCamant

delivered the. opinion of the court.

The sole assignment of errors on behalf of plaintiffs is as follows:

“That the court erred in not rendering judgment for the plaintiffs in a larger amount.”

1. The defendant contends that this assignment is insufficient. It would have been better practice for [211]*211plaintiffs to specify the items in the findings of the lower court which are objected to and also the additional amounts claimed by them for each class of work. The requirement of assignments of error is no longer statutory in this state, but is found in the rules of this court. The requirement is that appellant “set out briefly and concisely the errors relied on.” The rule “should be construed reasonably and liberally to promote justice, and not so as to embarrass suitors in the appellate courts by unnecessary restrictions ”: 3 C. J. 1349. In other words, a party entitled to relief in this court should not be turned away remediless if any fair construction of the rule will uphold his assignments of error.

“In the later cases courts have shown that they are no longer disposed to scrutinize assignments of error with the minuteness which was applied in the earlier decisions”: 2 E. C. L. 163.

The bill of exceptions shows that plaintiffs pointed out to the lower court with precision and in great detail what their contentions were, and these contentions are presented in this court with the same clearness in plaintiffs’ briefs. In view of these other portions of the record we think the assignment of error above quoted sufficiently serves the purpose designed by the rule of this court.

2. The lower court found that the defendant had imposed burdens on plaintiffs not contemplated by the contract and that there had been such departures from the contract as entitled plaintiffs to recover on a quantum meruit. Plaintiffs claim that the measure of their recovery should be the cost to them of the work performed plus fifteen per cent for overhead and profit. The evidence abundantly sustains the findings of the. lower court on the subject of a departure from the con[212]*212tract. It sufficiently appears that the excavation contemplated by the parties when the contract was let could have been completed by May 1, 1912, and the entire dam could have been constructed by October 1, 1912; that by reason of an enlargement of the excavation and burdensome methods of doing the work, imposed on plaintiffs by defendant’s engineers, the progress of the work was so delayed that plaintiffs could not begin the laying of concrete until September, 1912, and that the most burdensome portion of the work had to be done in the winter season under most disadvantageous conditions. These circumstances clearly entitle plaintiffs to recover on a quantum meruit for the reasons set. forth in the former opinion of this court.

3-5. Evidence was offered and received on behalf of plaintiffs to the effect that contractors are usually compensated for work without their contract by the “force -account” method; that is, by paying them the cost of doing the work plus a percentage to cover overhead expense and profit. Notwithstanding this testimony we think the lower court adopted the proper method of relieving plaintiffs. In this character of litigation the contract is admissible in evidence as establishing the standard of value: Reynolds v. Jourdan, 6 Cal. 108, 111; Boyd v. Bargagliotti, 12 Cal. App. 228 (107 Pac. 150, 154); Wheeden v. Fiske, 50 N. H. 125, 128. In so far as the work conforms to the contract in character and in the conditions under which it is done, the contract price will govern: Dermott (Ingle) v. Jones, 2 Wall. (69 U. S.) 1, 9 (17 L. Ed. 762); Hollinsead v. Mactier, 13 Wend. (N. Y.) 276; Merrill v. Ithaca etc. R. Co., 16 Wend. (N. Y.) 586, 589 (30 Am. Dec. 130); Board of Commissioners v. O'Connor, 137 Ind. 622 (35 N. E. 1006, 1009, 37 N. E. 16); Houston, E. & W. T. Ry. Co. v. Snelling, 59 Tex. 116, 119; Be Boom v. Priestly, [213]*2131 Cal. 206, 207. "When, as in this case, the work is done under burdensome conditions not within the contemplation of the parties when the contract was made and when the deviations from the contract are so material as to entitle the contractor to recover on a quantum meruit, the recovery allowed should take the form of damages adequate to compensate for the additional burdens, which damages should be added to the contract price: Dubois v. Delaware & H. Canal Co., 4 Wend. (N. Y.) 285, 291; Koon v. Greenman, 7 Wend. (N. Y.) 121, 123; Houston, E. & W. T. Ry. Co. v. Snelling, 59 Tex. 116, 120; Wood v. Fort Wayne, 119 U. S. 312, 321 (30 L. Ed. 416, 7 Sup. Ct. Rep. 219). In Jones v. Woodbury, 11 B. Mon. (50 Ky.) 167-169, the Kentucky court says:

“The general principle applicable to the case of a special contract for erecting a house, when in the progress of the work there have been alterations or additions not originally contemplated nor expressly provided for, seems to be that as far as the work can be traced under the original contract, it shall be paid for under that contract, and that the residue which cannot be brought within the contract shall be paid for as if there were no contract. But the safety of employers, and the good faith proper to be observed in all cases, requires that this rule should be so applied as not to violate the principles above stated; and they seem to indicate further, that extra work either in quantity or quality, unless done under an express agreement, or at least a statement of the price, should not be charged for at a greater rate in reference to the measure and value price of such work, than the contract price bears to the measure and value price of the work contracted to be done. So that if the contract price was a fourth or a fifth less than the price estimated by measure and value, the extra work should not be estimated at more than three-fourths or four-fifths of its price according to measure and value.”

[214]*214The rales announced in these authorities forbid us to sustain plaintiffs’ contention that they are entitled to recover the cost to them of the work and materials plus a percentage for profit and superintendence. Their recovery was properly based on the unit prices provided by the contract with added damages to compensate for the burdens imposed upon them. This brings us to the question of the adequacy of the damages awarded.

6. The Circuit Court in trying this case exercised the functions of a jury. Its findings are binding on this court unless wholly without support in the evidence. The lower court found that Lars Bergsvik was engineer of the defendant in charge on its behalf of the work in question, and that Arne Froyseth was his assistant who was present on the work at all times. There was some conflict in the testimony as to the circumstances under which the work of excavation proceeded. The court resolved this conflicting testimony in favor of plaintiffs, finding as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Howser
497 P.2d 1163 (Oregon Supreme Court, 1972)
Friberg v. Elrod
296 P. 1061 (Oregon Supreme Court, 1930)
Feldschau v. Clatsop Co.
208 P. 764 (Oregon Supreme Court, 1922)
Howland v. Fenner Mfg. Co.
206 P. 730 (Oregon Supreme Court, 1922)
McDonald v. Supple
190 P. 315 (Oregon Supreme Court, 1920)
Multnomah County v. Standard Am. Dredging Co.
180 P. 508 (Oregon Supreme Court, 1919)
Manley v. City of Marshfield
172 P. 488 (Oregon Supreme Court, 1918)
Seaweard v. First Nat. Bank
165 P. 232 (Oregon Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
164 P. 729, 84 Or. 205, 1917 Ore. LEXIS 225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hayden-v-city-of-astoria-or-1917.