Boyd v. Bargagliotti

107 P. 150, 12 Cal. App. 228, 1909 Cal. App. LEXIS 20
CourtCalifornia Court of Appeal
DecidedDecember 17, 1909
DocketCiv. No. 632.
StatusPublished
Cited by13 cases

This text of 107 P. 150 (Boyd v. Bargagliotti) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boyd v. Bargagliotti, 107 P. 150, 12 Cal. App. 228, 1909 Cal. App. LEXIS 20 (Cal. Ct. App. 1909).

Opinion

HART, J.

By the terms of a certain contract entered into by and between the parties on the seventeenth day of September, 1906, the plaintiff and one J. L. Hughes agreed to construct for the appellant a bridge across Russian river, near the town of Pieta, in Mendocino county, for the sum of $575. Said contract, although made on the seventeenth day of Sep *230 tember, 1906, was not signed by the parties until the thirteenth day of October of said year. By the contract, however, the defendant agreed to furnish all the materials with which said bridge was to be built, and to place the same on the bridge site, where they would be accessible to the builders. The parties of the second part (plaintiff and Hughes) covenanted to complete the erection of said bridge “within sixty working days from the date hereof.” It was stipulated on the part of the defendant that he would pay Boyd and Hughes “twenty-five per cent of said $575 when fifty per cent of said work shall have been completed and the remainder of said' sum, $575, at the completion of said work.” The contract further contained the following clause: “And for the true and faithful performance of all and every of the covenants and agreements above mentioned, the parties to these presents covenant and agree each with the other that the sum of three hundred dollars ($300) gold coin of said United States, as fixed, settled, and liquidated damages shall be paid to the other by the failing party, if such there be. ’ ’ On November 26, 1906, the defendant made a payment to the plaintiff and Hughes of the sum of $200 on the contract price.

The bridge was not completed within the time stipulated in the contract, and a controversy arose between the parties upon the question whether the contractors had performed their work according to their agreement. This led to an agreement on the part of all the parties to submit the question upon which the differences between them rested to the determination of two disinterested persons, to be selected by the parties—one by the contractors and the other by the defendant. Accordingly, two persons were selected to arbitrate and decide the controversy, and, in furtherance of the agreement to arbitrate, they heard the statements oí the parties to the contract, examined the contract and the specifications and inspected the bridge and finally rendered the following decision or award: “We find that said bridge is not completed in accordance with the written contract, in so far as that the railing is not in place. One strut is not in place. Three cross-rods are not in place. Bracing between piling of center pier is not in place. As far as the concrete work is concerned, the preponderance of evidence is in favor of the contractor, and we must so hold. The time limit of the written contract certainly *231 has expired, and no donbt the owner has been injured thereby. But we will not assess damages thereon, provided the contractor without unnecessary delay completes said structure. Provided, further, that under all the circumstances, contractor should devote at least five days’ actual time of a good mechanic, to assist the owner in completing the approaches to said bridge. If the contractor does complete said structure, fully and in accordance with each and every stipulation herein contained, then, it is our judgment, that the contractor shall be entitled to the compensation, as it is contained in the original contract.”

The submission of the controversy to arbitration was not in writing, and it is not pretended, and obviously it could not be, that the arbitration herein mentioned is the proceeding authorized by sections 1281 to 1290, inclusive, of the Code of Civil Procedure.

In February, 1907, however, the bridge was carried away by the force of the high waters of Russian river, and whether the contractors completed the bridge according to the terms of their agreement, or, if they did, whether their default in so completing it within the time prescribed by the contract was excused because of the conduct of the defendant, constitute the principal propositions in the case and from which arise all the legal points upon which appellant asks for a reversal.

The defendant claims that the plaintiff and Hughes failed to complete the bridge in accordance with the stipulations of the contract, and upon such claim refused to pay to the contractors the balance which they claimed was due them under said contract.

The complaint contains several distinct counts, all, with the exception of one, being pleaded1 in the form of a general assumpsit, to wit: For “lumber and material, and work and labor and money laid out and expended, ’ ’ by the plaintiff, in the sum of $226.70; 2. For “labor performed and for moneys laid out and expended by said plaintiff and said Hughes for said defendant,” of the value of $46.05; 3. The balance due under the terms of the contract, to wit, the sum of $375.

The first and second counts are upon a quantum meruit. It may here be stated that, under an oral agreement made between the parties subsequently to the execution of the writ *232 ten contract, there were some deviations in the erection of the bridge from the original specifications, and hence the plaintiff not only declared upon the contract but also counted upon the unpaid balance thereunder in the form of a common count, or in indebitatus assumpsit. The complaint further pleads an assignment to plaintiff by Hughes of all his right to and interest in the claims pleaded in the complaint.

The answer denies each and all the material allegations qf the complaint, and, furthermore, and in addition to general damages, sets up a number of counterclaims—one in the nature of damages for loss of lumber alleged to have been sustained by the defendant through the negligence of plaintiff and Hughes, and others, for the reasonable value of the use of defendant’s tools and implements; for rent and occupation of a house and barn while the bridge was in process of construction; for labor performed for plaintiff and Hughes “at their special instance and request”; for wines and vegetables furnished to the said contractors at their request, and for the alleged liquidated damages provided for in the contract for negligently failing to complete the contract within the stipulated time. The answer, moreover, pleads the award of said arbitrators as a defense and also in abatement of the action.

The prayer of the answer is for affirmative relief by way of general damages, liquidated damages and for a sum on account of the other claims alleged in said answer to be due defendant.

The defendant also filed a cross-complaint making Hughes a party thereto, wherein the contract between the parties is pleaded, failure of the contractors through inexcusable negligence to complete the bridge is alleged and general damages,, in addition to those fixed by the contract, pleaded and prayed for.

Boyd and Hughes answered the cross-complaint, denying each and all of the material allegations thereof.

The court found in favor of Boyd and Hughes upon -all vital points, and accordingly rendered and entered judgment in favor of Boyd for the sum of $562.75, and in favor of Hughes, as defendant to the cross-complaint, for costs. This appeal is from said judgment and the order of the court denying Bargagliotti’s motion for a new trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trollope v. Jeffries
55 Cal. App. 3d 816 (California Court of Appeal, 1976)
Mayo v. Pacific Project Consultants, Inc.
1 Cal. App. 3d 1013 (California Court of Appeal, 1969)
Lesser Towers, Inc. v. Roscoe-Ajax Construction Co.
271 Cal. App. 2d 675 (California Court of Appeal, 1969)
Ely v. Bottini
179 Cal. App. 2d 287 (California Court of Appeal, 1960)
Ulene v. Murray Millman of California, Inc.
346 P.2d 494 (California Court of Appeal, 1959)
United States Plywood Corp. v. Hudson Lumber Co.
269 P.2d 93 (California Court of Appeal, 1954)
Miller v. McLaglen
186 P.2d 48 (California Court of Appeal, 1947)
Aldrich v. Aldrich
260 Ill. App. 333 (Appellate Court of Illinois, 1931)
Miller v. Childers
1924 OK 675 (Supreme Court of Oklahoma, 1924)
Sessions v. Pacific Improvement Co.
206 P. 653 (California Court of Appeal, 1922)
Hayden v. City of Astoria
164 P. 729 (Oregon Supreme Court, 1917)
Humboldt County v. Ward Bros.
145 N.W. 49 (Supreme Court of Iowa, 1914)
Naylor v. Adams
115 P. 335 (California Court of Appeal, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
107 P. 150, 12 Cal. App. 228, 1909 Cal. App. LEXIS 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boyd-v-bargagliotti-calctapp-1909.