Lesser Towers, Inc. v. Roscoe-Ajax Construction Co.

271 Cal. App. 2d 675, 77 Cal. Rptr. 100, 1969 Cal. App. LEXIS 2426
CourtCalifornia Court of Appeal
DecidedApril 11, 1969
DocketCiv. 32023
StatusPublished
Cited by50 cases

This text of 271 Cal. App. 2d 675 (Lesser Towers, Inc. v. Roscoe-Ajax Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lesser Towers, Inc. v. Roscoe-Ajax Construction Co., 271 Cal. App. 2d 675, 77 Cal. Rptr. 100, 1969 Cal. App. LEXIS 2426 (Cal. Ct. App. 1969).

Opinion

AISO, J

This case illustrates that unfortunately arbitration is not always a simple, expeditious, or inexpensive method of adjudicating commercial controversies. 1

*678 Roscoe-Ajax Construction Co., Inc., a Maryland corporation (“Roscoe-Ajax”), appeals from the judgment entered December 14, 1966, confirming an arbitration award in favor of the respondent Lesser Towers, Inc., a California corporation (“Lesser”), in two consolidated cases 2 and from the order of November 15, 1966, confirming the award and denying a motion to vacate the award. 3

The judgment ordered, adjudged and decreed, inter alia, that: (1) the arbitrators’ award be confirmed in all respects; (2) Lesser recover from Roscoe-Ajax $884,947, together with $25,795.92 interest, thus totalling $910,742.92; (3) the claims and counterclaims filed by Roscoe-Ajax against Lesser in the arbitration be dismissed and Roscoe-Ajax take nothing by reason thereof; (4) Roscoe-Ajax is not entitled to any liens on the property; (5) Roscoe-Ajax clear the property involved of all liens, outstanding or thereafter recorded, for work, labor, services, or materials furnished to Roscoe-Ajax; (6) (reserved an item for future arbitration, which does not concern us); and (7) Lesser recover $6,031.75 costs from Roscoe-Ajax.

L

On this appeal, Roscoe-Ajax contends that: (1) the arbitrators in deciding who terminated the contract and what damages flowed therefrom exceeded their powers because Roscoe-Ajax did not agree to arbitrate those issues, and (2) the award should be vacated because the arbitrators committed “gross errors.” After having considered carefully the claimed errors, we conclude that the judgment confirming the award should be affirmed.

*679 II.

Lesser, as owner, and Roscoe-Ajax, as contractor, entered into a written agreement on October 25, 1961, for the construction of a 20-story apartment in the Wilshire District of Los Angeles for a guaranteed maximum cost of $5,350,380. Roscoe-Ajax’s fee was 5 percent of the cost. Should the actual cost exceed that guaranteed maximum, Roscoe-Ajax was to absorb the excess. However, for certain kinds of changes or delays attributable to Lesser, the maximum guaranteed cost was to be increased to compensate Roscoe-Ajax for increased costs resulting from such changes or delays. Plans and specifications were to be provided by Lesser through the architectural firm of Daniel, Mann, Johnson and Mendenhall. Roscoe-Ajax was to execute its work in conformity with the architect’s drawings and instructions. It was to “do no work without proper drawings and instructions. ’ ’

Roscoe-Ajax undertook to complete construction by “no later than 18 months following the notice to proceed,” which it received on December 21, 1961. Barring intervening excusable delays, completion was scheduled for June 20,1963.

Controversies arose between Lesser and Roscoe-Ajax shortly after construction was begun. Roscoe-Ajax claimed that Lesser decided upon making extensive changes in the lay-out of the kitchens and bathrooms, heating and air conditioning systems, fireproofing, cabinet work, fixtures, and electrical work. It claimed further that the architect did not provide proper specifications and drawings to enable it to proceed with the construction through its subcontractors. Lesser charged Roscoe-Ajax with refusal to sign change requests needed for obtaining necessary Federal Housing Administration approvals. Roscoe-Ajax contended that it was entitled to an increase in the guaranteed maximum cost because of the changes which necessitated long delays. Roscoe-Ajax also claimed that Lesser’s stop order compelling it to cease application of fireproofing to the structural frame prevented completion of its work. At any rate the work came to a virtual standstill in April 1963. 4

*680 On July 20, 1964, Roscoe-Ajax walked off the job and refused to further perforin under the construction agreement. It had up to that time completed less than 40 percent of its work contracted, but had demanded and received payment of $3,316,913.29, approximating 60 percent of the contract price.

Other relevant facts will be mentioned when they become pertinent to the discussion which follows.

III.

Consideration of some of the arguments advanced by the parties necessitates a cognizance of the procedural steps, taken by the parties and the court below, which culminated in the arbitration award and its confirmation.

On June 19, 1964, Lesser by letter, invoking Article 39 of the General Conditions 5 of the contract, requested the architect to determine seven specific items of dispute. It read in part:

“We have a number of claims against [Roscoe-Ajax], Said contractor, on the other hand, made certain claims against us.
“We desire to proceed to obtain, in accordance with Article 39, a determination of the following specific claims against the contractor :“
“6. The owner desires you to direct the Contractor to sign Change Request No. 19, dated June 4, 1964 ; Change Request No. 21, dated June 4, 1964; and Change Request No. 22, dated June 4, 1964. The Contractor has failed and refused to sign said Change Requests and has failed and refused to do the work contemplated thereof [sic],
“7. In addition to the foregoing claims, the owner calls upon the Architect to give an interpretation of the contract documents in the following particulars:
‘‘The Contractor claims that Article 26 of the General Conditions of the contract for the construction of the building is ineffective and is not binding upon the Contractor because the Contractor claims said Article 26 to be in conflict with Article V of the contract itself. In this regard, the Contractor asserts *681 that Article 26 of the General Conditions is inconsistent with Article V of the contract, and that therefore, says the Contractor, Article V must govern. The owner contends contrariwise; the owner contends that Article 26 of the General Conditions must be read together with Article V, and that, when read together, there is no inconsistency between the two.
“The owner desires your interpretation of the contracts in the regard set forth hereinabove. ’ ’ 6

The refusal of Roscoe-Ajax to sign the change requests enumerated in paragraph 6 was an integral part of the dispute between the parties; approval of the contractor was needed before the changes could be submitted to the Federal Housing Administration for approval as required by Article IX of the Agreement. Change Eequest No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Felisilda v. FCA US LLC
California Court of Appeal, 2020
Dornbirer v. Kaiser Foundation Health Plan, Inc.
166 Cal. App. 4th 831 (California Court of Appeal, 2008)
Casden Park La Brea Retail v. Ross Dress for Less, Inc.
75 Cal. Rptr. 3d 763 (California Court of Appeal, 2008)
Vivid Video, Inc. v. Playboy Entertainment Group, Inc.
54 Cal. Rptr. 3d 232 (California Court of Appeal, 2007)
Siegel v. Prudential Ins. Co. of America
79 Cal. Rptr. 2d 726 (California Court of Appeal, 1998)
Advanced Micro Devices, Inc. v. Intel Corp.
885 P.2d 994 (California Supreme Court, 1994)
Pacific Gas & Electric Co. v. Superior Court
15 Cal. App. 4th 576 (California Court of Appeal, 1993)
JKL Components Corp. v. Insul-Reps, Inc.
596 N.E.2d 945 (Indiana Court of Appeals, 1992)
Southern California Rapid Transit District v. United Transportation Union
5 Cal. App. 4th 416 (California Court of Appeal, 1992)
Melchor Investment Co. v. Rolm Systems
3 Cal. App. 4th 587 (California Court of Appeal, 1992)
U. FIREFIGHTERS OF LOS ANGELES v. City of LA
231 Cal. App. 3d 1576 (California Court of Appeal, 1991)
Estate of Cole v. Commissioner
1989 T.C. Memo. 623 (U.S. Tax Court, 1989)
Summit Industrial Equipment, Inc. v. Koll/Wells Bay Area
186 Cal. App. 3d 309 (California Court of Appeal, 1986)
Woodard v. Southern California Permanente Medical Group
171 Cal. App. 3d 656 (California Court of Appeal, 1985)
Blanton v. Womancare, Inc.
696 P.2d 645 (California Supreme Court, 1985)
United Food & Commercial Workers Union v. Clougherty Packing Co.
154 Cal. App. 3d 282 (California Court of Appeal, 1984)
Int'l Film Investors v. Arbitration Tribunal
152 Cal. App. 3d 699 (California Court of Appeal, 1984)
International Film Investors v. Arbitration Tribunal of Directors Guild
152 Cal. App. 3d 699 (California Court of Appeal, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
271 Cal. App. 2d 675, 77 Cal. Rptr. 100, 1969 Cal. App. LEXIS 2426, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lesser-towers-inc-v-roscoe-ajax-construction-co-calctapp-1969.