Lang v. Badger

320 P.2d 906, 157 Cal. App. 2d 345, 1958 Cal. App. LEXIS 2246
CourtCalifornia Court of Appeal
DecidedFebruary 3, 1958
DocketCiv. 22427
StatusPublished
Cited by6 cases

This text of 320 P.2d 906 (Lang v. Badger) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lang v. Badger, 320 P.2d 906, 157 Cal. App. 2d 345, 1958 Cal. App. LEXIS 2246 (Cal. Ct. App. 1958).

Opinion

HERNDON, J. pro tem. *

This appeal is taken from an order confirming an arbitration award. Appellants challenge the validity of the award upon two grounds: (1) That the arbitrators failed to give notice of their hearings to the parties or their attorneys; (2) that the arbitrators exceeded their powers in setting aside a release given to appellants by respondent.

The factual issues were submitted to the trial court upon affidavits. Our review, therefore, is governed by the rule that the affidavits favoring the contentions of the prevailing party establish not only the facts therein expressly stated, but also all facts which reasonably may be inferred therefrom. And when the evidence is conflicting it will be presumed that the trial court found every fact necessary to support its order that the evidence would justify. (Griffith Co. v. San Diego College for Women, 45 Cal.2d 501, 507, 508 [289 P.2d 476, 47 A.L.R.2d 1349].)

Viewed in this light, the record before us furnishes ample *347 support for the implied findings of the trial court upon which the order under review presumably was made. We shall state the operative facts chronologically.

The arbitration was conducted pursuant to the provisions of a building contract and a subsequent stipulation executed by the attorneys for the respective parties. The contract, dated September 14, 1953, required respondent Badger as contractor to make certain alterations and additions to appellants’ residence. The contract provided that “as between the parties hereto all questions as to the rights and obligations arising under the terms of the contract, and the plans and specifications are subject to arbitration.”

On February 6, 1954, after he had completed the work of improvement, respondent submitted to appellants his statement showing a balance due him of $6,004.66. Appellants disputed the correctness of this statement. After discussion, the parties agreed upon a compromise figure of $5,773.66. Respondent accepted payment of this amount and over his signature endorsed the statement “Paid in full.”

Shortly thereafter appellants asserted a claim that respondent had deviated from the plans and specifications and that some of the construction was defective. Respondent contractor then made a counterdemand contending, among other things, that his acceptance of the compromise settlement had been induced by fraud. On May 27, 1954, respondent’s attorney addressed to counsel for appellants a letter which has a significant bearing upon appellants’ claim that the award of the arbitrators was in excess of their powers and beyond the agreed scope of the submission. This letter refers to earlier exchanges of correspondence between the attorneys relative to this dispute and contains, among others, the following statements:

“At the time of the settlement and release under date of February 6, 1954, to which you refer, Mr. Badger accepted a considerable sum less than was due him, not only in settlement of his claims but in settlement of any claims which Dr. Lang might have. Either that settlement stands as to both parties, or the whole matter is again opened up, and Mr. Badger’s claims are again subject to negotiation. My letter of May 3d, to which you refer, was only in response to your letter of April 29th, and the offer to arbitrate at that time was only upon condition that the whole matter be arbitrated. If Dr. Lang desires to stand upon the settlement of February 6th, we will likewise stand upon the settlement.”

*348 The events immediately following the quoted letter of May 27, 1954, are not fully revealed by the record, but it does appear that prior to June 28, 1955, appellants had filed suit against respondent in the Long Beach Municipal Court and that proceedings were pending in the superior court seeking confirmation of an earlier arbitration award which is not involved on this appeal. On June 28, 1955, the attorneys for the parties entered into a formal stipulation: “. . . that any and all disputes which have arisen by reason of that certain building contract dated September 14, 1953, will be submitted to arbitration in accordance with said building contract, the procedures to be followed at said arbitration hearing to be formulated by undersigned. ...” The stipulation further provided that the pending court proceedings would be held in abeyance until the decision of the board of arbitrators had become final. Thereafter appellants designated a Mr. Frank and respondent designated a Mr. Skelton as arbitrators. Both were duly licensed contractors. During September, 1955, detailed statements of the respective contentions and claims of the parties were prepared by their attorneys and submitted to the two arbitrators.

According to the affidavit of respondent’s attorney, E. 0. Leake, it was orally agreed between him and George A. Hart, Jr., attorney for appellants, that the arbitrators should go forward with the arbitration in accordance with their own methods of procedure and that the arbitrators should interview the parties and make their investigations without any participation on the part of the lawyers. This understanding was confirmed by Mr. Leake’s letter addressed to the firm of Ball, Hunt and Hart, under date of October 5, 1955, reading in part as follows:

“As I stated to Mr. Hart over the telephone, I see no particular reason why we should participate as attorneys in this hearing before the arbitrators. The various contentions of the parties are set forth in the letters above mentioned and the arbitrators can secure such evidence of the parties and witnesses as they desire and allow in whole or in part, or disallow, the items claimed. The arbitrators being practical contractors should have no difficulty deciding this matter. ’ ’

' The affidavits of the two arbitrators indicate that between October 5,1955, and March 15,1956, they pursued their investigations, held hearings and received the evidence offered by the respective parties. By letter dated March 16, 1956, Mr. Frank, the arbitrator designated by appellants, informed Mr. Hart that as a result of a meeting of the two arbitrators held *349 on the preceding day, such differences of opinion had arisen between them as to require the appointment of a third arbitrator.

Under date of March 19, 1956, a letter signed by the attorneys for both parties was addressed to the two arbitrators advising them that in the event of their inability to agree they should appoint a third arbitrator and that the decision of two would be final. The concluding sentence of the letter read as follows: “Accordingly, you two should appoint a third arbitrator and the board of arbitrators so composed should render its decision, taking any additional evidence, or not, as you may deem advisable or necessary to render a fair decision in the matter.”

Promptly thereafter B. R. McCollum, a licensed contractor, was appointed the third arbitrator. The affidavit of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

California State Council of Carpenters v. Superior Court
11 Cal. App. 3d 144 (California Court of Appeal, 1970)
Lesser Towers, Inc. v. Roscoe-Ajax Construction Co.
271 Cal. App. 2d 675 (California Court of Appeal, 1969)
Posner v. Grunwald-Marx, Inc.
363 P.2d 313 (California Supreme Court, 1961)
Goossen v. Adair
185 Cal. App. 2d 810 (California Court of Appeal, 1960)
Firestone Tire & Rubber Co. v. United Rubber Workers
335 P.2d 990 (California Court of Appeal, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
320 P.2d 906, 157 Cal. App. 2d 345, 1958 Cal. App. LEXIS 2246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lang-v-badger-calctapp-1958.