Castagnino v. Balletta

23 P. 127, 82 Cal. 250, 1889 Cal. LEXIS 842
California Supreme Court·Decided December 30, 1889·No. No. 11713·Published·Cited by 51 cases

Opinion

Thokntox, J.

This action was originally brought to foreclose a mechanic’s lien for $1,395.50 on a block of buildings in the city of San Francisco. The buildings were erected by plaintiff for defendants under a written contract, which provided that plaintiff should furnish all the materials, and do the work according to plans and specifications made by George Bordwell, architect, and receive therefor the sum of $9,800, payable in installments as the work progressed, the last payment to be made “when the houses shall be completed, each in all its parts, and accepted by the architect.” The $1,395.50 consisted of an unpaid balance of the contract price and $375 alleged to be due for extra work and materials. The case was tried, and judgment rendered for plaintiff. An appeal was taken by defendants from the judgment, and an order denying them a new trial, and the judgment and order were reversed on authority of Loup v. Railroad Co., 63 Cal. 97. The case came on again for trial, and the plaintiff was allowed, over the objections of defendants, to file an amended complaint in indebitatus assumpsit. It contained three counts. The first alleged an indebtedness from defendants to plaintiff of $1,020.50 [254]*254for work and labor done and materials furnished in the erection of a block of buildings in the city of San Francisco; the second alleged an indebtedness of $270 for extra work done and materials furnished in the erection of the said block of buildings; and the third alleged an indebtedness of $105 for putting a door in defendants’ building, and constructing a sidewalk in front thereof, at their special instance and request. ■ The prayer was for judgment for $1,395.50, the aggregate of these amounts, with interest and costs.

The defendants, by their answer, denied that they were indebted to plaintiff in the sum of money named in the complaint, or in any sums or sum whatever, and to the first two counts they pleaded the statute of limitations. They then alleged that the labor and materials sued for, except the last item of $105, were furnished under a -written contract, which was executed by the parties on the 26th of April, 1876, and a copy of which was set forth and made a part of the answer. They further alleged that they complied with all the conditions of the contract on their part, and paid plaintiff during the progress of the work the sum of $9,104, but that plaintiff failed to comply with the conditions of the contract on his part; that he omitted to put in the buildings many things required by the contract and specifications, and that the value of the articles and work omitted was $450; that the buildings were not completed within the time named in the contract, and defendants -were damaged thereby in the sum of $900; that the foundation was not put down to solid ground, and by reason thereof the buildings settled, to the damage of the same in the sum of over $1,000. The prayer was for judgment against the plaintiff for $1,500, and costs of suit. The case was tried before a jury, and the verdict and judgment were for plaintiff. Defendants moved for a new trial, which was denied, and have appealed from the judgment and order.

When the trial commenced, the plaintiff first intro[255]*255duced in evidence the building contract, a copy of which is set out in the answer and the specifications referred to therein. He then introduced evidence showing that the terms of the contract were subsequently changed in certain respects by agreement of the parties; that he proceeded to construct and complete the buildings according to the plans and specifications; that he performed certain extra work which was provided for by an indorsement on the contract, and for which he was to receive two hundred and seventy dollars; that he also placed an extra door in one of the houses, by direction of the architect, at a cost of fifteen dollars, and by an agreement with defendants laid a new sidewalk in front of the building, for which they were to pay him ninety dollars; that he was prevented by defendants from completing the whole work at the time named in the contract; that after it was in fact completed, the architect suggested certain items of work which he wished to have done, saying that when they were done to his satisfaction he would accept the buildings as complete, and that he (plaintiff) did the suggested work so far as it was called for by the contract; that a few days afterward, at a meeting of the plaintiff, defendant Balletta, and the architect, the architect said he was satisfied with the building and would accept it; that at this meeting the architect also said to plaintiff’s attorney, who was present, that “ he [plaintiff] had a hard contract, anyhow, and that he was glad that he had finished it up, and that he had advised him not to take the contract in the first place; that he knew he lost a great deal of money on it; he said he knew he lost not less than two thousand dollars on the contract; he was glad it was finished”; that it was then arranged that another meeting of the parties should be held at the architect’s office to figure up the amount due plaintiff and settle the whole matter; and that in pursuance of this arrangement the parties met, the amount due plaintiff was [256]*256figured up and agreed to be, including the extra work, $1,395.50, and that after that the architect called plaintiff’s attorney aside “ and spoke in a low tone and said that he wanted plaintiff to pay him one hundred dollars; that he had been to a great deal of trouble in superintending the buildings, and that the amount paid him by defendant for his services was not sufficient”; that plaintiff, on being informed of this demand, refused to pay it, and the architect then said that he would charge plaintiff for lost time, and would not receive the buildings; that defendant was present with a bag of money on the table, ready to pay plaintiff, if the architect had not stopped him from doing so.

The defendants objected to the admission in evidence of the contract and specifications, on the ground that they showed an entirely different contract from the one set up in the complaint, and were therefore irrelevant and immaterial; and to all the evidence showing that the terms of the contract were varied and changed, and to all evidence offered to excuse or explain the delay in the completion of the contract according to its terms, on the ground that it was incompetent, and inadmissible under the pleadings. They also moved for a nonsuit on similar grounds. The objections and motion were all overruled, and exceptions reserved.

The above statement, which we find to be correct, is taken from the opinion of Commissioner Belcher, filed July 1, 1889, after which a rehearing was granted.

The objection to the permission of the court below, granted plaintiff, to file an amended complaint, on which the cause was tried, is without merit. There is no change of the cause of action which inhibits the court from allowing the amendment. A complaint in an action to enforce a mechanic’s lien in which the special contract between contractor and owner was stated can be changed by amendment into an action on the contract, which contract may be counted on specially; or the common [257]*257counts in assumpsit, in certain cases, which will be hereafter pointed out, may be made use of by the pleader.

That the common counts may be resorted to in actions on contracts, within certain defined limits, has been too long and two -well settled in this state to be the subject of further debate or controversy.

Free access — add to your briefcase to read the full text and ask questions with AI

Castagnino v. Balletta, 23 P. 127, 82 Cal. 250, 1889 Cal. LEXIS 842 (Cal. 1889).

23 P. 127 (Castagnino v. Balletta) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Frank X. Ruiz Avionics v. Grossman CA5
California Court of Appeal, 2025
Montano v. Hernandez CA2/7
California Court of Appeal, 2013
Truestone, Inc. v. Simi West Industrial Park II
163 Cal. App. 3d 715 (California Court of Appeal, 1984)
Moya v. Northrup
10 Cal. App. 3d 276 (California Court of Appeal, 1970)
Overland Machined Products, Inc. v. Swingline, Inc.
263 Cal. App. 2d 642 (California Court of Appeal, 1968)
Benson Elec. Co. v. Hale Bros. Assoc., Inc.
246 Cal. App. 2d 686 (California Court of Appeal, 1966)
Higgins v. Desert Braemar, Inc.
219 Cal. App. 2d 744 (California Court of Appeal, 1963)
Emo v. Massae
200 Cal. App. 2d 473 (California Court of Appeal, 1962)
Rains v. Arnett
189 Cal. App. 2d 337 (California Court of Appeal, 1961)
Carnation Co. v. Marcevich
186 Cal. App. 2d 618 (California Court of Appeal, 1960)
Ben-Hur Manufacturing Co. v. Empire Factors
181 Cal. App. 2d 123 (California Court of Appeal, 1960)
Vick v. Grasser
338 P.2d 223 (California Court of Appeal, 1959)
Ferro v. Citizens National Trust & Savings Bank
282 P.2d 849 (California Supreme Court, 1955)
Oliver v. Campbell
273 P.2d 15 (California Supreme Court, 1954)
Kurland v. Simmons
271 P.2d 553 (California Court of Appeal, 1954)
Roseleaf Corp. v. Radis
264 P.2d 964 (California Court of Appeal, 1953)
Weitzenkorn v. Lesser
256 P.2d 947 (California Supreme Court, 1953)
Haggerty v. Warner
252 P.2d 373 (California Court of Appeal, 1953)
King v. San Jose Pacific Building & Loan Ass'n
107 P.2d 442 (California Court of Appeal, 1940)