Benson Elec. Co. v. Hale Bros. Assoc., Inc.

246 Cal. App. 2d 686, 55 Cal. Rptr. 73, 1966 Cal. App. LEXIS 1072
CourtCalifornia Court of Appeal
DecidedNovember 29, 1966
DocketCiv. 22644
StatusPublished
Cited by19 cases

This text of 246 Cal. App. 2d 686 (Benson Elec. Co. v. Hale Bros. Assoc., Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benson Elec. Co. v. Hale Bros. Assoc., Inc., 246 Cal. App. 2d 686, 55 Cal. Rptr. 73, 1966 Cal. App. LEXIS 1072 (Cal. Ct. App. 1966).

Opinion

AGEE, J.

Defendants appeal from a judgment of the trial court foreclosing a mechanic’s lien in favor of plaintiff Benson Electric Company (hereafter Benson) in the amount of $4,534.05 and intervener General Electric Company in the amount of $10,965.95, or a total sum of $15,500. Personal judgment in like ratio was entered against defendant Millbrae Bowling Corporation (hereafter Millbrae) alone.

The subject property is located on El Camino Real in Mill-brae, on it now standing the completed King’s Bowl. In 1960, the then unimproved realty was owned in fee by defendant Hale Brothers Associates (hereafter Hales), subject to the leasehold interest of Millbrae, a corporation in which Harold *689 Dobbs was the sole stockholder. In 1963, Dobbs acquired the fee from Hales, still subject to the leasehold of Millbrae.

Millbrae began construction of King’s Bowl in 1960. Robert McLean was a licensed contractor and proficient in this sort of construction. However, he was unable to secure the necessary-bonding to contract directly with Millbrae as its general contractor.

Consequently, Millbrae engaged McLean as its general superintendent at a salary of $1,000 per month, month-to-month. He supervised general construction work directly, but the general construction workers were employed by Millbrae. Although he negotiated with other contractors for the project, he did not contract with any of them.

Rather, such contracting was done on behalf of Millbrae by Ferdinand Masberg, its fully authorized agent. Benson entered into one such written contract with Millbrae on May 2, 1960. Benson was to install the electrical system in the bowling alley according to specifications furnished by Millbrae.

Section 1193.1, subdivision (c), of the Code of Civil Procedure provides: ‘‘ The owner shall within 10 days after the completion of the work of improvement file for record a notice of completion. ... If such notice be so filed, then, . . . every original contractor must within 60 days after the date of filing for record such notice, and every person, other than an original contractor, claiming the benefit of this chapter must within 30 days after the date of filing for record such notice, file for record his claim of lien. ’ ’

The record amply shows that Benson contracted directly with defendant Millbrae, that Millbrae was the lessee, and that Hales was the owner-lessor. Hales filed notice of completion on September 8, 1960. Benson filed claim of lien on November 7, 1960, which was within 60 days of the notice of completion.

The issue is whether one who contracts directly with a lessee who is in command of construction is an “original contractor” within the meaning of the above section. Appellants contend Benson had only 30 days to file claim of lien.

The parties have based their respective arguments on the assumption that an “original contractor” must have a direct contract with the owner. Thus, they focus on whether a lessee is an owner within the meaning of section 1193.1, subdivision (c).

However, whether a lien claimant is a subcontractor or an original contractor does not depend upon ownership interest, but rather on the rank of the particular contract in ques *690 tion in relation to all the construction contracts concerning the project. The issue is the relationship of all the contractors inter sese.

Unless some adverse possessor initiates the project, it must be started by a person with some estate in the property, whether as fee owner, life tenant, remainderman, lessee, or whatever. The interest of such person becomes important only when determining the extent of the lien. 1

In Peterson v. Freiermuth (1911) 17 Cal.App. 609 [121 P. 299], the plaintiff contracted with a lessee to extensively remodel the building on the leasehold for a price in excess of $5,000. The court affirmed a judgment for the defendant-lessor, entered after an order sustaining a demurrer. At that time, the code required any contract for a sum over $1,000 to be in writing and filed with the county recorder, and this was not done. Such requirement did not apply if the lien claimant was a materialman rather than a contractor. The court held there could “be no room for doubting that the plaintiff was an original contractor.’’ (P. 614; italics supplied.)

In Hihn-Hammond, Lumber Co. v. Elsom (1915) 171 Cal. 570, 574 [154 P. 12, Ann.Cas. 1917C 798], the court offered this analysis: “Section 1194 [as then enacted] divides the liens which can be asserted against property under the mechanic’s lien law into four classes, to wit, laborers, materialmen, subcontractors, and original contractors. The meaning of the term ‘subcontractors,’ as there used, must be determined by reference to this classification and to the subject to which it relates. The original contractor is the person who agrees with the owner to construct a building on his property. Those who perform labor in the construction of the building come within the first class, as laborers. Persons who merely furnish material to the contractors to be used, and which are used, in the construction of the building come within the second class, as materialmen. The term ‘subcontractor’ embraces all persons who agree with the original contractor to furnish the material and construct for him on the premises some part of the structure which the original contractor has agreed to erect for the owner. ’ ’

Thus, in the Peterson case, when deciding if a particular lien claimant was or was not a materialman, the court said:

*691 “In such, cases [if the claimant furnishes both extensive labor and material] the persons who furnish materials cease to be materialmen and become original contractors or subcontractors as the facts of the case may be.” (Peterson v. Freiermuth, supra, 17 Gal.App. at p. 614; italics supplied.) And that a lien claimant contracts with a lessee rather than a fee owner was not noted as a material fact on this issue.

The two cases above cited, as well as many other decisions containing a definition of “materialman,” have been discussed recently in Theisen v. County of Los Angeles (1960) 54 Cal.2d 170,180-182, footnotes 5 and 6 [5 Cal.Rptr. 161, 352 P.2d 529]. An examination of these cases discloses that the issue was either materialman versus contractor or materialman versus subcontractor, and further that whether the court used the term “original contractor” or “subcontractor” depended factually on whether the lien claimant undertook the construction directly, or whether he undertook to perform a portion of the work which the party with whom he contracts had himself contracted to perform for another. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swan Engineering v. Tuscan Ridge Associates CA3
California Court of Appeal, 2025
Restoration Management Co. v. Lee CA1/2
California Court of Appeal, 2025
Kim v. Lee CA2/7
California Court of Appeal, 2021
Silbermann v. Shangri-La Construction CA2/7
California Court of Appeal, 2020
Chu v. Gong CA2/8
California Court of Appeal, 2014
Montano v. Hernandez CA2/7
California Court of Appeal, 2013
San Diego Metro. Transit Dev. Bd. v. Cushman
53 Cal. App. 4th 918 (California Court of Appeal, 1997)
Union Asphalt, Inc. v. Planet Insurance
21 Cal. App. 4th 1762 (California Court of Appeal, 1994)
Vaughn Materials Co. v. Security Pacific National Bank
170 Cal. App. 3d 908 (California Court of Appeal, 1985)
People v. Southern Pacific Co.
139 Cal. App. 3d 627 (California Court of Appeal, 1983)
University Casework Systems, Inc. v. Superior Court
41 Cal. App. 3d 263 (California Court of Appeal, 1974)
Frank Pisano & Associates v. Taggart
29 Cal. App. 3d 1 (California Court of Appeal, 1972)
M. Arthur Gensler, Jr., & Associates, Inc. v. Larry Barrett, Inc.
499 P.2d 503 (California Supreme Court, 1972)
Schrader Iron Works, Inc. v. Lee
26 Cal. App. 3d 621 (California Court of Appeal, 1972)
Daugherty Co. v. Kimberly-Clark Corp.
14 Cal. App. 3d 151 (California Court of Appeal, 1971)
Scott, Blake & Wynne v. Summit Ridge Estates, Inc.
251 Cal. App. 2d 347 (California Court of Appeal, 1967)
MacOmber v. State of California
250 Cal. App. 2d 391 (California Court of Appeal, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
246 Cal. App. 2d 686, 55 Cal. Rptr. 73, 1966 Cal. App. LEXIS 1072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benson-elec-co-v-hale-bros-assoc-inc-calctapp-1966.